Detail Letting Schedule for Throckmorton County (FY 2005)
|
Detail Letting Schedule for Throckmorton County (FY 2005) |
|
Last Update: Monday, August 15, 2005 |
Throckmorton County (FY 2005) |
CCSJ: 0361-01-025
|
District: |
Wichita Falls |
Let Date: |
DEC 2004 |
Highway: |
US 380 |
Let Status: |
Actual |
Project ID: |
STP 2005(51) |
CSJ: |
0361-01-025 |
Description: |
ADD SHOULDERS, REPLACE BRIDGE AND APPROACHES |
Handling Code: |
|
Limits From: |
NEAR ELM CREEK |
Fund Cat: |
1 |
Limits To: |
YOUNG COUNTY LINE AND RELIEF & DRAW |
Estimate: |
$4,101,820 |
Length: |
7.3 Miles |
Actual: |
$4,535,780 |
|
District: |
Wichita Falls |
Let Date: |
DEC 2004 |
Highway: |
US 380 |
Let Status: |
Actual |
Project ID: |
BR 2005(52) |
CSJ: |
0361-01-029 |
Description: |
REPLACE BRIDGES AND APPROACHES |
Handling Code: |
|
Limits From: |
AT ELM CREEK BRIDGE |
Fund Cat: |
6 |
Limits To: |
. |
Estimate: |
$484,342 |
Length: |
0.0 Miles |
Actual: |
$784,809 |
|
Back...
|
Totals for 0361-01-025 |
Length: |
7.3 Miles |
Estimate: |
$4,586,162 |
Actual: |
$5,320,589 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|