Detail Letting Schedule for Waller County (FY 2003)

 
 
Last Update: Thursday, August 28, 2003
Waller County (FY 2003)

CCSJ: 0409-02-021

District: Houston Let Date: APR 2003
Highway: SH 159 Let Status: Actual
Project ID: BR 2001(297) CSJ: 0409-02-021
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: AT BRAZOS RIVER Fund Cat: 6
Limits To: . Estimate: $5,975,366
Length: 1.0 Miles Actual: $7,552,113
 
Back...

Totals for 0409-02-021
Length: 1.0 Miles
Estimate: $5,975,366
Actual: $7,552,113

CCSJ: 0523-02-028

District: Houston Let Date: NOV 2002
Highway: FM 362 Let Status: Actual
Project ID: STP 2003(41) CSJ: 0523-02-028
Description: ACP OVERLAY, BASE REPAIR, WIDEN SUBGRADE AND PAVEMENT Handling
Code:
 
Limits From: BU US 290 SOUTH 250 FEET Fund Cat: 1
Limits To: BU US 290 SOUTH 4,093 FEET Estimate: $546,818
Length: 0.7 Miles Actual: $409,806
 
Back...

Totals for 0523-02-028
Length: 0.7 Miles
Estimate: $546,818
Actual: $409,806

CCSJ: 0944-02-008

District: Houston Let Date: JAN 2003
Highway: FM 362 Let Status: Actual
Project ID: CPM 944-2-8 CSJ: 0944-02-008
Description: BASE REPAIR, SUBGRADE WIDENING, PLANING, ASPHALTIC SURFACE Handling
Code:
 
Limits From: GRIMES C/L Fund Cat: 1
Limits To: FM 1488 Estimate: $1,405,991
Length: 5.7 Miles Actual: $1,101,864
 
Back...

Totals for 0944-02-008
Length: 5.7 Miles
Estimate: $1,405,991
Actual: $1,101,864

CCSJ: 1687-02-007

District: Houston Let Date: FEB 2003
Highway: FM 1736 Let Status: Actual
Project ID: CPM 1687-2-7 CSJ: 1687-02-007
Description: SEAL COAT Handling
Code:
 
Limits From: SH 6 Fund Cat: 1
Limits To: FM 1488 Estimate: $1,043,363
Length: 9.1 Miles Actual: $908,094
 
Back...

Totals for 1687-02-007
Length: 9.1 Miles
Estimate: $1,043,363
Actual: $908,094

CCSJ: 1745-01-017

District: Houston Let Date: JAN 2003
Highway: FM 1887 Let Status: Actual
Project ID: CPM 1745-1-17 CSJ: 1745-01-017
Description: BASE REPAIR, PLANING, ASPHALT SURFACE REHABILITATION, Handling
Code:
 
Limits From: SH 159 Fund Cat: 1
Limits To: HAMILTON STREET Estimate: $365,387
Length: 1.1 Miles Actual: $285,122
 
Back...

Totals for 1745-01-017
Length: 1.1 Miles
Estimate: $365,387
Actual: $285,122

CCSJ: 3047-02-009

District: Houston Let Date: JAN 2003
Highway: FM 529 Let Status: Actual
Project ID: STP 2003(183) CSJ: 3047-02-009
Description: ACP REHAB AND OVERLAY, BASE REPAIR, PLANING AND Handling
Code:
 
Limits From: BRAZOS RIVER Fund Cat: 1
Limits To: FM 362 Estimate: $1,474,183
Length: 9.4 Miles Actual: $1,085,646
 
Back...

Totals for 3047-02-009
Length: 9.4 Miles
Estimate: $1,474,183
Actual: $1,085,646

CCSJ: 3051-01-005

District: Houston Let Date: JAN 2003
Highway: FM 2979 Let Status: Actual
Project ID: CPM 3051-1-5 CSJ: 3051-01-005
Description: SEAL COAT Handling
Code:
 
Limits From: SH 6 Fund Cat: 1
Limits To: FM 362 Estimate: $748,787
Length: 7.7 Miles Actual: $685,824
 
Back...

Totals for 3051-01-005
Length: 7.7 Miles
Estimate: $748,787
Actual: $685,824

CCSJ: 3445-01-006

District: Houston Let Date: JAN 2003
Highway: FM 3346 Let Status: Actual
Project ID: CPM 3445-1-6 CSJ: 3445-01-006
Description: BASE REPAIR, PLANING, ASPHALT CONCRETE PAVEMENT OVERLAY AND Handling
Code:
 
Limits From: SH 159 Fund Cat: 1
Limits To: FM 359 Estimate: $777,930
Length: 4.1 Miles Actual: $475,024
 
Back...

Totals for 3445-01-006
Length: 4.1 Miles
Estimate: $777,930
Actual: $475,024

CCSJ: 3506-02-004

District: Houston Let Date: MAR 2003
Highway: FM 3318 Let Status: Actual
Project ID: CPM 3506-2-4 CSJ: 3506-02-004
Description: BASE REPAIR, PLANING, ASPHALT SURFACE REHABILITATION, Handling
Code:
 
Limits From: FM 1458 Fund Cat: 1
Limits To: END OF MAINTENANCE Estimate: $321,965
Length: 2.2 Miles Actual: $272,929
 
Back...

Totals for 3506-02-004
Length: 2.2 Miles
Estimate: $321,965
Actual: $272,929


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract