Detail Letting Schedule for Dallam County (FY 2012)
| |
| Detail Letting Schedule for Dallam County (FY 2012) |
| |
| Last Update: Monday, September 24, 2012 |
CCSJ: 0238-03-052
|
| District: |
Amarillo |
Let Date: |
JUN 2012 |
| Highway: |
US 54 |
Let Status: |
Actual |
| Project ID: |
C 238-3-52 |
CSJ: |
0238-03-052 |
| Description: |
REHAB EXIST RDWY & ADD PASSING LNS |
Handling Code: |
|
| Limits From: |
DALHART CURB & GUTTER |
Fund Cat: |
3 |
| Limits To: |
CHAMBERLIN |
Estimate: |
$2,439,160 |
| Length: |
7.1 Miles |
Actual: |
$2,590,430 |
| |
| District: |
Amarillo |
Let Date: |
JUN 2012 |
| Highway: |
US 54 |
Let Status: |
Actual |
| Project ID: |
C 238-4-30 |
CSJ: |
0238-04-030 |
| Description: |
REHAB EXIST RDWY & ADD PASSING LNS |
Handling Code: |
|
| Limits From: |
CHAMBERLIN |
Fund Cat: |
3 |
| Limits To: |
SHERMAN COUNTY LINE |
Estimate: |
$4,159,873 |
| Length: |
16.2 Miles |
Actual: |
$3,827,523 |
| |
Back...
|
Totals for 0238-03-052 |
| Length: |
23.3 Miles |
| Estimate: |
$6,599,033 |
| Actual: |
$6,417,953 |
| Handling Code |
Definition |
| XX |
Project not processed through statewide letting |
| TR |
Transfer of funds |
| LC |
Project let through local entity |
| NC |
Project not charged against district apportionment |
| Let Status |
Definition |
| Tentative |
Estimated letting date for this project |
| Approved |
Project has administrative approval to be let |
| Actual |
Project was let to contract |
|