Detail Letting Schedule for Karnes County (FY 2007)
| |
| Detail Letting Schedule for Karnes County (FY 2007) |
| |
| Last Update: Monday, July 30, 2007 |
CCSJ: 0359-04-020
|
| District: |
Corpus Christi |
Let Date: |
NOV 2006 |
| Highway: |
SH 119 |
Let Status: |
Actual |
| Project ID: |
STP 2007(197) |
CSJ: |
0359-04-020 |
| Description: |
RESTORE EXISTING ROADWAY |
Handling Code: |
|
| Limits From: |
SH 80 |
Fund Cat: |
1 |
| Limits To: |
DEWITT COUNTY LINE |
Estimate: |
$2,478,667 |
| Length: |
8.6 Miles |
Actual: |
$2,211,983 |
| |
Back...
|
Totals for 0359-04-020 |
| Length: |
8.6 Miles |
| Estimate: |
$2,478,667 |
| Actual: |
$2,211,983 |
| Handling Code |
Definition |
| XX |
Project not processed through statewide letting |
| TR |
Transfer of funds |
| LC |
Project let through local entity |
| NC |
Project not charged against district apportionment |
| Let Status |
Definition |
| Tentative |
Estimated letting date for this project |
| Approved |
Project has administrative approval to be let |
| Actual |
Project was let to contract |
|