Detail Letting Schedule for Dallam County (FY 2004)

 
 
Last Update: Tuesday, August 17, 2004
Dallam County (FY 2004)

CCSJ: 0040-01-029

District: Amarillo Let Date: JAN 2004
Highway: US 87 Let Status: Actual
Project ID: NH 2002(564) CSJ: 0040-01-029
Description: RECONSTRUCT AND ADD 2 LANES Handling
Code:
 
Limits From: NEW MEXICO STATE LINE Fund Cat: 4
Limits To: 3.6 MI NW OF FM 3110 Estimate: $11,186,991
Length: 8.7 Miles Actual: $12,297,259
 
District: Amarillo Let Date: JAN 2004
Highway: US 87 Let Status: Actual
Project ID: RW 40-1-31 CSJ: 0040-01-031
Description: RIGHT OF WAY ACQUISITION, UTILITY ADJUSTMENTS & RELOCATION Handling
Code:
 
Limits From: NEW MEXICO STATE LINE Fund Cat: ROW
Limits To: 3.6 MI NW OF FM 3110 Estimate: $15,417
Length: 0.0 Miles Actual: $39,098
 
District: Amarillo Let Date: JAN 2004
Highway: US 87 Let Status: Actual
Project ID: NH 2002(564) CSJ: 0040-01-032
Description: RECONSTRUCT AND ADD 2 LANES Handling
Code:
 
Limits From: 0.732 MI NW OF NEW MEXICO STATE LIN Fund Cat: 11
Limits To: TEXAS STATE LINE Estimate: $678,439
Length: 0.7 Miles Actual: $747,901
 
District: Amarillo Let Date: JAN 2004
Highway: US 87 Let Status: Actual
Project ID: BR 2004(179) CSJ: 0040-01-033
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: AT RITA BLANCO CREEK Fund Cat: 6
Limits To: . Estimate: $509,174
Length: 0.1 Miles Actual: $665,314
 
Back...

Totals for 0040-01-029
Length: 9.5 Miles
Estimate: $12,390,021
Actual: $13,749,572


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract