Detail Letting Schedule for Archer County (FY 2011)
|
Detail Letting Schedule for Archer County (FY 2011) |
|
Last Update: Tuesday, September 6, 2011 |
CCSJ: 0156-05-053
|
District: |
Wichita Falls |
Let Date: |
NOV 2010 |
Highway: |
US 82 |
Let Status: |
Actual |
Project ID: |
NH 2011(538) |
CSJ: |
0156-05-053 |
Description: |
ACP OVERLAY |
Handling Code: |
|
Limits From: |
BAYLOR COUNTY LINE |
Fund Cat: |
1 |
Limits To: |
HOLLIDAY |
Estimate: |
$3,291,054 |
Length: |
14.9 Miles |
Actual: |
$3,131,860 |
|
Back...
|
Totals for 0156-05-053 |
Length: |
14.9 Miles |
Estimate: |
$3,291,054 |
Actual: |
$3,131,860 |
CCSJ: 0903-29-025
|
District: |
Wichita Falls |
Let Date: |
APR 2011 |
Highway: |
CR |
Let Status: |
Actual |
Project ID: |
BR 2011(096) |
CSJ: |
0903-29-025 |
Description: |
REPLACE BRIDGE AND APPROACHES |
Handling Code: |
|
Limits From: |
CR 238 SOUTH SIDE IRRIGATION CANAL |
Fund Cat: |
6 |
Limits To: |
(CONTINENTAL) |
Estimate: |
$280,704 |
Length: |
0.1 Miles |
Actual: |
$266,729 |
|
Back...
|
Totals for 0903-29-025 |
Length: |
0.1 Miles |
Estimate: |
$280,704 |
Actual: |
$266,729 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|