| Let Date: |
2001-02 |
County: |
CAMERON |
| CCSJ: |
0039-07-185 |
District: |
PHARR |
| Project ID: |
MG 2001(257) |
Pct Complete: |
97% |
| Commitment Amount: |
0.00 |
| Commitment Work: |
|
| Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
| |
| Let Date: |
2001-02 |
County: |
CAMERON |
| CCSJ: |
0039-07-185 |
District: |
PHARR |
| Project ID: |
MG 2001(257) |
Pct Complete: |
97% |
| CUF REV Results: |
|
Sub Replaced: |
REPLACED |
| Commitment Amount: |
0.00 |
| Commitment Work: |
MANUF CONCRET |
| Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
| |
| Let Date: |
2002-07 |
County: |
ZAPATA |
| CCSJ: |
0038-04-050 |
District: |
PHARR |
| Project ID: |
NH 2002(731) |
Pct Complete: |
100% |
| Commitment Amount: |
197,464.75 |
| Commitment Work: |
CONC CURB & GUTTER, CONC GUTTER(VALLEY), TERM ANCHSECT, MBGF, REM MBGF, REM TERM ANCH SECT, SINGL GDRAIL TERM (MOVE & RESET |
| Prime Contractors: |
FOREMOST PAVING, INC |
| |
| Let Date: |
2002-11 |
County: |
KLEBERG |
| CCSJ: |
1446-02-015 |
District: |
CORPUS CHRISTI |
| Project ID: |
STP 2003(18) |
Pct Complete: |
87% |
| Commitment Amount: |
0.00 |
| Commitment Work: |
|
| Prime Contractors: |
HUNTER INDUSTRIES, LTD |
| |
| Let Date: |
2002-12 |
County: |
CAMERON |
| CCSJ: |
0039-07-186 |
District: |
PHARR |
| Project ID: |
NH 2002(80) |
Pct Complete: |
70% |
| Commitment Amount: |
1,028,045.26 |
| Commitment Work: |
RAIL (TY T201), (TYC201), (TY 203R), TERM ANCHOR MTL BEAM GD FENCE, REMOVE, TERM ANCHOR, SIGNA GDRAIL, CONC CURB & GUTTER, CURB RAMP & LANDIN |
| Prime Contractors: |
ZACHRY CONSTRUCTION CORPORATIO |
| |
| Let Date: |
2003-04 |
County: |
CAMERON |
| CCSJ: |
0039-16-057 |
District: |
PHARR |
| Project ID: |
NH 2003(369) |
Pct Complete: |
64% |
| Commitment Amount: |
678,193.01 |
| Commitment Work: |
DRVWYS, CONCRETE SIDEWALK, MTL BM GD FEN, REMOV METAL TERM, CHAIM LINK, QUADGD SYS, CURB RAM SINGLE GUARDRAI |
| Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
| |
| Let Date: |
2003-10 |
County: |
HIDALGO |
| CCSJ: |
0255-08-091 |
District: |
PHARR |
| Project ID: |
MG 2003(689) |
Pct Complete: |
76% |
| Commitment Amount: |
658,399.05 |
| Commitment Work: |
TERM ANCHOR SECT, MBGF, SINGLE GUARDRAIL TERM, REAC |
| Prime Contractors: |
BALLENGER CONSTRUCTION COMPAN |
| |
| Let Date: |
2004-02 |
County: |
HIDALGO |
| CCSJ: |
0255-08-094 |
District: |
PHARR |
| Project ID: |
NH 2004(255) |
Pct Complete: |
39% |
| Commitment Amount: |
540,460.00 |
| Commitment Work: |
RIPRAP, CURB & GUTTER, CONC CURB, DRVWYS, SIDEWALK RAMP AND LANDING |
| Prime Contractors: |
ZACHRY CONSTRUCTION CORPORATIO |
| |
| Let Date: |
2004-05 |
County: |
HIDALGO |
| CCSJ: |
0921-02-101 |
District: |
PHARR |
| Project ID: |
STP 2002(180)TE |
Pct Complete: |
75% |
| Commitment Amount: |
494,699.90 |
| Commitment Work: |
REMOC CONC RIPRAP, REMOV CONC SIDEWALK, RMV STB BS AND ASH, EXCAVATION, EMBANKMENT, EMBANK CHAI FLEX BASE RDWY DEL, LIME TREAT, RIPRAP |
| Prime Contractors: |
H2O CONSTRUCTION, INCORPORATE |
| |
| Let Date: |
2004-09 |
County: |
CAMERON |
| CCSJ: |
0039-06-031 |
District: |
PHARR |
| Project ID: |
STP 2005(55) |
Pct Complete: |
40% |
| Commitment Amount: |
424,262.65 |
| Commitment Work: |
CONC CURB AND GUTTER, DRVWYS, CONC SIDEWALKS CURB RAMP AND LANDIN |
| Prime Contractors: |
FOREMOST PAVING, INC |
| |
| Let Date: |
2004-09 |
County: |
CAMERON |
| CCSJ: |
0039-19-042 |
District: |
PHARR |
| Project ID: |
MG 2004(548) |
Pct Complete: |
15% |
| Commitment Amount: |
0.00 |
| Commitment Work: |
|
| Prime Contractors: |
ZACHRY CONSTRUCTION CORPORATIO |
| |
| Let Date: |
2004-09 |
County: |
CAMERON |
| CCSJ: |
0039-08-086 |
District: |
PHARR |
| Project ID: |
MG 2003(303) |
Pct Complete: |
28% |
| Commitment Amount: |
202,873.00 |
| Commitment Work: |
TERM ANCHOR SECT (12), MTL BM GD FEN, REMOV BM GD FEN, QUADGUARD SYSTEM, SINGLE GD RL, REACT 35 |
| Prime Contractors: |
BALLENGER CONSTRUCTION COMPAN |
| |
| Let Date: |
2004-10 |
County: |
HIDALGO |
| CCSJ: |
0921-02-100 |
District: |
PHARR |
| Project ID: |
STP 2002(182)TE |
Pct Complete: |
88% |
| Commitment Amount: |
846,937.20 |
| Commitment Work: |
PREP ROW,REM CONC,REM STB,EXCAV,EMBNK,TPSL,FL BS, LIME TRT,ASHP MATRL,FLUME,RE WALL,RIPRAP,RAIL,ADJ MNHL,PVC PIPE,CURB&GUTR,SDWL |
| Prime Contractors: |
H2O CONSTRUCTION, INCORPORATE |
| |
| Let Date: |
2004-11 |
County: |
HIDALGO |
| CCSJ: |
1889-01-007 |
District: |
PHARR |
| Project ID: |
STP 2005(8) |
Pct Complete: |
92% |
| Commitment Amount: |
73,942.50 |
| Commitment Work: |
DRVWYS, MBGF, REMOV TERM ANCHOR SECT, SINGLE GUARDRAIL TER |
| Prime Contractors: |
FOREMOST PAVING, INC |
| |
| Let Date: |
2005-05 |
County: |
HIDALGO |
| CCSJ: |
0921-02-090 |
District: |
PHARR |
| Project ID: |
BOR 2001(592) |
Pct Complete: |
0% |
| Commitment Amount: |
119,754.40 |
| Commitment Work: |
RC PIPE (CLIII 18" & 60"), INLET (COMP)(TYC |
| Prime Contractors: |
FOREMOST PAVING, INC |
| |
| Let Date: |
2005-06 |
County: |
CAMERON |
| CCSJ: |
1425-03-042 |
District: |
PHARR |
| Project ID: |
STP 2004(189) |
Pct Complete: |
0% |
| Commitment Amount: |
25,570.20 |
| Commitment Work: |
TERM ANCHOR SECT (12GA), MBGF (FLK OUT)(12GA)TIM POST, SL GDRL RERM (TY III |
| Prime Contractors: |
BALLENGER CONSTRUCTION COMPAN |
| |
| Let Date: |
2005-06 |
County: |
CAMERON |
| CCSJ: |
0220-07-051 |
District: |
PHARR |
| Project ID: |
MG 2004(778) |
Pct Complete: |
0% |
| Commitment Amount: |
764,880.00 |
| Commitment Work: |
FL BS (MPL IN PL)(TY A), RM ACR SCT, MBGF (TM PT),MBGF TRNS (THIE BM), RMV MBGF, RMV TRM ACT SCT SL GR TRM (TY II) & (MV & RST), REACT 350 (NRW |
| Prime Contractors: |
FOREMOST PAVING, INC |
| |
| Let Date: |
2005-07 |
County: |
CAMERON |
| CCSJ: |
0039-08-087 |
District: |
PHARR |
| Project ID: |
MG 2005(288) |
Pct Complete: |
0% |
| Commitment Amount: |
753,247.50 |
| Commitment Work: |
TEXTURED CONC,MTL W-BEAM GD FEN,TERMINAL ANCHOR SECTION, REMVOING METAL BEAM GUARD FENCE,TERMINA ANCHOR SECTION,GUARD RAIL END TREATMENT,CUSH ATTE |
| Prime Contractors: |
BALLENGER CONSTRUCTION COMPAN |
| |
| Let Date: |
2005-07 |
County: |
HIDALGO |
| CCSJ: |
0861-01-053 |
District: |
PHARR |
| Project ID: |
STP 2005(387) |
Pct Complete: |
0% |
| Commitment Amount: |
89,175.00 |
| Commitment Work: |
MTL W-BEAM GD FEN,MTL BEAM GD FEN TRANS,REMOVING METAL BEAM GUARD FENCE,GUARDRAIL END TREATMENT CRASH CUSH ATTE |
| Prime Contractors: |
BALLENGER CONSTRUCTION COMPAN |
| |