Detail Letting Schedule for Nueces County (FY 2005)
Detail Letting Schedule for Nueces County (FY 2005) | ||||
Last Update: Monday, August 15, 2005 |
Nueces County (FY 2005) |
CCSJ: 0074-06-201 | |||
District: | Corpus Christi | Let Date: | FEB 2005 |
Highway: | IH 37 | Let Status: | Actual |
Project ID: | IM 37-1(126) | CSJ: | 0074-06-201 |
Description: | IMPROVEMENT OF CONNECTOR RAMP FROM NORTHBOUND IH 37 TO | Handling Code: |
|
Limits From: | AT INTERCHANGE OF IH 37 & US 77 | Fund Cat: | 1 |
Limits To: | . | Estimate: | $7,147,558 |
Length: | 0.5 Miles | Actual: | $8,894,284 |
Back... |
Totals for 0074-06-201 | ||
---|---|---|---|
Length: | 0.5 Miles | ||
Estimate: | $7,147,558 | ||
Actual: | $8,894,284 | ||
CCSJ: 0074-06-210 | |||
District: | Corpus Christi | Let Date: | AUG 2005 |
Highway: | US 181 | Let Status: | Actual |
Project ID: | C 74-6-210 | CSJ: | 0074-06-210 |
Description: | LANDSCAPE | Handling Code: |
|
Limits From: | MESQUITE ST. | Fund Cat: | 10 |
Limits To: | BROADWAY | Estimate: | $23,370 |
Length: | 0.0 Miles | Actual: | $32,862 |
District: | Corpus Christi | Let Date: | AUG 2005 |
Highway: | SH 358 | Let Status: | Actual |
Project ID: | C 617-1-166 | CSJ: | 0617-01-166 |
Description: | LANDSCAPE ESTABLISHMENT | Handling Code: |
|
Limits From: | AT SH 358/ PR 22 INTERCHANGE | Fund Cat: | 10 |
Limits To: | . | Estimate: | $51,000 |
Length: | 0.2 Miles | Actual: | $67,000 |
List Showing Order Proposal Req Form Bidders List Bid Tabulations Back... |
Totals for 0074-06-210 | ||
Length: | 0.2 Miles | ||
Estimate: | $74,370 | ||
Actual: | $99,862 | ||
CCSJ: 0102-11-011 | |||
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | BU 77-V | Let Status: | Actual |
Project ID: | CPM 102-11-11 | CSJ: | 0102-11-011 |
Description: | SEAL COAT ROADWAY (FY 05 S. LOW CONTROL SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | US 77 (NORTH "Y") | Fund Cat: | 1 |
Limits To: | KELBERG CO. LINE | Estimate: | $408,022 |
Length: | 4.8 Miles | Actual: | $445,232 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | BU 77-V | Let Status: | Actual |
Project ID: | CPM 102-12-30 | CSJ: | 0102-12-030 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | NUECES CO. LINE | Fund Cat: | 1 |
Limits To: | US 77 (SOUTH "Y") | Estimate: | $375,379 |
Length: | 8.7 Miles | Actual: | $347,122 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | CPM 254-1-126 | CSJ: | 0254-01-126 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | SH 72 | Fund Cat: | 1 |
Limits To: | IH 37 | Estimate: | $194,816 |
Length: | 4.0 Miles | Actual: | $195,299 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | CPM 254-3-72 | CSJ: | 0254-03-072 |
Description: | SEAL COAT ROADWAYS (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | LIVE OAK/JIM WELLS CO. LINE | Fund Cat: | 1 |
Limits To: | US 281 BYPASS | Estimate: | $308,125 |
Length: | 17.6 Miles | Actual: | $299,500 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | CPM 254-7-1 | CSJ: | 0254-07-001 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | BU 281 | Fund Cat: | 1 |
Limits To: | FM 625 | Estimate: | $448,092 |
Length: | 9.0 Miles | Actual: | $445,310 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | SH 72 | Let Status: | Actual |
Project ID: | CPM 483-4-34 | CSJ: | 0483-04-034 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | MCMULLEN CO. LINE | Fund Cat: | 1 |
Limits To: | US 281 | Estimate: | $257,703 |
Length: | 9.6 Miles | Actual: | $255,799 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | SH 358 | Let Status: | Actual |
Project ID: | CPM 617-1-168 | CSJ: | 0617-01-168 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) FRTG RD. | Handling Code: |
|
Limits From: | LEOPARD ST. | Fund Cat: | 1 |
Limits To: | GREENWOOD | Estimate: | $226,237 |
Length: | 4.8 Miles | Actual: | $207,172 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 624 | Let Status: | Actual |
Project ID: | CPM 989-2-42 | CSJ: | 0989-02-042 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | FM 70 | Fund Cat: | 1 |
Limits To: | 0.931 MI. WEST OF FM 666 | Estimate: | $193,222 |
Length: | 5.3 Miles | Actual: | $179,644 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 1546 | Let Status: | Actual |
Project ID: | CPM 992-2-9 | CSJ: | 0992-02-009 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | FM 628 | Fund Cat: | 1 |
Limits To: | END OF MAINT. SECTION | Estimate: | $44,637 |
Length: | 3.8 Miles | Actual: | $46,147 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 665 | Let Status: | Actual |
Project ID: | CPM 1052-2-72 | CSJ: | 1052-02-072 |
Description: | SEAL COAT ROADWAY (PROJECT TO REPLACE FM43 - 05 PROJECT) | Handling Code: |
|
Limits From: | FM 43 | Fund Cat: | 1 |
Limits To: | CR 49A | Estimate: | $149,000 |
Length: | 6.1 Miles | Actual: | |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 2044 | Let Status: | Actual |
Project ID: | CPM 1086-1-17 | CSJ: | 1086-01-017 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | US 281 | Fund Cat: | 1 |
Limits To: | FM 1539 | Estimate: | $174,305 |
Length: | 11.1 Miles | Actual: | $179,807 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 892 | Let Status: | Actual |
Project ID: | CPM 1088-4-22 | CSJ: | 1088-04-022 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | US 77 | Fund Cat: | 1 |
Limits To: | FM 665 | Estimate: | $79,111 |
Length: | 7.1 Miles | Actual: | $81,846 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 763 | Let Status: | Actual |
Project ID: | CPM 1093-1-26 | CSJ: | 1093-01-026 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | SH 44 | Fund Cat: | 1 |
Limits To: | FM 43 | Estimate: | $127,784 |
Length: | 7.1 Miles | Actual: | $132,079 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 888 | Let Status: | Actual |
Project ID: | CPM 1207-2-20 | CSJ: | 1207-02-020 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | FM 3190 | Fund Cat: | 1 |
Limits To: | END OF STATE MAINT. | Estimate: | $94,082 |
Length: | 7.1 Miles | Actual: | $96,948 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 2044 | Let Status: | Actual |
Project ID: | CPM 1472-1-17 | CSJ: | 1472-01-017 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | FM 1539 | Fund Cat: | 1 |
Limits To: | SH 44 | Estimate: | $20,350 |
Length: | 1.8 Miles | Actual: | $21,010 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 1042 | Let Status: | Actual |
Project ID: | CPM 1553-1-11 | CSJ: | 1553-01-011 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | FM 1545 | Fund Cat: | 1 |
Limits To: | US 281 | Estimate: | $145,651 |
Length: | 8.7 Miles | Actual: | $150,604 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 1545 | Let Status: | Actual |
Project ID: | CPM 1553-2-6 | CSJ: | 1553-02-006 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | SH 72 | Fund Cat: | 1 |
Limits To: | SH 72 | Estimate: | $88,291 |
Length: | 6.3 Miles | Actual: | $90,889 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 1040 | Let Status: | Actual |
Project ID: | CPM 1554-2-8 | CSJ: | 1554-02-008 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | FM 888 | Fund Cat: | 1 |
Limits To: | END STATE MAINT. | Estimate: | $15,025 |
Length: | 1.1 Miles | Actual: | $15,480 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 70 | Let Status: | Actual |
Project ID: | CPM 1558-2-30 | CSJ: | 1558-02-030 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | SH 44 | Fund Cat: | 1 |
Limits To: | BU 77-V | Estimate: | $341,099 |
Length: | 18.8 Miles | Actual: | $347,095 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 70 | Let Status: | Actual |
Project ID: | CPM 1558-3-24 | CSJ: | 1558-03-024 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | BU 77-V | Fund Cat: | 1 |
Limits To: | JOINT NEAR PETRONILLA CREEK | Estimate: | $207,398 |
Length: | 10.1 Miles | Actual: | $207,884 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 2444 | Let Status: | Actual |
Project ID: | CPM 2342-1-29 | CSJ: | 2343-01-029 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | BEGIN SHOULDER SECTION | Fund Cat: | 1 |
Limits To: | 0.2 MI. S. OF OSO CREEK | Estimate: | $138,984 |
Length: | 8.9 Miles | Actual: | $135,422 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 2619 | Let Status: | Actual |
Project ID: | CPM 2609-1-6 | CSJ: | 2609-01-006 |
Description: | SEAL COAT ROADWAY_ (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | FM 1717 | Fund Cat: | 1 |
Limits To: | FM 1118 | Estimate: | $36,781 |
Length: | 2.7 Miles | Actual: | $38,282 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 3088 | Let Status: | Actual |
Project ID: | CPM 3176-1-8 | CSJ: | 3176-01-008 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | FM 70 | Fund Cat: | 1 |
Limits To: | FM 666 | Estimate: | $89,399 |
Length: | 5.3 Miles | Actual: | $92,414 |
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 3320 | Let Status: | Actual |
Project ID: | CPM 3511-1-7 | CSJ: | 3511-01-007 |
Description: | SEAL COAT ROADWAY (2005 S. SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | FM 425 | Fund Cat: | 1 |
Limits To: | FM 1717 | Estimate: | $26,751 |
Length: | 2.0 Miles | Actual: | $27,769 |
Back... |
Totals for 0102-11-011 | ||
Length: | 171.8 Miles | ||
Estimate: | $4,190,244 | ||
Actual: | $4,038,754 | ||
CCSJ: 0373-05-026 | |||
District: | Corpus Christi | Let Date: | MAY 2005 |
Highway: | BS 44-C | Let Status: | Actual |
Project ID: | STP 2005(273) | CSJ: | 0373-05-026 |
Description: | REHABILITATE ROADWAY | Handling Code: |
|
Limits From: | BU 77-U | Fund Cat: | 1 |
Limits To: | BUENA VISTA ST. | Estimate: | $1,824,987 |
Length: | 0.7 Miles | Actual: | $1,987,150 |
District: | Corpus Christi | Let Date: | MAY 2005 |
Highway: | BS 44-C | Let Status: | Actual |
Project ID: | STP 2005(298) | CSJ: | 0373-05-028 |
Description: | REHAB. ROADWAY | Handling Code: |
|
Limits From: | US 77 | Fund Cat: | 1 |
Limits To: | 9TH STREET | Estimate: | $539,472 |
Length: | 0.1 Miles | Actual: | $683,146 |
District: | Corpus Christi | Let Date: | MAY 2005 |
Highway: | BS 44-C | Let Status: | Actual |
Project ID: | STP 2005(273) | CSJ: | 0373-05-029 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: |
|
Limits From: | BUENA VISTA ST | Fund Cat: | 1 |
Limits To: | SH 44 | Estimate: | $88,819 |
Length: | 0.9 Miles | Actual: | $187,330 |
Back... |
Totals for 0373-05-026 | ||
Length: | 1.7 Miles | ||
Estimate: | $2,453,278 | ||
Actual: | $2,857,626 | ||
CCSJ: 0617-01-167 | |||
District: | Corpus Christi | Let Date: | FEB 2005 |
Highway: | SH 358 | Let Status: | Actual |
Project ID: | C 617-1-167 | CSJ: | 0617-01-167 |
Description: | CONSTRUCTION OF TRAF. MGMT CENTER | Handling Code: |
|
Limits From: | AT CORPUS CHRISTI DIST. COMPLEX | Fund Cat: | 11 |
Limits To: | . | Estimate: | $505,000 |
Length: | 0.1 Miles | Actual: | $498,699 |
Back... |
Totals for 0617-01-167 | ||
Length: | 0.1 Miles | ||
Estimate: | $505,000 | ||
Actual: | $498,699 | ||
CCSJ: 0916-35-074 | |||
District: | Corpus Christi | Let Date: | SEP 2004 |
Highway: | CS | Let Status: | Actual |
Project ID: | BR 99(576) | CSJ: | 0916-35-074 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | STR(B00155001) BEAR LN @ DRAINAGE D | Fund Cat: | 6 |
Limits To: | APPROX 1.0 MI W OF SH 358__________ | Estimate: | $438,618 |
Length: | 0.1 Miles | Actual: | $467,548 |
Back... |
Totals for 0916-35-074 | ||
Length: | 0.1 Miles | ||
Estimate: | $438,618 | ||
Actual: | $467,548 | ||
CCSJ: 0916-35-088 | |||
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | VA | Let Status: | Actual |
Project ID: | FBD 2001(586) | CSJ: | 0916-35-088 |
Description: | CONSTR WATERFRONT PASS FERRY & TERMINAL | Handling Code: |
LC |
Limits From: | AT THE PORT OF CORPUS CHRISTI | Fund Cat: | 10 |
Limits To: | . | Estimate: | $1,623,080 |
Length: | 0.0 Miles | Actual: | $2,119,846 |
Back... |
Totals for 0916-35-088 | ||
Length: | 0.0 Miles | ||
Estimate: | $1,623,080 | ||
Actual: | $2,119,846 | ||
CCSJ: 0916-35-094 | |||
District: | Corpus Christi | Let Date: | MAY 2005 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2002(510) | CSJ: | 0916-35-094 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | STR 2(AA0214002) CR 24 @ DRAINAGE D | Fund Cat: | 6 |
Limits To: | APPROX 1.6 MI W OF FM 892 | Estimate: | $273,563 |
Length: | 0.1 Miles | Actual: | $272,406 |
District: | Corpus Christi | Let Date: | MAY 2005 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2004(300) | CSJ: | 0916-35-122 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | STR 3(AA0214003) CR 24 @ DRAINAGE D | Fund Cat: | 6 |
Limits To: | 1.70 MI. E. OF US 77 | Estimate: | $323,168 |
Length: | 0.1 Miles | Actual: | $303,284 |
District: | Corpus Christi | Let Date: | MAY 2005 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2004(299) | CSJ: | 0916-35-130 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | STR2 (AA0175002) CR85 CARRETA CRK | Fund Cat: | 6 |
Limits To: | 1.10 MI S OF FM 70 | Estimate: | $253,744 |
Length: | 0.1 Miles | Actual: | $253,450 |
Back... |
Totals for 0916-35-094 | ||
Length: | 0.3 Miles | ||
Estimate: | $850,475 | ||
Actual: | $829,140 | ||
CCSJ: 0989-02-041 | |||
District: | Corpus Christi | Let Date: | APR 2005 |
Highway: | FM 624 | Let Status: | Actual |
Project ID: | STP 2005(325)MM | CSJ: | 0989-02-041 |
Description: | REHAB. ROADWAY AND ADD MEDIANS AND TRAFFIC CONTROL DEVICES | Handling Code: |
|
Limits From: | US 77 | Fund Cat: | 1 |
Limits To: | RIVER HILL ROAD | Estimate: | $5,087,533 |
Length: | 1.3 Miles | Actual: | $5,532,210 |
Back... |
Totals for 0989-02-041 | ||
Length: | 1.3 Miles | ||
Estimate: | $5,087,533 | ||
Actual: | $5,532,210 | ||
CCSJ: 1052-02-071 | |||
District: | Corpus Christi | Let Date: | NOV 2004 |
Highway: | FM 665 | Let Status: | Actual |
Project ID: | CPM 1052-2-71 | CSJ: | 1052-02-071 |
Description: | OVERLAY ROADWAY | Handling Code: |
|
Limits From: | APPROX. 1250' NORTH OF SH 357 | Fund Cat: | 1 |
Limits To: | SH 358 | Estimate: | $452,706 |
Length: | 2.0 Miles | Actual: | $527,217 |
Back... |
Totals for 1052-02-071 | ||
Length: | 2.0 Miles | ||
Estimate: | $452,706 | ||
Actual: | $527,217 | ||
CCSJ: 1558-01-017 | |||
District: | Corpus Christi | Let Date: | MAY 2005 |
Highway: | FM 70 | Let Status: | Actual |
Project ID: | STP 2005(379) | CSJ: | 1558-01-017 |
Description: | WIDEN PAVEMENT ON CURVES (AT VARIOUS LOCATIONS ON FM 70) | Handling Code: |
|
Limits From: | 1.2 MI SOUTH OF FM 1833 | Fund Cat: | 1 |
Limits To: | FM 1833 | Estimate: | $517,142 |
Length: | 1.1 Miles | Actual: | $551,879 |
Back... |
Totals for 1558-01-017 | ||
Length: | 1.1 Miles | ||
Estimate: | $517,142 | ||
Actual: | $551,879 | ||
CCSJ: 1558-03-023 | |||
District: | Corpus Christi | Let Date: | JAN 2005 |
Highway: | FM 70 | Let Status: | Actual |
Project ID: | CC 1558-3-23 | CSJ: | 1558-03-023 |
Description: | CONSTRUCT DRAINAGE CULVERT | Handling Code: |
|
Limits From: | AT LANDFILL DRAINAGE DITCH, 8.286 M | Fund Cat: | 10 |
Limits To: | OF SH 286 | Estimate: | $825,496 |
Length: | 0.5 Miles | Actual: | $923,565 |
Back... |
Totals for 1558-03-023 | ||
Length: | 0.5 Miles | ||
Estimate: | $825,496 | ||
Actual: | $923,565 | ||
CCSJ: 2263-02-078 | |||
District: | Corpus Christi | Let Date: | MAR 2005 |
Highway: | SH 361 | Let Status: | Actual |
Project ID: | STP 2004(665) | CSJ: | 2263-02-078 |
Description: | CONSTR NEW FERRY LANDINGS AND APPROACHES | Handling Code: |
|
Limits From: | 0.25 MI N OF HARBOR ISLAND FERRY LA | Fund Cat: | 11 |
Limits To: | 0.1 MI S OF MUSTANG ISLAND FERRY LA | Estimate: | $3,996,767 |
Length: | 0.1 Miles | Actual: | $4,597,629 |
Back... |
Totals for 2263-02-078 | ||
Length: | 0.1 Miles | ||
Estimate: | $3,996,767 | ||
Actual: | $4,597,629 |
|
|