Let Date: |
2001-02 |
County: |
CAMERON |
CCSJ: |
0039-07-185 |
District: |
PHARR |
Project ID: |
MG 2001(257) |
Pct Complete: |
97% |
Commitment Amount: |
3,202,925.00 |
Commitment Work: |
CONC FOR PAV, CONC FOR STRS CLB/CLC/CLS/CLS |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2001-02 |
County: |
CAMERON |
CCSJ: |
0039-07-185 |
District: |
PHARR |
Project ID: |
MG 2001(257) |
Pct Complete: |
97% |
Commitment Amount: |
2,161,253.59 |
Commitment Work: |
MANUF REINF STEE |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2002-07 |
County: |
BEXAR |
CCSJ: |
0072-12-159 |
District: |
SAN ANTONIO |
Project ID: |
NH 2002(305) |
Pct Complete: |
69% |
Commitment Amount: |
4,605,480.00 |
Commitment Work: |
MANUF CLALL P,B,C,S CONC, FLOW BKF |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2002-07 |
County: |
BEXAR |
CCSJ: |
0072-12-159 |
District: |
SAN ANTONIO |
Project ID: |
NH 2002(305) |
Pct Complete: |
69% |
Commitment Amount: |
0.00 |
Commitment Work: |
|
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2002-09 |
County: |
HIDALGO |
CCSJ: |
0039-18-085 |
District: |
PHARR |
Project ID: |
NH 2002(588) |
Pct Complete: |
74% |
Commitment Amount: |
3,209,788.00 |
Commitment Work: |
MANUF CL P, B, C, S CONCRET |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2002-09 |
County: |
HIDALGO |
CCSJ: |
0039-18-085 |
District: |
PHARR |
Project ID: |
NH 2002(588) |
Pct Complete: |
74% |
Commitment Amount: |
536,246.92 |
Commitment Work: |
PLACE AND TIE REINF STEEL FOR CONC PAV, DRILLSHAFTCL C CONC, REINF, RETAINING WALL, RAIL, PER CONC TRAF BAR SG |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2002-09 |
County: |
HIDALGO |
CCSJ: |
0039-18-085 |
District: |
PHARR |
Project ID: |
NH 2002(588) |
Pct Complete: |
74% |
Commitment Amount: |
3,037,962.00 |
Commitment Work: |
DRILL SHAFT, ALUM SIGNS, LG RDSD, REM LG RDSD, OVHD SIGN SUPT, SGN WLKWY, FND LG RDSD SGN SUPT RDWY ILL ASSEM, CONDUITS, ELEC CONDUCTORS,TRAF SI |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2003-04 |
County: |
CAMERON |
CCSJ: |
0039-16-057 |
District: |
PHARR |
Project ID: |
NH 2003(369) |
Pct Complete: |
64% |
Commitment Amount: |
1,528,504.50 |
Commitment Work: |
CONC PAV, DRILL SHAFT, CL C CONC, REINF SLAB, RETAINING WALL (SOIL NAILED), RAIL (TY SSTR) PREMCON |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2004-08 |
County: |
HIDALGO |
CCSJ: |
0039-18-086 |
District: |
PHARR |
Project ID: |
MG 2004(617) |
Pct Complete: |
22% |
Commitment Amount: |
3,504,066.25 |
Commitment Work: |
INSTALL REINF REBA |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2002-08 |
County: |
HARRIS |
CCSJ: |
0027-13-171 |
District: |
HOUSTON |
Project ID: |
NH 2002(570) |
Pct Complete: |
93% |
Commitment Amount: |
5,549,152.00 |
Commitment Work: |
MANUF CLASS P,B,C,S,SS,F CONCRET |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2002-08 |
County: |
HARRIS |
CCSJ: |
0027-13-171 |
District: |
HOUSTON |
Project ID: |
NH 2002(570) |
Pct Complete: |
93% |
Commitment Amount: |
0.00 |
Commitment Work: |
|
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2003-04 |
County: |
WALLER |
CCSJ: |
0409-02-021 |
District: |
HOUSTON |
Project ID: |
BR 2001(297) |
Pct Complete: |
94% |
Commitment Amount: |
29,478.35 |
Commitment Work: |
STRAW OR HAY MULCH, DRILL SEED, FERTILIZE |
Prime Contractors: |
LONE STAR ROAD CONSTRUCTION, LTD |
|
Let Date: |
2003-07 |
County: |
HARRIS |
CCSJ: |
0271-17-127 |
District: |
HOUSTON |
Project ID: |
NH 2002(326) |
Pct Complete: |
67% |
Commitment Amount: |
0.00 |
Commitment Work: |
|
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2003-12 |
County: |
HARRIS |
CCSJ: |
0028-01-078 |
District: |
HOUSTON |
Project ID: |
BR 2004(82) |
Pct Complete: |
90% |
Commitment Amount: |
1,814,148.30 |
Commitment Work: |
PRIME CONTRACTOR IS A DB |
Prime Contractors: |
SOUTH COAST CONSTRUCTION, INC |
|
Let Date: |
2005-01 |
County: |
JEFFERSON |
CCSJ: |
0200-15-013 |
District: |
BEAUMONT |
Project ID: |
STP 2005(113) |
Pct Complete: |
27% |
Commitment Amount: |
0.00 |
Commitment Work: |
|
Prime Contractors: |
APAC-TEXAS, INC |
|
Let Date: |
2005-03 |
County: |
HARRIS |
CCSJ: |
0912-71-867 |
District: |
HOUSTON |
Project ID: |
STP 2004(504)TE |
Pct Complete: |
100% |
CUF REV Results: |
|
Sub Replaced: |
REPLACED |
Commitment Amount: |
0.00 |
Commitment Work: |
MBGF ADJUSTMENT, GRD RL END TREAT (MOVE & RESET), CHAIN LINK FENCE (INSTALL)(4' |
Prime Contractors: |
SLACK & CO. CONTRACTING, INC |
|
Let Date: |
2000-08 |
County: |
MONTGOMERY |
CCSJ: |
0110-04-122 |
District: |
HOUSTON |
Project ID: |
STP 2000(495)MM |
Pct Complete: |
62% |
Commitment Amount: |
3,283,539.00 |
Commitment Work: |
CONC FOR CONC PAV CLP, CONC FOR FSTRK PAV, CEM TREAT BASE PROD, CONC FOR STR |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2000-08 |
County: |
MONTGOMERY |
CCSJ: |
0110-04-122 |
District: |
HOUSTON |
Project ID: |
STP 2000(495)MM |
Pct Complete: |
62% |
Commitment Amount: |
0.00 |
Commitment Work: |
|
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2002-11 |
County: |
HARRIS |
CCSJ: |
0050-06-045 |
District: |
HOUSTON |
Project ID: |
STP 2001(860)MM |
Pct Complete: |
100% |
Commitment Amount: |
938,178.50 |
Commitment Work: |
REINFORCING STEE |
Prime Contractors: |
W.W. WEBBER INC |
|
Let Date: |
2004-04 |
County: |
HARRIS |
CCSJ: |
3510-05-009 |
District: |
HOUSTON |
Project ID: |
STP 2004(294)MM |
Pct Complete: |
100% |
Commitment Amount: |
0.00 |
Commitment Work: |
|
Prime Contractors: |
W.W. WEBBER INC |
|
Let Date: |
2004-10 |
County: |
GALVESTON |
CCSJ: |
1607-02-016 |
District: |
HOUSTON |
Project ID: |
HP 300(100) |
Pct Complete: |
44% |
Commitment Amount: |
1,043,909.09 |
Commitment Work: |
FURNISH AND INSTALL REINFORCING STEE |
Prime Contractors: |
ZACHRY CONSTRUCTION CORPORATIO |
|
Let Date: |
2004-12 |
County: |
HARRIS |
CCSJ: |
0271-07-254 |
District: |
HOUSTON |
Project ID: |
NH 2005(85) |
Pct Complete: |
28% |
Commitment Amount: |
5,310,248.85 |
Commitment Work: |
REINFORCING STEE |
Prime Contractors: |
BALFOUR BEATTY CONSTRUCTION, INC |
|
Let Date: |
2005-01 |
County: |
HARRIS |
CCSJ: |
0271-07-247 |
District: |
HOUSTON |
Project ID: |
NH 2002(328) |
Pct Complete: |
36% |
Commitment Amount: |
12,888,964.38 |
Commitment Work: |
CONC PAV; DRILL SHAFT;CL C CONC; REINF CONC SLAB; RETAINING WALL; RAIL; PERM CONC TRAF BAR SG SLP; FAST TRK CON |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2005-02 |
County: |
HARRIS |
CCSJ: |
0271-07-245 |
District: |
HOUSTON |
Project ID: |
NH 2003(81) |
Pct Complete: |
23% |
Commitment Amount: |
10,762,354.85 |
Commitment Work: |
CONC PAV(CONT REINF)DRL SHAFT, CONC(INCIDENTALS) RAILS, PERM CONC BARRIERS, FAST TRK CONC COUPLER |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|
Let Date: |
2005-03 |
County: |
HARRIS |
CCSJ: |
0271-07-249 |
District: |
HOUSTON |
Project ID: |
NH 2002(969) |
Pct Complete: |
24% |
Commitment Amount: |
11,151,262.22 |
Commitment Work: |
CONC. PAV. REINF HY STL,DRILL SHAFT,CLC CONC,REINFCONC. SLAB,RETAINING WALLS, RAIL,FAST TRK.CONC CLF CONC. SIGN COLUMN,COUPLER |
Prime Contractors: |
WILLIAMS BROTHERS CONSTRUCTION CO., INC |
|