Detail Letting Schedule for Oldham County (FY 2011)

 
 
Last Update: Tuesday, September 6, 2011
Oldham County (FY 2011)

CCSJ: 0090-03-055

District: Amarillo Let Date: OCT 2010
Highway: IH 40 Let Status: Actual
Project ID: IM 0401(203) CSJ: 0090-03-055
Description: SEAL COAT Handling
Code:
 
Limits From: 0.2 MI WEST OF FM 2558 Fund Cat: 1
Limits To: 0.2 MI EAST OF SH 214 Estimate: $1,130,530
Length: 6.7 Miles Actual: $909,996
 
District: Amarillo Let Date: OCT 2010
Highway: SH 217 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0168-11-017
Description: SEAL COAT Handling
Code:
 
Limits From: US 87 Fund Cat: 1
Limits To: US 60 Estimate: $58,074
Length: 1.2 Miles Actual: $46,928
 
District: Amarillo Let Date: OCT 2010
Highway: US 60 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0169-09-014
Description: SEAL COAT Handling
Code:
 
Limits From: ROBERTS COUNTY LINE Fund Cat: 1
Limits To: US 83 INTERCHANGE Estimate: $293,840
Length: 8.5 Miles Actual: $236,091
 
District: Amarillo Let Date: OCT 2010
Highway: FM 282 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0169-10-019
Description: SEAL COAT Handling
Code:
 
Limits From: FM 750 Fund Cat: 1
Limits To: SH 152 Estimate: $73,867
Length: 1.0 Miles Actual: $60,068
 
District: Amarillo Let Date: OCT 2010
Highway: FM 750 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0169-10-020
Description: SEAL COAT Handling
Code:
 
Limits From: FM 282 Fund Cat: 1
Limits To: SH 273 Estimate: $84,249
Length: 2.0 Miles Actual: $69,358
 
District: Amarillo Let Date: OCT 2010
Highway: FM 750 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0169-11-007
Description: SEAL COAT Handling
Code:
 
Limits From: US 60 Fund Cat: 1
Limits To: FM 282 Estimate: $10,313
Length: 0.2 Miles Actual: $8,459
 
District: Amarillo Let Date: OCT 2010
Highway: US 54 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0238-05-040
Description: SEAL COAT Handling
Code:
 
Limits From: DALLAM COUNTY LINE Fund Cat: 1
Limits To: US 287 Estimate: $164,759
Length: 6.1 Miles Actual: $133,563
 
District: Amarillo Let Date: OCT 2010
Highway: IH 40 Let Status: Actual
Project ID: IM 0401(203) CSJ: 0275-01-157
Description: SEAL COAT (FRONTAGE ROADS) Handling
Code:
 
Limits From: SONCY RD Fund Cat: 1
Limits To: JOHNSON ST Estimate: $535,844
Length: 6.0 Miles Actual: $448,306
 
District: Amarillo Let Date: OCT 2010
Highway: FM 759 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0308-05-011
Description: SEAL COAT Handling
Code:
 
Limits From: HANSFORD COUNTY LINE Fund Cat: 1
Limits To: SH 70 Estimate: $329,113
Length: 15.4 Miles Actual: $235,207
 
District: Amarillo Let Date: OCT 2010
Highway: SH 70 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0309-01-039
Description: SEAL COAT Handling
Code:
 
Limits From: US 60 Fund Cat: 1
Limits To: IH 40 Estimate: $748,619
Length: 23.5 Miles Actual: $606,839
 
District: Amarillo Let Date: OCT 2010
Highway: FM 2298 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0461-15-007
Description: SEAL COAT Handling
Code:
 
Limits From: PARMER COUNTY LINE Fund Cat: 1
Limits To: FM 1058 Estimate: $104,103
Length: 5.7 Miles Actual: $74,187
 
District: Amarillo Let Date: OCT 2010
Highway: FM 119 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0727-02-018
Description: SEAL COAT Handling
Code:
 
Limits From: FM 1573 Fund Cat: 1
Limits To: SH 15 Estimate: $397,229
Length: 13.0 Miles Actual: $283,251
 
District: Amarillo Let Date: OCT 2010
Highway: FM 282 Let Status: Actual
Project ID: STP 2011(457) CSJ: 0798-01-024
Description: SEAL COAT Handling
Code:
 
Limits From: US 60 IN MIAMI Fund Cat: 1
Limits To: SH 70 Estimate: $438,793
Length: 21.4 Miles Actual: $311,349
 
District: Amarillo Let Date: OCT 2010
Highway: FM 760 Let Status: Actual
Project ID: STP 2011(457) CSJ: 1107-01-016
Description: SEAL COAT Handling
Code:
 
Limits From: FM 759 Fund Cat: 1
Limits To: FM 281 Estimate: $244,333
Length: 8.0 Miles Actual: $174,486
 
District: Amarillo Let Date: OCT 2010
Highway: FM 1058 Let Status: Actual
Project ID: STP 2011(457) CSJ: 1243-01-024
Description: SEAL COAT Handling
Code:
 
Limits From: NEW MEXICO STATE LINE Fund Cat: 1
Limits To: US 385 Estimate: $1,122,708
Length: 36.3 Miles Actual: $802,209
 
District: Amarillo Let Date: OCT 2010
Highway: FM 1913 Let Status: Actual
Project ID: STP 2011(457) CSJ: 1244-02-018
Description: SEAL COAT Handling
Code:
 
Limits From: US 87 Fund Cat: 1
Limits To: RM 1319 Estimate: $500,376
Length: 25.3 Miles Actual: $353,543
 
District: Amarillo Let Date: OCT 2010
Highway: FM 1290 Let Status: Actual
Project ID: STP 2011(457) CSJ: 1338-01-011
Description: SEAL COAT Handling
Code:
 
Limits From: SH 15 Fund Cat: 1
Limits To: OKLAHOMA STATE LINE Estimate: $226,289
Length: 11.9 Miles Actual: $160,639
 
District: Amarillo Let Date: OCT 2010
Highway: FM 1541 Let Status: Actual
Project ID: STP 2011(457) CSJ: 1480-02-028
Description: SEAL COAT Handling
Code:
 
Limits From: LP 335 Fund Cat: 1
Limits To: IH 27 Estimate: $238,159
Length: 3.8 Miles Actual: $193,788
 
District: Amarillo Let Date: OCT 2010
Highway: FM 1573 Let Status: Actual
Project ID: STP 2011(457) CSJ: 1489-02-010
Description: SEAL COAT Handling
Code:
 
Limits From: SHERMAN COUNTY LINE Fund Cat: 1
Limits To: SH 15 Estimate: $176,732
Length: 5.2 Miles Actual: $125,679
 
District: Amarillo Let Date: OCT 2010
Highway: FM 281 Let Status: Actual
Project ID: STP 2011(457) CSJ: 1885-03-011
Description: SEAL COAT Handling
Code:
 
Limits From: SH 70 Fund Cat: 1
Limits To: US 83 Estimate: $390,388
Length: 14.4 Miles Actual: $277,230
 
District: Amarillo Let Date: OCT 2010
Highway: FM 2018 Let Status: Actual
Project ID: STP 2011(457) CSJ: 1886-01-012
Description: SEAL COAT Handling
Code:
 
Limits From: FM 1573 Fund Cat: 1
Limits To: SH 15 Estimate: $330,969
Length: 16.0 Miles Actual: $237,359
 
District: Amarillo Let Date: OCT 2010
Highway: FM 1151 Let Status: Actual
Project ID: STP 2011(457) CSJ: 2002-03-021
Description: SEAL COAT Handling
Code:
 
Limits From: FM 1258 Fund Cat: 1
Limits To: ARMSTRONG COUNTY LINE Estimate: $108,513
Length: 4.6 Miles Actual: $77,582
 
District: Amarillo Let Date: OCT 2010
Highway: FM 1151 Let Status: Actual
Project ID: STP 2011(457) CSJ: 2002-04-012
Description: SEAL COAT Handling
Code:
 
Limits From: RANDALL COUNTY LINE Fund Cat: 1
Limits To: FM 2250 Estimate: $54,502
Length: 2.7 Miles Actual: $39,012
 
District: Amarillo Let Date: OCT 2010
Highway: FM 282 Let Status: Actual
Project ID: STP 2011(457) CSJ: 2492-01-013
Description: SEAL COAT Handling
Code:
 
Limits From: GRAY COUNTY LINE Fund Cat: 1
Limits To: SH 70 Estimate: $63,555
Length: 3.0 Miles Actual: $45,138
 
District: Amarillo Let Date: OCT 2010
Highway: FM 282 Let Status: Actual
Project ID: STP 2011(457) CSJ: 2492-02-014
Description: SEAL COAT Handling
Code:
 
Limits From: SH 152 Fund Cat: 1
Limits To: ROBERTS COUNTY LINE Estimate: $211,323
Length: 5.9 Miles Actual: $172,447
 
District: Amarillo Let Date: OCT 2010
Highway: LP 335 Let Status: Actual
Project ID: STP 2011(457) CSJ: 2635-01-028
Description: SEAL COAT Handling
Code:
 
Limits From: IH 40 Fund Cat: 1
Limits To: SH 136 Estimate: $605,120
Length: 4.7 Miles Actual: $483,156
 
Back...

Totals for 0090-03-055
Length: 252.5 Miles
Estimate: $8,642,300
Actual: $6,565,870


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract