Detail Letting Schedule for Smith County (FY 2003)
Detail Letting Schedule for Smith County (FY 2003) | ||||
Last Update: Thursday, August 28, 2003 |
Smith County (FY 2003) |
CCSJ: 0165-01-071 | |||
District: | Tyler | Let Date: | JAN 2003 |
Highway: | US 271 | Let Status: | Actual |
Project ID: | BR 2003(220) | CSJ: | 0165-01-071 |
Description: | REHABILITATE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | BECKHAM ST OVERPASS AT UPRR & BOW ST | Fund Cat: | 6 |
Limits To: | IN TYLER, STR# 025, DOT 789811F | Estimate: | $2,073,228 |
Length: | 0.3 Miles | Actual: | $1,419,742 |
Back... |
Totals for 0165-01-071 | ||
---|---|---|---|
Length: | 0.3 Miles | ||
Estimate: | $2,073,228 | ||
Actual: | $1,419,742 | ||
CCSJ: 0190-05-052 | |||
District: | Tyler | Let Date: | APR 2003 |
Highway: | US 69 | Let Status: | Actual |
Project ID: | STP 2003(378) | CSJ: | 0190-05-052 |
Description: | OVERLAY | Handling Code: |
|
Limits From: | 0.134 MI N OF IH 20 IN LINDALE, S | Fund Cat: | 1 |
Limits To: | LP 323 IN TYLER | Estimate: | $3,841,890 |
Length: | 7.0 Miles | Actual: | $3,732,710 |
Back... |
Totals for 0190-05-052 | ||
Length: | 7.0 Miles | ||
Estimate: | $3,841,890 | ||
Actual: | $3,732,710 | ||
CCSJ: 0495-05-016 | |||
District: | Tyler | Let Date: | OCT 2002 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | BR 2002(739) | CSJ: | 0495-05-016 |
Description: | REHABILITATE BRIDGES AND APPROACHES | Handling Code: |
|
Limits From: | FM 14, EAST | Fund Cat: | 1 |
Limits To: | US 271 | Estimate: | $14,856,766 |
Length: | 3.9 Miles | Actual: | $13,080,855 |
District: | Tyler | Let Date: | OCT 2002 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | STP 2003(84)HES | CSJ: | 0495-05-042 |
Description: | ADD TEXTURIZED SHOULDERS FOR SAFETY | Handling Code: |
|
Limits From: | 1.3 MI W OF FM 14, E | Fund Cat: | 8 |
Limits To: | US 271 | Estimate: | $56,856 |
Length: | 9.2 Miles | Actual: | $41,495 |
Back... |
Totals for 0495-05-016 | ||
Length: | 13.1 Miles | ||
Estimate: | $14,913,622 | ||
Actual: | $13,122,350 | ||
CCSJ: 0910-00-048 | |||
District: | Tyler | Let Date: | JAN 2003 |
Highway: | VA | Let Status: | Actual |
Project ID: | C 910-0-48 | CSJ: | 0910-00-048 |
Description: | THERMO PLASTIC PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | VARIOUS LOCATIONS IN | Fund Cat: | 1 |
Limits To: | THE TYLER DISTRICT | Estimate: | $229,535 |
Length: | 0.0 Miles | Actual: | $199,981 |
District: | Tyler | Let Date: | JAN 2003 |
Highway: | FM 1804 | Let Status: | Actual |
Project ID: | C 1791-1-7 | CSJ: | 1791-01-007 |
Description: | THERMO PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 1.9 MI S OF FM 2422 (WOOD C/L), S | Fund Cat: | 1 |
Limits To: | US 69 | Estimate: | $21,500 |
Length: | 4.9 Miles | Actual: | $21,500 |
District: | Tyler | Let Date: | JAN 2003 |
Highway: | FM 1804 | Let Status: | Actual |
Project ID: | C 1791-2-4 | CSJ: | 1791-02-004 |
Description: | THERMO PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | FM 2422, S | Fund Cat: | 1 |
Limits To: | WOOD COUNTY LINE | Estimate: | $9,800 |
Length: | 2.9 Miles | Actual: | $9,800 |
Back... |
Totals for 0910-00-048 | ||
Length: | 7.8 Miles | ||
Estimate: | $260,835 | ||
Actual: | $231,281 | ||
CCSJ: 0910-00-055 | |||
District: | Tyler | Let Date: | MAY 2003 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2003(458) | CSJ: | 0910-00-055 |
Description: | NON - SITE SPECIFIC SIGNAL UPGRADE FY 2003 | Handling Code: |
|
Limits From: | VARIOUS LOCATIONS IN | Fund Cat: | 1 |
Limits To: | THE TYLER DISTRICT | Estimate: | $304,125 |
Length: | 1.0 Miles | Actual: | $373,776 |
Back... |
Totals for 0910-00-055 | ||
Length: | 1.0 Miles | ||
Estimate: | $304,125 | ||
Actual: | $373,776 | ||
CCSJ: 0910-00-057 | |||
District: | Tyler | Let Date: | OCT 2002 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2000(630)TE | CSJ: | 0910-00-057 |
Description: | REPAIR DETERIORATED BRIDGES AND EROSION CONTROL | Handling Code: |
|
Limits From: | TEXAS STATE RAILROAD HISTORICAL PARK | Fund Cat: | 9 |
Limits To: | RUSK DEPOT TO PALESTINE DEPOT | Estimate: | $2,022,539 |
Length: | 0.4 Miles | Actual: | $2,129,037 |
Back... |
Totals for 0910-00-057 | ||
Length: | 0.4 Miles | ||
Estimate: | $2,022,539 | ||
Actual: | $2,129,037 | ||
CCSJ: 0910-16-081 | |||
District: | Tyler | Let Date: | MAR 2003 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2000(634)TE | CSJ: | 0910-16-081 |
Description: | COTTON BELT DEPOT RESTORATION | Handling Code: |
LC |
Limits From: | OAKWOOD AVE @ SPRING ST, IN TYLER | Fund Cat: | 9 |
Limits To: | COTTON BELT DEPOT | Estimate: | $417,960 |
Length: | 0.0 Miles | Actual: | $435,700 |
Back... |
Totals for 0910-16-081 | ||
Length: | 0.0 Miles | ||
Estimate: | $417,960 | ||
Actual: | $435,700 | ||
CCSJ: 0910-16-085 | |||
District: | Tyler | Let Date: | MAR 2003 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2001(762) | CSJ: | 0910-16-085 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | CR 46 @ PRAIRIE CREEK SMITH | Fund Cat: | 6 |
Limits To: | STR# AA01-63-001 | Estimate: | $357,754 |
Length: | 0.2 Miles | Actual: | $313,660 |
Back... |
Totals for 0910-16-085 | ||
Length: | 0.2 Miles | ||
Estimate: | $357,754 | ||
Actual: | $313,660 | ||
CCSJ: 3487-01-002 | |||
District: | Tyler | Let Date: | APR 2003 |
Highway: | LP 49 | Let Status: | Actual |
Project ID: | STP 2003(410) | CSJ: | 3487-01-002 |
Description: | CONSTRUCT 2 - LANE ROAD ON NEW LOCATION | Handling Code: |
|
Limits From: | SH 155, 2.1 MI N OF FM 2868, SE & E | Fund Cat: | 11 |
Limits To: | 0.3 MI E OF US 69 | Estimate: | $21,699,716 |
Length: | 5.0 Miles | Actual: | $22,307,972 |
Back... |
Totals for 3487-01-002 | ||
Length: | 5.0 Miles | ||
Estimate: | $21,699,716 | ||
Actual: | $22,307,972 |
|
|