Detail Letting Schedule for Clay County (FY 2008)
| |
| Detail Letting Schedule for Clay County (FY 2008) |
| |
| Last Update: Monday, February 2, 2009 |
CCSJ: 0224-01-056
|
| District: |
Wichita Falls |
Let Date: |
DEC 2007 |
| Highway: |
US 287 |
Let Status: |
Actual |
| Project ID: |
STP 2008(212)HES |
CSJ: |
0224-01-056 |
| Description: |
INSTALL MEDIAN BARRIER |
Handling Code: |
|
| Limits From: |
US 82 INTERCHANGE |
Fund Cat: |
8 |
| Limits To: |
0.9 MILES SOUTH OF SPUR 510 |
Estimate: |
$788,729 |
| Length: |
3.9 Miles |
Actual: |
$709,834 |
| |
Back...
|
Totals for 0224-01-056 |
| Length: |
3.9 Miles |
| Estimate: |
$788,729 |
| Actual: |
$709,834 |
CCSJ: 0239-06-010
|
| District: |
Wichita Falls |
Let Date: |
DEC 2007 |
| Highway: |
SH 59 |
Let Status: |
Actual |
| Project ID: |
STP 2008(214) |
CSJ: |
0239-06-010 |
| Description: |
WIDEN ROAD AND EXTEND STRUCTURES |
Handling Code: |
NC |
| Limits From: |
JACK COUNTY LINE |
Fund Cat: |
1 |
| Limits To: |
MONTAGUE COUNTY LINE |
Estimate: |
$2,925,976 |
| Length: |
3.5 Miles |
Actual: |
$2,618,946 |
| |
Back...
|
Totals for 0239-06-010 |
| Length: |
3.5 Miles |
| Estimate: |
$2,925,976 |
| Actual: |
$2,618,946 |
| Handling Code |
Definition |
| XX |
Project not processed through statewide letting |
| TR |
Transfer of funds |
| LC |
Project let through local entity |
| NC |
Project not charged against district apportionment |
| Let Status |
Definition |
| Tentative |
Estimated letting date for this project |
| Approved |
Project has administrative approval to be let |
| Actual |
Project was let to contract |
|