Detail Letting Schedule for Titus County (FY 2003)

 
 
Last Update: Thursday, August 28, 2003
Titus County (FY 2003)

CCSJ: 0919-30-028

District: Atlanta Let Date: SEP 2002
Highway: CR Let Status: Actual
Project ID: BR 2000(320)OX CSJ: 0919-30-028
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: ON CR NE35(181), Fund Cat: 6
Limits To: AT HORSE CREEK Estimate: $169,307
Length: 0.1 Miles Actual: $152,660
 
District: Atlanta Let Date: SEP 2002
Highway: CR Let Status: Actual
Project ID: BR 2000(322)OX CSJ: 0919-30-030
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: ON CR NW18 AT RIPLEY BRANCH Fund Cat: 6
Limits To: . Estimate: $170,069
Length: 0.1 Miles Actual: $146,021
 
District: Atlanta Let Date: SEP 2002
Highway: CR Let Status: Actual
Project ID: BR 2000(323)OX CSJ: 0919-30-031
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: ON CR NW04, Fund Cat: 6
Limits To: AT MCCULLOUGH CREEK Estimate: $207,680
Length: 0.1 Miles Actual: $174,372
 
District: Atlanta Let Date: SEP 2002
Highway: CR Let Status: Actual
Project ID: BR 2000(324)OX CSJ: 0919-30-032
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: ON CR NW41 Fund Cat: 6
Limits To: AT EAST PINEY CREEK Estimate: $175,438
Length: 0.1 Miles Actual: $166,366
 
Back...

Totals for 0919-30-028
Length: 0.4 Miles
Estimate: $722,494
Actual: $639,419


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract