DBE Construction Report for BTA SERVICES, LTD.
| |
DBE Construction Report for BTA SERVICES, LTD. |
| |
| Last Update: Wednesday, September 7, 2005 |
| BTA SERVICES, LTD. |
Vendor #: |
06444 |
| P.O. BOX 850 |
DBE Certification Status: |
CERTIFIED |
| ROCKWALL, TX 75087 |
Expiration Date: |
01/31/06 |
| Phone: (972)771-3832 |
Fax: |
(972)771-6525 |
| |
| Let Date: |
2003-08 |
County: |
COLLIN |
| CCSJ: |
0091-04-039 |
District: |
DALLAS |
| Project ID: |
BR 99(239) |
Pct Complete: |
71% |
| Commitment Amount: |
24,924.96 |
| Commitment Work: |
WRK ZN PAV MRK, REFL PAV MRK, RAIS PAV MRK, ELIM PAV MRK, PAV SURF PRE |
| Prime Contractors: |
APAC-TEXAS, INC |
| |
| Let Date: |
2003-08 |
County: |
TARRANT |
| CCSJ: |
0008-12-074 |
District: |
FORT WORTH |
| Project ID: |
BR 2003(62) |
Pct Complete: |
92% |
| Commitment Amount: |
0.00 |
| Commitment Work: |
|
| Prime Contractors: |
EARTH BUILDERS, INC |
| |
| Let Date: |
2004-05 |
County: |
COOKE |
| CCSJ: |
0312-01-058 |
District: |
WICHITA FALLS |
| Project ID: |
MG 2004(418) |
Pct Complete: |
71% |
| Commitment Amount: |
24,025.40 |
| Commitment Work: |
REFL PAV MRK TY (1) (4"),(12"), RAIS PAV MRK CL |
| Prime Contractors: |
AUI CONTRACTORS, L.P |
| |
| Let Date: |
2004-06 |
County: |
LAMAR |
| CCSJ: |
0045-09-074 |
District: |
PARIS |
| Project ID: |
STP 2004(451)HES |
Pct Complete: |
48% |
| Commitment Amount: |
24,472.83 |
| Commitment Work: |
PAVEMENT MARKING |
| Prime Contractors: |
APAC-TEXAS, INC |
| |
| Let Date: |
2004-07 |
County: |
PARKER |
| CCSJ: |
1468-01-019 |
District: |
FORT WORTH |
| Project ID: |
BR 2004(259) |
Pct Complete: |
63% |
| Commitment Amount: |
13,993.20 |
| Commitment Work: |
WRK ZN PAV MRK, REFL PAV MRK, RAIS PAV MRK, ELIM PAV MRK, PAV SURF PRE |
| Prime Contractors: |
ELLIS-MCGINNIS CONSTRUCTION CO |
| |
| Let Date: |
2004-08 |
County: |
TARRANT |
| CCSJ: |
0902-48-575 |
District: |
FORT WORTH |
| Project ID: |
STP 2004(51)MM |
Pct Complete: |
69% |
| Commitment Amount: |
61,912.50 |
| Commitment Work: |
WRK ZN PAV MRK, REFL PAV MRK, RAIS PAV MRK, ELIM EXT PAV MARKR, PAV SURF PRE |
| Prime Contractors: |
AUSTIN BRIDGE & ROAD, L |
| |
| Let Date: |
2004-08 |
County: |
WISE |
| CCSJ: |
0902-20-060 |
District: |
FORT WORTH |
| Project ID: |
BR 2001(680) |
Pct Complete: |
57% |
| Commitment Amount: |
2,171.00 |
| Commitment Work: |
REFL PAV MRK, PAV SURF PRE |
| Prime Contractors: |
COPPELL CONSTRUCTION CO., INC |
| |
| Let Date: |
2005-03 |
County: |
PARKER |
| CCSJ: |
0902-38-038 |
District: |
FORT WORTH |
| Project ID: |
BR 2001(733) |
Pct Complete: |
61% |
| Commitment Amount: |
4,500.00 |
| Commitment Work: |
REFL PAV MRK TYII, PAF SURF PREP FOR MRK |
| Prime Contractors: |
HODGES AND SON CONSTRUCTION COMPANY, INC |
| |
| Let Date: |
2005-05 |
County: |
ELLIS |
| CCSJ: |
1139-02-014 |
District: |
DALLAS |
| Project ID: |
BR 2005(394) |
Pct Complete: |
7% |
| Commitment Amount: |
14,598.00 |
| Commitment Work: |
WK ZN PAV MRK, REFL PAV MRK,ELIM EXT PAV MRKS PAV SURF PREP FOR MR |
| Prime Contractors: |
ED BELL CONSTRUCTION COMPAN |
| |