Detail Letting Schedule for Carson County (FY 2012)
| |
| Detail Letting Schedule for Carson County (FY 2012) |
| |
| Last Update: Monday, September 24, 2012 |
CCSJ: 0275-04-048
|
| District: |
Amarillo |
Let Date: |
MAR 2012 |
| Highway: |
IH 40 |
Let Status: |
Actual |
| Project ID: |
IM 0401(206) |
CSJ: |
0275-04-048 |
| Description: |
REHAB EXISTING ROADWAY - ACP OVERLAY |
Handling Code: |
|
| Limits From: |
2.0 MILES WEST OF GROOM |
Fund Cat: |
1 |
| Limits To: |
GRAY COUNTY LINE |
Estimate: |
$3,228,747 |
| Length: |
4.3 Miles |
Actual: |
$3,773,637 |
| |
| District: |
Amarillo |
Let Date: |
MAR 2012 |
| Highway: |
IH 40 |
Let Status: |
Actual |
| Project ID: |
IM 0401(206) |
CSJ: |
0275-05-042 |
| Description: |
REHAB EXISTING ROADWAY - ACP OVERLAY |
Handling Code: |
|
| Limits From: |
CARSON COUNTY LINE |
Fund Cat: |
1 |
| Limits To: |
2.0 MILES EAST OF GROOM |
Estimate: |
$924,489 |
| Length: |
1.3 Miles |
Actual: |
$973,864 |
| |
Back...
|
Totals for 0275-04-048 |
| Length: |
5.6 Miles |
| Estimate: |
$4,153,236 |
| Actual: |
$4,747,501 |
| Handling Code |
Definition |
| XX |
Project not processed through statewide letting |
| TR |
Transfer of funds |
| LC |
Project let through local entity |
| NC |
Project not charged against district apportionment |
| Let Status |
Definition |
| Tentative |
Estimated letting date for this project |
| Approved |
Project has administrative approval to be let |
| Actual |
Project was let to contract |
|