Detail Letting Schedule for Titus County (FY 2012)
| Detail Letting Schedule for Titus County (FY 2012) | ||||
| Last Update: Monday, September 24, 2012 |
| Titus County (FY 2012) |
CCSJ: 0248-09-001 | |||
| District: | Atlanta | Let Date: | DEC 2011 |
| Highway: | US 271 | Let Status: | Actual |
| Project ID: | PTF 2011(591) | CSJ: | 0248-01-068 |
| Description: | CONSTRUCT FIRST PHASE OF ULTIMATE 4 - LANE DIVIDED FREEWAY | Handling Code: |
LC |
| Limits From: | 1.3 MI. NORTH OF FM 3417 | Fund Cat: | 3 |
| Limits To: | 0.7 MI. SOUTH OF FM 3417 | Estimate: | $29,324,082 |
| Length: | 1.8 Miles | Actual: | $22,840,432 |
| District: | Atlanta | Let Date: | DEC 2011 |
| Highway: | US 271 | Let Status: | Actual |
| Project ID: | PTF 2011(591) | CSJ: | 0248-09-001 |
| Description: | CONSTRUCT FIRST PHASE OF ULTIMATE 4 - LANE DIVIDED FREEWAY | Handling Code: |
LC |
| Limits From: | 0.3 MI. NORTH OF US 67 | Fund Cat: | 3 |
| Limits To: | 1.2 MI. NORTH OF FM 3417 | Estimate: | $50,174,227 |
| Length: | 4.0 Miles | Actual: | $49,985,186 |
|
Back... |
Totals for 0248-09-001 | ||
|---|---|---|---|
| Length: | 5.8 Miles | ||
| Estimate: | $79,498,309 | ||
| Actual: | $72,825,618 | ||
CCSJ: 0919-30-047 | |||
| District: | Atlanta | Let Date: | MAY 2012 |
| Highway: | CR | Let Status: | Actual |
| Project ID: | BR 2006(528) | CSJ: | 0919-30-047 |
| Description: | REPLACE BRIDGE AND APPROACHES_ON CR 3250 AT MILL CREEK | Handling Code: |
|
| Limits From: | ON CR 3250 AT MILL CREEK | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $276,819 |
| Length: | 0.1 Miles | Actual: | $251,563 |
| District: | Atlanta | Let Date: | MAY 2012 |
| Highway: | CR | Let Status: | Actual |
| Project ID: | BR 2006(529) | CSJ: | 0919-30-048 |
| Description: | REPLACE BRIDGE AND APPROACHES_ON CR 3130 AT TAYLOR CREEK | Handling Code: |
|
| Limits From: | ON CR 3130 AT TAYLOR CREEK | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $237,647 |
| Length: | 0.1 Miles | Actual: | $207,079 |
|
Back... |
Totals for 0919-30-047 | ||
| Length: | 0.2 Miles | ||
| Estimate: | $514,466 | ||
| Actual: | $458,642 | ||
CCSJ: 1226-01-009 | |||
| District: | Atlanta | Let Date: | MAR 2012 |
| Highway: | FM 1000 | Let Status: | Actual |
| Project ID: | BR 2012(388) | CSJ: | 1226-01-009 |
| Description: | REPLACE BRIDGE AND APPROACHES ON 2 LANE HIGHWAY | Handling Code: |
|
| Limits From: | AT SWAUANO CREEK | Fund Cat: | 11 |
| Limits To: | . | Estimate: | $364,331 |
| Length: | 0.1 Miles | Actual: | $336,484 |
|
Back... |
Totals for 1226-01-009 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $364,331 | ||
| Actual: | $336,484 | ||
CCSJ: 1578-02-026 | |||
| District: | Atlanta | Let Date: | JUN 2012 |
| Highway: | FM 1734 | Let Status: | Actual |
| Project ID: | C 1578-2-26 | CSJ: | 1578-02-026 |
| Description: | INSTALL NEW TRAFFIC SIGNAL | Handling Code: |
|
| Limits From: | AT OLD PARIS ROAD | Fund Cat: | 3 |
| Limits To: | . | Estimate: | $54,502 |
| Length: | 0.1 Miles | Actual: | $49,996 |
|
Back... |
Totals for 1578-02-026 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $54,502 | ||
| Actual: | $49,996 | ||
CCSJ: 2240-01-012 | |||
| District: | Atlanta | Let Date: | APR 2012 |
| Highway: | FM 2348 | Let Status: | Actual |
| Project ID: | PTF 2012(586) | CSJ: | 2240-01-012 |
| Description: | CONSTRUCT 2 - LANE FM ROAD ON NEW LOCATION | Handling Code: |
LC |
| Limits From: | US 67 AT FM 1001, SOUTH | Fund Cat: | 3 |
| Limits To: | SH 49 | Estimate: | $10,730,090 |
| Length: | 3.2 Miles | Actual: | $8,512,734 |
|
Back... |
Totals for 2240-01-012 | ||
| Length: | 3.2 Miles | ||
| Estimate: | $10,730,090 | ||
| Actual: | $8,512,734 | ||
|
| |