DBE Construction Report for LEAL CONSTRUCTION, INC.

 
 
Last Update: Wednesday, September 7, 2005
LEAL CONSTRUCTION, INC. Vendor #: 05145
PO BOX 157 DBE Certification Status: CERTIFIED
OLMITO, TX 78575 Expiration Date: 06/30/08
Phone: (956)542-4630 Fax: (956)542-5975
 
Let Date: 2001-02 County: CAMERON
CCSJ: 0039-07-185 District: PHARR
Project ID: MG 2001(257) Pct Complete: 97%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: WILLIAMS BROTHERS CONSTRUCTION CO., INC
 
Let Date: 2001-02 County: CAMERON
CCSJ: 0039-07-185 District: PHARR
Project ID: MG 2001(257) Pct Complete: 97%
CUF REV Results:   Sub Replaced: REPLACED
Commitment Amount: 0.00
Commitment Work: MANUF CONCRET
Prime Contractors: WILLIAMS BROTHERS CONSTRUCTION CO., INC
 
Let Date: 2002-07 County: ZAPATA
CCSJ: 0038-04-050 District: PHARR
Project ID: NH 2002(731) Pct Complete: 100%
Commitment Amount: 197,464.75
Commitment Work: CONC CURB & GUTTER, CONC GUTTER(VALLEY), TERM ANCHSECT, MBGF, REM MBGF, REM TERM ANCH SECT, SINGL GDRAIL TERM (MOVE & RESET
Prime Contractors: FOREMOST PAVING, INC
 
Let Date: 2002-11 County: KLEBERG
CCSJ: 1446-02-015 District: CORPUS CHRISTI
Project ID: STP 2003(18) Pct Complete: 87%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: HUNTER INDUSTRIES, LTD
 
Let Date: 2002-12 County: CAMERON
CCSJ: 0039-07-186 District: PHARR
Project ID: NH 2002(80) Pct Complete: 70%
Commitment Amount: 1,028,045.26
Commitment Work: RAIL (TY T201), (TYC201), (TY 203R), TERM ANCHOR MTL BEAM GD FENCE, REMOVE, TERM ANCHOR, SIGNA GDRAIL, CONC CURB & GUTTER, CURB RAMP & LANDIN
Prime Contractors: ZACHRY CONSTRUCTION CORPORATIO
 
Let Date: 2003-04 County: CAMERON
CCSJ: 0039-16-057 District: PHARR
Project ID: NH 2003(369) Pct Complete: 64%
Commitment Amount: 678,193.01
Commitment Work: DRVWYS, CONCRETE SIDEWALK, MTL BM GD FEN, REMOV METAL TERM, CHAIM LINK, QUADGD SYS, CURB RAM SINGLE GUARDRAI
Prime Contractors: WILLIAMS BROTHERS CONSTRUCTION CO., INC
 
Let Date: 2003-10 County: HIDALGO
CCSJ: 0255-08-091 District: PHARR
Project ID: MG 2003(689) Pct Complete: 76%
Commitment Amount: 658,399.05
Commitment Work: TERM ANCHOR SECT, MBGF, SINGLE GUARDRAIL TERM, REAC
Prime Contractors: BALLENGER CONSTRUCTION COMPAN
 
Let Date: 2004-02 County: HIDALGO
CCSJ: 0255-08-094 District: PHARR
Project ID: NH 2004(255) Pct Complete: 39%
Commitment Amount: 540,460.00
Commitment Work: RIPRAP, CURB & GUTTER, CONC CURB, DRVWYS, SIDEWALK RAMP AND LANDING
Prime Contractors: ZACHRY CONSTRUCTION CORPORATIO
 
Let Date: 2004-05 County: HIDALGO
CCSJ: 0921-02-101 District: PHARR
Project ID: STP 2002(180)TE Pct Complete: 75%
Commitment Amount: 494,699.90
Commitment Work: REMOC CONC RIPRAP, REMOV CONC SIDEWALK, RMV STB BS AND ASH, EXCAVATION, EMBANKMENT, EMBANK CHAI FLEX BASE RDWY DEL, LIME TREAT, RIPRAP
Prime Contractors: H2O CONSTRUCTION, INCORPORATE
 
Let Date: 2004-09 County: CAMERON
CCSJ: 0039-06-031 District: PHARR
Project ID: STP 2005(55) Pct Complete: 40%
Commitment Amount: 424,262.65
Commitment Work: CONC CURB AND GUTTER, DRVWYS, CONC SIDEWALKS CURB RAMP AND LANDIN
Prime Contractors: FOREMOST PAVING, INC
 
Let Date: 2004-09 County: CAMERON
CCSJ: 0039-19-042 District: PHARR
Project ID: MG 2004(548) Pct Complete: 15%
Commitment Amount: 0.00
Commitment Work:  
Prime Contractors: ZACHRY CONSTRUCTION CORPORATIO
 
Let Date: 2004-09 County: CAMERON
CCSJ: 0039-08-086 District: PHARR
Project ID: MG 2003(303) Pct Complete: 28%
Commitment Amount: 202,873.00
Commitment Work: TERM ANCHOR SECT (12), MTL BM GD FEN, REMOV BM GD FEN, QUADGUARD SYSTEM, SINGLE GD RL, REACT 35
Prime Contractors: BALLENGER CONSTRUCTION COMPAN
 
Let Date: 2004-10 County: HIDALGO
CCSJ: 0921-02-100 District: PHARR
Project ID: STP 2002(182)TE Pct Complete: 88%
Commitment Amount: 846,937.20
Commitment Work: PREP ROW,REM CONC,REM STB,EXCAV,EMBNK,TPSL,FL BS, LIME TRT,ASHP MATRL,FLUME,RE WALL,RIPRAP,RAIL,ADJ MNHL,PVC PIPE,CURB&GUTR,SDWL
Prime Contractors: H2O CONSTRUCTION, INCORPORATE
 
Let Date: 2004-11 County: HIDALGO
CCSJ: 1889-01-007 District: PHARR
Project ID: STP 2005(8) Pct Complete: 92%
Commitment Amount: 73,942.50
Commitment Work: DRVWYS, MBGF, REMOV TERM ANCHOR SECT, SINGLE GUARDRAIL TER
Prime Contractors: FOREMOST PAVING, INC
 
Let Date: 2005-05 County: HIDALGO
CCSJ: 0921-02-090 District: PHARR
Project ID: BOR 2001(592) Pct Complete: 0%
Commitment Amount: 119,754.40
Commitment Work: RC PIPE (CLIII 18" & 60"), INLET (COMP)(TYC
Prime Contractors: FOREMOST PAVING, INC
 
Let Date: 2005-06 County: CAMERON
CCSJ: 1425-03-042 District: PHARR
Project ID: STP 2004(189) Pct Complete: 0%
Commitment Amount: 25,570.20
Commitment Work: TERM ANCHOR SECT (12GA), MBGF (FLK OUT)(12GA)TIM POST, SL GDRL RERM (TY III
Prime Contractors: BALLENGER CONSTRUCTION COMPAN
 
Let Date: 2005-06 County: CAMERON
CCSJ: 0220-07-051 District: PHARR
Project ID: MG 2004(778) Pct Complete: 0%
Commitment Amount: 764,880.00
Commitment Work: FL BS (MPL IN PL)(TY A), RM ACR SCT, MBGF (TM PT),MBGF TRNS (THIE BM), RMV MBGF, RMV TRM ACT SCT SL GR TRM (TY II) & (MV & RST), REACT 350 (NRW
Prime Contractors: FOREMOST PAVING, INC
 
Let Date: 2005-07 County: CAMERON
CCSJ: 0039-08-087 District: PHARR
Project ID: MG 2005(288) Pct Complete: 0%
Commitment Amount: 753,247.50
Commitment Work: TEXTURED CONC,MTL W-BEAM GD FEN,TERMINAL ANCHOR SECTION, REMVOING METAL BEAM GUARD FENCE,TERMINA ANCHOR SECTION,GUARD RAIL END TREATMENT,CUSH ATTE
Prime Contractors: BALLENGER CONSTRUCTION COMPAN
 
Let Date: 2005-07 County: HIDALGO
CCSJ: 0861-01-053 District: PHARR
Project ID: STP 2005(387) Pct Complete: 0%
Commitment Amount: 89,175.00
Commitment Work: MTL W-BEAM GD FEN,MTL BEAM GD FEN TRANS,REMOVING METAL BEAM GUARD FENCE,GUARDRAIL END TREATMENT CRASH CUSH ATTE
Prime Contractors: BALLENGER CONSTRUCTION COMPAN