Detail Letting Schedule for Haskell County (FY 2004)
| Detail Letting Schedule for Haskell County (FY 2004) | ||||
| Last Update: Tuesday, August 17, 2004 |
| Haskell County (FY 2004) |
CCSJ: 0157-03-041 | |||
| District: | Abilene | Let Date: | MAY 2004 |
| Highway: | US 277 | Let Status: | Actual |
| Project ID: | MG 2004(364) | CSJ: | 0157-03-041 |
| Description: | ACP OVERLAY & UNDERSEAL | Handling Code: |
|
| Limits From: | LAKE CK BRIDGE | Fund Cat: | 11 |
| Limits To: | 11.2 MI SOUTH | Estimate: | $4,259,998 |
| Length: | 11.2 Miles | Actual: | $3,163,552 |
|
Back... |
Totals for 0157-03-041 | ||
|---|---|---|---|
| Length: | 11.2 Miles | ||
| Estimate: | $4,259,998 | ||
| Actual: | $3,163,552 | ||
CCSJ: 0157-09-001 | |||
| District: | Abilene | Let Date: | AUG 2004 |
| Highway: | US 277 | Let Status: | Approved |
| Project ID: | NH 2004(515) | CSJ: | 0157-09-001 |
| Description: | RELOCATE AND RECONTRUCT EXISTING HIGHWAY TO A 4 - LANE | Handling Code: |
|
| Limits From: | US 277 SOUTH OF HASKELL | Fund Cat: | 10 |
| Limits To: | US 277 NORTH OF HASKELL | Estimate: | $16,782,373 |
| Length: | 4.9 Miles | Actual: | |
|
List Showing Order Bidders List Bid Tabulations Proposal Req Form Back... |
Totals for 0157-09-001 | ||
| Length: | 4.9 Miles | ||
| Estimate: | $16,782,373 | ||
| Actual: | |||
CCSJ: 2031-04-001 | |||
| District: | Abilene | Let Date: | SEP 2003 |
| Highway: | FM 3337 | Let Status: | Actual |
| Project ID: | C 2031-4-1 | CSJ: | 2031-04-001 |
| Description: | CONSTRUCT NEW FARM TO MARKET ROAD | Handling Code: |
|
| Limits From: | FM 2407 | Fund Cat: | 4 |
| Limits To: | FM 2163 | Estimate: | $830,946 |
| Length: | 2.2 Miles | Actual: | $668,283 |
|
Back... |
Totals for 2031-04-001 | ||
| Length: | 2.2 Miles | ||
| Estimate: | $830,946 | ||
| Actual: | $668,283 | ||
|
| |