Detail Letting Schedule for Kerr County (FY 2003)
| Detail Letting Schedule for Kerr County (FY 2003) | ||||
| Last Update: Thursday, August 28, 2003 |
| Kerr County (FY 2003) |
CCSJ: 0142-05-056 | |||
| District: | San Antonio | Let Date: | JUN 2003 |
| Highway: | SH 27 | Let Status: | Actual |
| Project ID: | MG 2001(60) | CSJ: | 0142-05-056 |
| Description: | UPGRADE TO 4 LANE WITH CONTINUOUS LEFT TURN LANE | Handling Code: |
|
| Limits From: | IN KERRVILLE ON BROADWAY FROM WATER ST,N | Fund Cat: | 4 |
| Limits To: | MAIN ST | Estimate: | $2,764,338 |
| Length: | 0.7 Miles | Actual: | $2,535,229 |
|
Bid Tabulations Back... |
Totals for 0142-05-056 | ||
|---|---|---|---|
| Length: | 0.7 Miles | ||
| Estimate: | $2,764,338 | ||
| Actual: | $2,535,229 | ||
CCSJ: 0142-05-069 | |||
| District: | San Antonio | Let Date: | SEP 2002 |
| Highway: | SH 27 | Let Status: | Actual |
| Project ID: | CPM 142-5-69 | CSJ: | 0142-05-069 |
| Description: | SEAL COAT, MICRO - SURFACE & MARKINGS | Handling Code: |
|
| Limits From: | EAST SIDE OF CENTER POINT | Fund Cat: | 1 |
| Limits To: | KERR/KENDALL COUNTY LINE | Estimate: | $580,569 |
| Length: | 7.2 Miles | Actual: | $505,927 |
| District: | San Antonio | Let Date: | SEP 2002 |
| Highway: | SH 27 | Let Status: | Actual |
| Project ID: | CPM 142-5-70 | CSJ: | 0142-05-070 |
| Description: | SEAL COAT, MICRO - SURFACE & MARKINGS | Handling Code: |
|
| Limits From: | 1200' E OF OAK WAY | Fund Cat: | 1 |
| Limits To: | EAST SIDE OF CENTER POINT | Estimate: | $419,165 |
| Length: | 5.1 Miles | Actual: | $360,884 |
|
Back... |
Totals for 0142-05-069 | ||
| Length: | 12.3 Miles | ||
| Estimate: | $999,734 | ||
| Actual: | $866,811 | ||
CCSJ: 0193-02-035 | |||
| District: | San Antonio | Let Date: | DEC 2002 |
| Highway: | SH 39 | Let Status: | Actual |
| Project ID: | BR 2002(670) | CSJ: | 0193-02-035 |
| Description: | REPAIR EROSION AT BRIDGE AND CHANNEL | Handling Code: |
|
| Limits From: | AT BUMBLE BEE CREEK | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $111,083 |
| Length: | 0.1 Miles | Actual: | $75,344 |
|
Back... |
Totals for 0193-02-035 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $111,083 | ||
| Actual: | $75,344 | ||
CCSJ: 0609-01-018 | |||
| District: | San Antonio | Let Date: | SEP 2002 |
| Highway: | SH 173 | Let Status: | Actual |
| Project ID: | STP 2002(901) | CSJ: | 0609-01-018 |
| Description: | INSTALL STORM SEWER | Handling Code: |
|
| Limits From: | 0.31 MI W OF LP 534 (RIVERHILLS BLVD) | Fund Cat: | 1 |
| Limits To: | 0.093 MI W (CAMP MEETING CREEK) | Estimate: | $205,681 |
| Length: | 0.1 Miles | Actual: | $193,954 |
|
Back... |
Totals for 0609-01-018 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $205,681 | ||
| Actual: | $193,954 | ||
|
| |