Detail Letting Schedule for Kleberg County (FY 2017)
| Kleberg County (FY 2017) | 
| CCSJ: 0102-04-104 | |||
| District: | CORPUS CHRISTI | Let Date: | Oct 2016 | 
| Highway: | US 77 | Let Status: | Actual | 
| Project ID: | NH 2017(156) | CSJ: | 0102-04-104 | 
| Description: | MILL AND OVERALY | Handling Code: | |
| Limits From: | SH 285 | Fund Cat: | 1 | 
| Limits To: | END OF FIVE LANE SECTION | ESTIMATE: | $1,844,433 | 
| Length: | 1.5 | Actual | $1,551,557 | 
| District: | CORPUS CHRISTI | Let Date: | Oct 2016 | 
| Highway: | US 77 | Let Status: | Actual | 
| Project ID: | NH 2017(156) | CSJ: | 0327-01-032 | 
| Description: | MILL AND OVERLAY | Handling Code: | |
| Limits From: | SH 285 | Fund Cat: | 1 | 
| Limits To: | KENEDY COUNTY LINE | ESTIMATE: | $1,988,649 | 
| Length: | 2.0 | Actual | $1,765,567 | 
| Back... | Totals for 0102-04-104 | ||
|---|---|---|---|
| Length: | 3.5 | ||
| Estimate: | $3,833,081 | ||
| Actual: | $3,317,125 | ||
| Handling Code | Definition | 
|---|---|
| XX | Project not processed through statewide letting | 
| TR | Transfer of funds | 
| LC | Project let through local entity | 
| LC | Project not charged against district apportionment | 
| Let Status | Definition | 
|---|---|
| Tentative | Estimated letting date for this project | 
| Approved | Project has administrative approval to be let | 
| Actual | Project was let to contract |