Detail Letting Schedule for Hutchinson County (FY 2006)
| |
| Detail Letting Schedule for Hutchinson County (FY 2006) |
| |
| Last Update: Monday, August 28, 2006 |
| Hutchinson County (FY 2006) |
CCSJ: 2437-01-017
|
| District: |
Amarillo |
Let Date: |
APR 2006 |
| Highway: |
RM 1319 |
Let Status: |
Actual |
| Project ID: |
STP 2005(910)SFT |
CSJ: |
2437-01-017 |
| Description: |
HAZARD ELIMINATION |
Handling Code: |
|
| Limits From: |
JCT SH 136 |
Fund Cat: |
11 |
| Limits To: |
1.2 MI SE OF ANTELOPE CREEK |
Estimate: |
$2,090,513 |
| Length: |
3.7 Miles |
Actual: |
$2,557,266 |
| |
| District: |
Amarillo |
Let Date: |
APR 2006 |
| Highway: |
RM 1319 |
Let Status: |
Actual |
| Project ID: |
C 2437-1-18 |
CSJ: |
2437-01-018 |
| Description: |
REPLACE BRIDGE & APPROACHES |
Handling Code: |
|
| Limits From: |
AT ANTELOPE CREEK |
Fund Cat: |
11 |
| Limits To: |
. |
Estimate: |
$715,557 |
| Length: |
0.1 Miles |
Actual: |
$1,067,728 |
| |
| District: |
Amarillo |
Let Date: |
APR 2006 |
| Highway: |
RM 1319 |
Let Status: |
Actual |
| Project ID: |
STP 2006(400) |
CSJ: |
2437-01-019 |
| Description: |
OVERLAY |
Handling Code: |
|
| Limits From: |
1.2 MI SE OF ANTELOPE CREEK |
Fund Cat: |
1 |
| Limits To: |
GROVER ST IN SANFORD |
Estimate: |
$540,797 |
| Length: |
2.6 Miles |
Actual: |
$628,414 |
| |
Back...
|
Totals for 2437-01-017 |
| Length: |
6.4 Miles |
| Estimate: |
$3,346,867 |
| Actual: |
$4,253,408 |
| Handling Code |
Definition |
| XX |
Project not processed through statewide letting |
| TR |
Transfer of funds |
| LC |
Project let through local entity |
| NC |
Project not charged against district apportionment |
| Let Status |
Definition |
| Tentative |
Estimated letting date for this project |
| Approved |
Project has administrative approval to be let |
| Actual |
Project was let to contract |
|