Detail Letting Schedule for Comal County (FY 2003)
|
Detail Letting Schedule for Comal County (FY 2003) |
|
Last Update: Thursday, August 28, 2003 |
CCSJ: 0016-05-091
|
District: |
San Antonio |
Let Date: |
APR 2003 |
Highway: |
IH 35 |
Let Status: |
Actual |
Project ID: |
IM 35-2(302) |
CSJ: |
0016-05-091 |
Description: |
UPGRADE FRONTAGE ROADS |
Handling Code: |
|
Limits From: |
0.10 MI N OF FM 482 |
Fund Cat: |
4 |
Limits To: |
0.16 MI S OF SOLMS RD |
Estimate: |
$15,316,077 |
Length: |
5.8 Miles |
Actual: |
$10,112,919 |
|
Back...
|
Totals for 0016-05-091 |
Length: |
5.8 Miles |
Estimate: |
$15,316,077 |
Actual: |
$10,112,919 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|