Detail Letting Schedule for Hamilton County (FY 2007)
Detail Letting Schedule for Hamilton County (FY 2007) | ||||
Last Update: Monday, July 30, 2007 |
Hamilton County (FY 2007) |
CCSJ: 0251-01-054 | |||
District: | Waco | Let Date: | NOV 2006 |
Highway: | SH 14 | Let Status: | Actual |
Project ID: | CPM 93-7-19 | CSJ: | 0093-07-019 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | LIMESTONE CO LINE | Fund Cat: | 1 |
Limits To: | ROBERTSON CO LINE | Estimate: | $277,605 |
Length: | 6.9 Miles | Actual: | $251,583 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | BS 36-E | Let Status: | Actual |
Project ID: | CPM 184-5-4 | CSJ: | 0184-05-004 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | US 84 (MAIN ST) | Fund Cat: | 1 |
Limits To: | SH 36 EAST | Estimate: | $61,717 |
Length: | 1.1 Miles | Actual: | $59,729 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | CPM 231-3-122 | CSJ: | 0231-03-122 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | WS YOUNG | Fund Cat: | 1 |
Limits To: | SP 439 | Estimate: | $560,884 |
Length: | 8.5 Miles | Actual: | $543,259 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | CPM 231-4-52 | CSJ: | 0231-04-052 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | SP 439 | Fund Cat: | 1 |
Limits To: | IH 35 | Estimate: | $594,443 |
Length: | 7.9 Miles | Actual: | $576,555 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | CPM 251-1-54 | CSJ: | 0251-01-054 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | FM 1602 | Fund Cat: | 1 |
Limits To: | SH 36 | Estimate: | $1,197,072 |
Length: | 19.9 Miles | Actual: | $978,686 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | SH 317 | Let Status: | Actual |
Project ID: | CPM 398-4-65 | CSJ: | 0398-04-065 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | MCLENNAN CO LINE | Fund Cat: | 1 |
Limits To: | SH 36 | Estimate: | $300,763 |
Length: | 8.3 Miles | Actual: | $288,820 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | SH 164 | Let Status: | Actual |
Project ID: | CPM 413-2-29 | CSJ: | 0413-02-029 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | MCLENNAN CO LINE | Fund Cat: | 1 |
Limits To: | WHITE ST IN GROESBECK | Estimate: | $400,535 |
Length: | 16.6 Miles | Actual: | $367,029 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | SH 171 | Let Status: | Actual |
Project ID: | CPM 419-2-38 | CSJ: | 0419-02-038 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | US 84 | Fund Cat: | 1 |
Limits To: | FM 73 | Estimate: | $517,965 |
Length: | 11.3 Miles | Actual: | $470,342 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | SH 174 | Let Status: | Actual |
Project ID: | CPM 519-2-20 | CSJ: | 0519-02-020 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | BOSQUE CO LINE | Fund Cat: | 1 |
Limits To: | JOHNSON CO LINE | Estimate: | $401,443 |
Length: | 9.4 Miles | Actual: | $385,329 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 3302 | Let Status: | Actual |
Project ID: | CPM 550-12-2 | CSJ: | 0550-12-002 |
Description: | EMULSION | Handling Code: |
|
Limits From: | US 281 | Fund Cat: | 1 |
Limits To: | FM 2005 | Estimate: | $46,197 |
Length: | 1.4 Miles | Actual: | $40,178 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 185 | Let Status: | Actual |
Project ID: | CPM 567-4-20 | CSJ: | 0567-04-020 |
Description: | EMULSION | Handling Code: |
|
Limits From: | LEONARD LANE | Fund Cat: | 1 |
Limits To: | CORYELL CO LINE | Estimate: | $159,407 |
Length: | 7.5 Miles | Actual: | $142,167 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 182 | Let Status: | Actual |
Project ID: | CPM 724-4-16 | CSJ: | 0724-04-016 |
Description: | EMULSION | Handling Code: |
|
Limits From: | SH 36 | Fund Cat: | 1 |
Limits To: | TURNERSVILLE | Estimate: | $198,619 |
Length: | 8.8 Miles | Actual: | $176,653 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 1637 | Let Status: | Actual |
Project ID: | CPM 833-3-42 | CSJ: | 0833-03-042 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | LAKE SHORE DRIVE | Fund Cat: | 1 |
Limits To: | COLLEGE DRIVE | Estimate: | $34,811 |
Length: | 0.6 Miles | Actual: | $33,638 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 3400 | Let Status: | Actual |
Project ID: | CPM 833-14-7 | CSJ: | 0833-14-007 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | FM 434 SOUTH | Fund Cat: | 1 |
Limits To: | FM 434 NORTH | Estimate: | $201,799 |
Length: | 5.3 Miles | Actual: | $182,891 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 708 | Let Status: | Actual |
Project ID: | CPM 1054-3-13 | CSJ: | 1054-03-013 |
Description: | EMULSION | Handling Code: |
|
Limits From: | FM 56 | Fund Cat: | 1 |
Limits To: | FM 219 | Estimate: | $198,135 |
Length: | 8.8 Miles | Actual: | $175,855 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 938 | Let Status: | Actual |
Project ID: | CPM 1187-2-15 | CSJ: | 1187-02-015 |
Description: | EMULSION | Handling Code: |
|
Limits From: | US 84 | Fund Cat: | 1 |
Limits To: | FM 185 | Estimate: | $105,744 |
Length: | 6.0 Miles | Actual: | $92,546 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 2603 | Let Status: | Actual |
Project ID: | CPM 1192-3-17 | CSJ: | 1192-03-017 |
Description: | EMULSION | Handling Code: |
|
Limits From: | FM 1240 | Fund Cat: | 1 |
Limits To: | MCLENNAN CO LINE | Estimate: | $78,533 |
Length: | 4.1 Miles | Actual: | $69,145 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 182 | Let Status: | Actual |
Project ID: | CPM 1219-2-16 | CSJ: | 1219-02-016 |
Description: | EMULSION | Handling Code: |
|
Limits From: | TURNERSVILLE | Fund Cat: | 1 |
Limits To: | BOSQUE CO LINE | Estimate: | $137,135 |
Length: | 6.9 Miles | Actual: | $120,387 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 1947 | Let Status: | Actual |
Project ID: | CPM 1830-1-10 | CSJ: | 1830-01-010 |
Description: | EMULSION | Handling Code: |
|
Limits From: | FM 310 | Fund Cat: | 1 |
Limits To: | SH 22 | Estimate: | $119,113 |
Length: | 5.6 Miles | Actual: | $106,417 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 2136 | Let Status: | Actual |
Project ID: | CPM 2058-1-8 | CSJ: | 2058-01-008 |
Description: | EMULSION | Handling Code: |
|
Limits From: | SH 6 | Fund Cat: | 1 |
Limits To: | SH 22 | Estimate: | $201,099 |
Length: | 8.7 Miles | Actual: | $179,098 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 2113 | Let Status: | Actual |
Project ID: | CPM 2060-1-32 | CSJ: | 2060-01-032 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | FM 2416 | Fund Cat: | 1 |
Limits To: | FM 107 | Estimate: | $187,865 |
Length: | 8.0 Miles | Actual: | $173,571 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 3220 | Let Status: | Actual |
Project ID: | CPM 3328-2-5 | CSJ: | 3328-02-005 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | SH 6 | Fund Cat: | 1 |
Limits To: | 0.530 MI W OF SH 6 | Estimate: | $23,257 |
Length: | 0.5 Miles | Actual: | $21,653 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 3375 | Let Status: | Actual |
Project ID: | CPM 3430-1-6 | CSJ: | 3430-01-006 |
Description: | EMULSION | Handling Code: |
|
Limits From: | FM 147 | Fund Cat: | 1 |
Limits To: | FM 2307 | Estimate: | $70,097 |
Length: | 3.1 Miles | Actual: | $61,729 |
District: | Waco | Let Date: | NOV 2006 |
Highway: | FM 3371 | Let Status: | Actual |
Project ID: | CPM 3459-1-10 | CSJ: | 3459-01-010 |
Description: | EMULSION | Handling Code: |
|
Limits From: | FM 937 | Fund Cat: | 1 |
Limits To: | SH 164 | Estimate: | $263,105 |
Length: | 9.2 Miles | Actual: | $231,645 |
Back... |
Totals for 0251-01-054 | ||
---|---|---|---|
Length: | 174.4 Miles | ||
Estimate: | $6,337,343 | ||
Actual: | $5,728,905 | ||
CCSJ: 0909-29-033 | |||
District: | Waco | Let Date: | APR 2007 |
Highway: | CS | Let Status: | Actual |
Project ID: | BR 2005(908) | CSJ: | 0909-29-033 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | ON FIRST ST @ GRUBBS BRANCH | Fund Cat: | 6 |
Limits To: | (MAP #4 HIC) | Estimate: | $292,731 |
Length: | 0.0 Miles | Actual: | $345,334 |
District: | Waco | Let Date: | APR 2007 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2006(298) | CSJ: | 0909-29-034 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | ON CR 284 @ LEON RIVER | Fund Cat: | 6 |
Limits To: | (MAP #222) | Estimate: | $495,331 |
Length: | 0.2 Miles | Actual: | $478,407 |
District: | Waco | Let Date: | APR 2007 |
Highway: | CR | Let Status: | Actual |
Project ID: | STP 2006(831)TE | CSJ: | 0909-29-041 |
Description: | REMOVE AND RELOCATE HISTORIC LEON RIVER TRUSS BRIDGE | Handling Code: |
|
Limits From: | ON CR 284 @ LEON RV | Fund Cat: | 9 |
Limits To: | (MAP #222) | Estimate: | $45,000 |
Length: | 0.0 Miles | Actual: | $20,000 |
Back... |
Totals for 0909-29-033 | ||
Length: | 0.2 Miles | ||
Estimate: | $833,062 | ||
Actual: | $843,741 |
|
|