Detail Letting Schedule for Delta County (FY 2013)
| Delta County (FY 2013) |
CCSJ: 0399-03-034 | |||
| District: | Paris | Let Date: | APR 2013 |
| Highway: | FM 64 | Let Status: | Actual |
| Project ID: | STP 2013(547) | CSJ: | 0399-03-034 |
| Description: | REHABILITATION OF EXISTING ROAD | Handling Code: |
|
| Limits From: | FM 1532 | Fund Cat: | 1 |
| Limits To: | FM 3388 | Estimate: | $1,137,058 |
| Length: | 2.4 Miles | Actual: | $759,416 |
| District: | Paris | Let Date: | APR 2013 |
| Highway: | FM 1532 | Let Status: | Actual |
| Project ID: | STP 2013(547) | CSJ: | 1463-02-014 |
| Description: | REHABILITATION OF EXISTING ROAD | Handling Code: |
|
| Limits From: | FM 904 | Fund Cat: | 1 |
| Limits To: | FM 64 | Estimate: | $856,884 |
| Length: | 2.6 Miles | Actual: | $640,361 |
|
Back... |
Totals for 0399-03-034 | ||
|---|---|---|---|
| Length: | 5.0 Miles | ||
| Estimate: | $1,993,942 | ||
| Actual: | $1,399,777 | ||
CCSJ: 0901-31-113 | |||
| District: | Paris | Let Date: | JAN 2013 |
| Highway: | CR | Let Status: | Actual |
| Project ID: | BR 99(600) | CSJ: | 0901-31-113 |
| Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
| Limits From: | @ BRANCH OF JOHNS CREEK | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $127,247 |
| Length: | 0.1 Miles | Actual: | $149,291 |
| District: | Paris | Let Date: | JAN 2013 |
| Highway: | CR | Let Status: | Actual |
| Project ID: | BR 2012(671) | CSJ: | 0901-31-129 |
| Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
| Limits From: | CR 138-1 | Fund Cat: | 6 |
| Limits To: | AT HONEY CREEK | Estimate: | $135,653 |
| Length: | 0.1 Miles | Actual: | $147,320 |
|
Back... |
Totals for 0901-31-113 | ||
| Length: | 0.2 Miles | ||
| Estimate: | $262,900 | ||
| Actual: | $296,611 | ||
|