Detail Letting Schedule for Rockwall County (FY 2005)
|
Detail Letting Schedule for Rockwall County (FY 2005) |
|
Last Update: Monday, August 15, 2005 |
Rockwall County (FY 2005) |
CCSJ: 0009-04-057
|
District: |
Dallas |
Let Date: |
OCT 2004 |
Highway: |
SH 66 |
Let Status: |
Actual |
Project ID: |
C 9-4-57 |
CSJ: |
0009-04-057 |
Description: |
LANDSCAPE DEVELOPMENT |
Handling Code: |
|
Limits From: |
LAKE RAY HUBBARD |
Fund Cat: |
10 |
Limits To: |
SH 205 |
Estimate: |
$198,710 |
Length: |
0.7 Miles |
Actual: |
$161,538 |
|
Back...
|
Totals for 0009-04-057 |
Length: |
0.7 Miles |
Estimate: |
$198,710 |
Actual: |
$161,538 |
CCSJ: 0009-12-067
|
District: |
Dallas |
Let Date: |
JUN 2005 |
Highway: |
IH 30 |
Let Status: |
Actual |
Project ID: |
IM 0301(048) |
CSJ: |
0009-12-067 |
Description: |
ADD NEW EXIT RAMP |
Handling Code: |
|
Limits From: |
1.2 MI EAST OF FM 551 |
Fund Cat: |
11 |
Limits To: |
1.4 MI EAST OF FM 551 |
Estimate: |
$341,389 |
Length: |
0.2 Miles |
Actual: |
$371,322 |
|
Bid Tabulations Back...
|
Totals for 0009-12-067 |
Length: |
0.2 Miles |
Estimate: |
$341,389 |
Actual: |
$371,322 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|