Detail Letting Schedule for Bosque County (FY 2004)

 
 
Last Update: Tuesday, August 17, 2004
Bosque County (FY 2004)

CCSJ: 0120-03-026

District: Waco Let Date: JAN 2004
Highway: SH 22 Let Status: Actual
Project ID: C 120-3-26 CSJ: 0120-03-026
Description: CONSTRUCTION OF SCENIC ENHANCEMENT CONSISTING OF RETAINING Handling
Code:
 
Limits From: @ SH 6 INTERSECTION Fund Cat: 10
Limits To: . Estimate: $18,609
Length: 0.1 Miles Actual: $15,300
 
District: Waco Let Date: JAN 2004
Highway: SH 22 Let Status: Actual
Project ID: C 121-1-41 CSJ: 0121-01-041
Description: CONSTRUCTION OF SCENIC ENHANCEMENT CONSISTING OF RETAINING Handling
Code:
 
Limits From: @ SH 6 INTERSECTION Fund Cat: 10
Limits To: . Estimate: $106,227
Length: 0.2 Miles Actual: $85,450
 
Back...

Totals for 0120-03-026
Length: 0.3 Miles
Estimate: $124,836
Actual: $100,750

CCSJ: 0121-01-036

District: Waco Let Date: MAY 2004
Highway: SH 22 Let Status: Actual
Project ID: STP 2002(298) CSJ: 0121-01-036
Description: INTERSECTION REHABILITATION / RADIUS CAPACITY IMPROVEMENT Handling
Code:
 
Limits From: AT SH 174 Fund Cat: 1
Limits To: IN MERIDIAN Estimate: $304,088
Length: 0.1 Miles Actual: $398,839
 
District: Waco Let Date: MAY 2004
Highway: FM 933 Let Status: Actual
Project ID: STP 2002(298) CSJ: 0121-12-009
Description: INTERSECTION REHABILITATION / RADIUS CAPACITY IMPROVEMENT Handling
Code:
 
Limits From: AT JEFFERSON ST Fund Cat: 1
Limits To: IN WHITNEY Estimate: $255,590
Length: 0.1 Miles Actual: $295,938
 
District: Waco Let Date: MAY 2004
Highway: SH 6 Let Status: Actual
Project ID: STP 2002(298) CSJ: 0258-06-031
Description: INTERSECTION REHABILITATION / RADIUS CAPACITY IMPROVEMENT Handling
Code:
 
Limits From: AT FM 219 Fund Cat: 1
Limits To: IN CLIFTON Estimate: $213,198
Length: 0.0 Miles Actual: $258,388
 
District: Waco Let Date: MAY 2004
Highway: SH 6 Let Status: Actual
Project ID: STP 2002(298) CSJ: 0258-07-041
Description: INTERSECTION REHABILITATION / RADIUS CAPACITY IMPROVEMENT Handling
Code:
 
Limits From: AT FM 219 Fund Cat: 1
Limits To: IN CLIFTON Estimate: $281,803
Length: 0.1 Miles Actual: $335,050
 
District: Waco Let Date: MAY 2004
Highway: SH 174 Let Status: Actual
Project ID: STP 2002(298) CSJ: 0519-03-025
Description: INTERSECTION REHABILITATION / RADIUS CAPACITY IMPROVEMENT Handling
Code:
 
Limits From: AT FM 2840 Fund Cat: 1
Limits To: IN MERIDIAN Estimate: $93,991
Length: 0.1 Miles Actual: $130,558
 
Back...

Totals for 0121-01-036
Length: 0.4 Miles
Estimate: $1,148,670
Actual: $1,418,773


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract