Detail Letting Schedule for Val Verde County (FY 2003)
Detail Letting Schedule for Val Verde County (FY 2003) | ||||
Last Update: Thursday, August 28, 2003 |
Val Verde County (FY 2003) |
CCSJ: 0022-07-024 | |||
District: | Laredo | Let Date: | JUN 2003 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | C 22-7-24 | CSJ: | 0022-07-024 |
Description: | FOR THE CONSTRUCTION OF TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | SH 163 | Fund Cat: | 11 |
Limits To: | AT THE INTERSECTION OF US90/SH 163 | Estimate: | $33,261 |
Length: | 0.1 Miles | Actual: | $24,979 |
District: | Laredo | Let Date: | JUN 2003 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | C 23-3-39 | CSJ: | 0023-03-039 |
Description: | FOR THE CONSTRUCTION OF TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | US 90 | Fund Cat: | 11 |
Limits To: | AT THE INTERSECTION OF FM 3348 | Estimate: | $19,709 |
Length: | 0.0 Miles | Actual: | $15,678 |
District: | Laredo | Let Date: | JUN 2003 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | C 160-5-41 | CSJ: | 0160-05-041 |
Description: | FOR THE CONSTRUCTION OF TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | US 277 | Fund Cat: | 1 |
Limits To: | AT THE INTERSECTION OF US 377 | Estimate: | $19,772 |
Length: | 0.1 Miles | Actual: | $15,757 |
District: | Laredo | Let Date: | JUN 2003 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | C 299-1-57 | CSJ: | 0299-01-057 |
Description: | FOR THE CONSTRUCTION OF TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | US 277 | Fund Cat: | 1 |
Limits To: | AT THE INTERSECTION OF FM 317 | Estimate: | $20,258 |
Length: | 0.1 Miles | Actual: | $17,163 |
Bid Tabulations Back... |
Totals for 0022-07-024 | ||
---|---|---|---|
Length: | 0.3 Miles | ||
Estimate: | $93,000 | ||
Actual: | $73,577 | ||
CCSJ: 0412-05-032 | |||
District: | Laredo | Let Date: | APR 2003 |
Highway: | SH 163 | Let Status: | Actual |
Project ID: | STP 2003(399) | CSJ: | 0412-05-032 |
Description: | THE UP GRADING OF A NON FREEWAY FACILITY | Handling Code: |
|
Limits From: | CROCKETT C/L | Fund Cat: | 1 |
Limits To: | RM 189 | Estimate: | $3,784,621 |
Length: | 8.8 Miles | Actual: | $3,295,240 |
Back... |
Totals for 0412-05-032 | ||
Length: | 8.8 Miles | ||
Estimate: | $3,784,621 | ||
Actual: | $3,295,240 |
|
|