Detail Letting Schedule for Panola County (FY 2004)
| Detail Letting Schedule for Panola County (FY 2004) | ||||
| Last Update: Tuesday, August 17, 2004 |
| Panola County (FY 2004) |
CCSJ: 0063-02-028 | |||
| District: | Atlanta | Let Date: | MAY 2004 |
| Highway: | FM 1186 | Let Status: | Actual |
| Project ID: | BR 2004(367) | CSJ: | 0063-02-028 |
| Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
| Limits From: | AT CADDO CREEK | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $1,093,722 |
| Length: | 0.3 Miles | Actual: | $1,198,559 |
|
Back... |
Totals for 0063-02-028 | ||
|---|---|---|---|
| Length: | 0.3 Miles | ||
| Estimate: | $1,093,722 | ||
| Actual: | $1,198,559 | ||
CCSJ: 0247-03-021 | |||
| District: | Atlanta | Let Date: | AUG 2004 |
| Highway: | US 79 | Let Status: | Approved |
| Project ID: | STP 2004(457)HES | CSJ: | 0247-03-021 |
| Description: | SAFETY TREAT FIXED OBJECTS | Handling Code: |
|
| Limits From: | FM 31 | Fund Cat: | 8 |
| Limits To: | LOUISIANA STATE LINE | Estimate: | $242,645 |
| Length: | 8.8 Miles | Actual: | |
|
List Showing Order Bidders List Bid Tabulations Proposal Req Form Back... |
Totals for 0247-03-021 | ||
| Length: | 8.8 Miles | ||
| Estimate: | $242,645 | ||
| Actual: | |||
CCSJ: 0394-03-030 | |||
| District: | Atlanta | Let Date: | NOV 2003 |
| Highway: | FM 699 | Let Status: | Actual |
| Project ID: | STP 2003(370) | CSJ: | 0394-03-030 |
| Description: | REHABILITATE EXISTING 2 - LANE RURAL HIGHWAY | Handling Code: |
|
| Limits From: | US 59 IN CARTHAGE | Fund Cat: | 11 |
| Limits To: | FM 2517 | Estimate: | $1,388,299 |
| Length: | 3.8 Miles | Actual: | $1,282,553 |
|
Back... |
Totals for 0394-03-030 | ||
| Length: | 3.8 Miles | ||
| Estimate: | $1,388,299 | ||
| Actual: | $1,282,553 | ||
CCSJ: 2239-01-018 | |||
| District: | Atlanta | Let Date: | FEB 2004 |
| Highway: | FM 2517 | Let Status: | Actual |
| Project ID: | C 2239-1-18 | CSJ: | 2239-01-018 |
| Description: | REHABILITATE AND WIDEN EXISTING 2 - LANE RURAL HIGHWAY | Handling Code: |
|
| Limits From: | FM 699 | Fund Cat: | 1 |
| Limits To: | SABINE RIVER | Estimate: | $1,867,009 |
| Length: | 4.4 Miles | Actual: | $1,544,075 |
|
Back... |
Totals for 2239-01-018 | ||
| Length: | 4.4 Miles | ||
| Estimate: | $1,867,009 | ||
| Actual: | $1,544,075 | ||
|
| |