Detail Letting Schedule for Cherokee County (FY 2019)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Cherokee County (FY 2019) |
CCSJ: 0198-07-014 |
|||
District: | TYLER | Let Date: | Jul 2019 |
Highway: | SH 204 | Let Status: | Approved |
Project ID: | STP ( ) | CSJ: | 0198-07-014 |
Description: | HIGHWAY/RAILROAD IMPROVEMENT | Handling Code: | |
Limits From: | US 79 IN JACKSONVILLE, SE | Fund Cat: | 1 |
Limits To: | SH 110 | ESTIMATE: | $14,697,621 |
Length: | 10.7 | Actual | $0 |
Back... | Totals for 0198-07-014 | ||
---|---|---|---|
Length: | 10.7 | ||
Estimate: | $14,697,621 | ||
Actual: | |||
CCSJ: 0198-07-015 |
|||
District: | TYLER | Let Date: | May 2019 |
Highway: | SH 204 | Let Status: | Approved |
Project ID: | STP 2019(882)HESG | CSJ: | 0198-07-015 |
Description: | Hazard Elimination & Safety | Handling Code: | |
Limits From: | SL 456 IN JACKSONVILLE, SE | Fund Cat: | 8 |
Limits To: | SH 110 | ESTIMATE: | $117,058 |
Length: | 9.5 | Actual | $0 |
District: | TYLER | Let Date: | May 2019 |
Highway: | SH 64 | Let Status: | Approved |
Project ID: | STP 2019(882)HESG | CSJ: | 0245-07-030 |
Description: | Hazard Elimination & Safety | Handling Code: | |
Limits From: | SH 135, E | Fund Cat: | 8 |
Limits To: | RUSK C/L | ESTIMATE: | $52,810 |
Length: | 4.4 | Actual | $0 |
District: | TYLER | Let Date: | May 2019 |
Highway: | SH 64 | Let Status: | Approved |
Project ID: | STP 2019(882)HESG | CSJ: | 0245-08-052 |
Description: | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | SMITH C/L, E | Fund Cat: | 8 |
Limits To: | SH 42 | ESTIMATE: | $28,995 |
Length: | 2.1 | Actual | $0 |
District: | TYLER | Let Date: | May 2019 |
Highway: | SH 135 | Let Status: | Approved |
Project ID: | STP 2019(882)HESG | CSJ: | 0378-06-020 |
Description: | Hazard Elimination & Safety | Handling Code: | |
Limits From: | 1.609 MI N OF FM 2064, W&S | Fund Cat: | 8 |
Limits To: | 1.564 MI NW OF US 69, J'VILLE CL | ESTIMATE: | $87,356 |
Length: | 14.5 | Actual | $0 |
District: | TYLER | Let Date: | May 2019 |
Highway: | SH 204 | Let Status: | Approved |
Project ID: | STP 2019(882)HESG | CSJ: | 0450-01-014 |
Description: | INSTALL PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | SH 110, SE | Fund Cat: | 8 |
Limits To: | 0.75 MI E OF FM 235 | ESTIMATE: | $32,914 |
Length: | 5.2 | Actual | $0 |
District: | TYLER | Let Date: | May 2019 |
Highway: | FM 315 | Let Status: | Approved |
Project ID: | STP 2019(882)HESG | CSJ: | 0890-02-019 |
Description: | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | HENDERSON C/L, S | Fund Cat: | 8 |
Limits To: | 0.005 MI S OF FM 3309 IN PALESTINE | ESTIMATE: | $259,443 |
Length: | 19.8 | Actual | $0 |
District: | TYLER | Let Date: | May 2019 |
Highway: | FM 747 | Let Status: | Approved |
Project ID: | STP 2019(882)HESG | CSJ: | 2407-02-009 |
Description: | Hazard Elimination & Safety | Handling Code: | |
Limits From: | 6.262 MI N OF US 79, S | Fund Cat: | 8 |
Limits To: | US 79 | ESTIMATE: | $80,123 |
Length: | 6.3 | Actual | $0 |
Back... | Totals for 0198-07-015 | ||
Length: | 61.8 | ||
Estimate: | $658,699 | ||
Actual: | |||
CCSJ: 0199-01-084 |
|||
District: | TYLER | Let Date: | Aug 2019 |
Highway: | US 69 | Let Status: | Approved |
Project ID: | STP ( ) | CSJ: | 0199-01-084 |
Description: | Construct Pedestrian Infrastructure | Handling Code: | |
Limits From: | NACOGDOCHES ST (0.1 MI S OF US79),S | Fund Cat: | 10 |
Limits To: | TENA(.1 MI S OF FM768)IN JACK'VILLE | ESTIMATE: | $1,027,382 |
Length: | 0.9 | Actual | $0 |
Back... | Totals for 0199-01-084 | ||
Length: | 0.9 | ||
Estimate: | $1,027,382 | ||
Actual: | |||
CCSJ: 0206-04-042 |
|||
District: | TYLER | Let Date: | Apr 2019 |
Highway: | US 79 | Let Status: | Actual |
Project ID: | NH 2019(733) | CSJ: | 0206-04-042 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | 2.8 MI W OF SH110 (C-S BREAK), W | Fund Cat: | 1 |
Limits To: | 3.5 MI E OF SH204,MUD CRK RELIEF BR | ESTIMATE: | |
Length: | 1.2 | Actual | $3,225,388 |
District: | TYLER | Let Date: | Apr 2019 |
Highway: | US 79 | Let Status: | Actual |
Project ID: | NH 2019(733) | CSJ: | 0206-05-032 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | .16 MI E OF SH110 IN NEW SMMRFLD,E | Fund Cat: | 1 |
Limits To: | 2.8 MI W OF SH110 (C-S BREAK) | ESTIMATE: | $4,455,435 |
Length: | 3.3 | Actual | $4,937,821 |
Back... | Totals for 0206-04-042 | ||
Length: | 4.5 | ||
Estimate: | $4,455,435 | ||
Actual: | $8,163,209 | ||
CCSJ: 0345-03-023 |
|||
District: | TYLER | Let Date: | Jan 2019 |
Highway: | SH 110 | Let Status: | Actual |
Project ID: | STP 2019(309)HES | CSJ: | 0345-03-023 |
Description: | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | 0.1 MI S OF FM1089-SMITH C/L, S | Fund Cat: | 8 |
Limits To: | US 79 IN NEW SUMMERFIELD | ESTIMATE: | $316,515 |
Length: | 10.9 | Actual | $155,141 |
District: | TYLER | Let Date: | Jan 2019 |
Highway: | FM 347 | Let Status: | Actual |
Project ID: | STP 2019(309)HES | CSJ: | 0191-05-007 |
Description: | INSTALL PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | US 69 IN JACKSONVILLE, S | Fund Cat: | 8 |
Limits To: | US 175 | ESTIMATE: | $32,082 |
Length: | 2.4 | Actual | $24,507 |
District: | TYLER | Let Date: | Jan 2019 |
Highway: | FM 347 | Let Status: | Actual |
Project ID: | STP 2019(309)HES | CSJ: | 0198-04-043 |
Description: | INSTALL PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | US 175 IN JACKSONVILLE, S | Fund Cat: | 8 |
Limits To: | OLD US175/WOODROW | ESTIMATE: | $6,284 |
Length: | 0.6 | Actual | $3,219 |
District: | TYLER | Let Date: | Jan 2019 |
Highway: | US 79 | Let Status: | Actual |
Project ID: | STP 2019(309)HES | CSJ: | 0206-04-041 |
Description: | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | 3.163 MI W OF SH 110-NEW SMMRFLD CL | Fund Cat: | 8 |
Limits To: | 1.108 MI E OF SH 204-J'VILLE CL | ESTIMATE: | $44,177 |
Length: | 3.6 | Actual | $27,555 |
District: | TYLER | Let Date: | Jan 2019 |
Highway: | SH 43 | Let Status: | Actual |
Project ID: | STP 2019(309)HES | CSJ: | 0207-02-029 |
Description: | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | 4.5 MI S OF FM 2658, S | Fund Cat: | 8 |
Limits To: | FM 1716 | ESTIMATE: | $51,011 |
Length: | 5.6 | Actual | $46,501 |
District: | TYLER | Let Date: | Jan 2019 |
Highway: | SH 43 | Let Status: | Actual |
Project ID: | STP 2019(309)HES | CSJ: | 0207-03-028 |
Description: | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | FM 2658, SW | Fund Cat: | 8 |
Limits To: | 4.5 MI S OF FM 2658 | ESTIMATE: | $62,131 |
Length: | 4.6 | Actual | $44,916 |
District: | TYLER | Let Date: | Jan 2019 |
Highway: | SH 110 | Let Status: | Actual |
Project ID: | STP 2019(309)HES | CSJ: | 0345-02-056 |
Description: | INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | FM 1089 IN TROUP, S | Fund Cat: | 8 |
Limits To: | 0.1 MI S OF FM1089-CHEROKEE C/L, S | ESTIMATE: | $3,422 |
Length: | 0.1 | Actual | $1,178 |
District: | TYLER | Let Date: | Jan 2019 |
Highway: | FM 347 | Let Status: | Actual |
Project ID: | STP 2019(309)HES | CSJ: | 0378-07-032 |
Description: | INSTALL PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | OLD US175/WOODROW, S | Fund Cat: | 8 |
Limits To: | US 84 AT OAKLAND | ESTIMATE: | $142,776 |
Length: | 11.6 | Actual | $104,899 |
District: | TYLER | Let Date: | Jan 2019 |
Highway: | SH 322 | Let Status: | Actual |
Project ID: | STP 2019(309)HES | CSJ: | 0594-02-028 |
Description: | INSTALL PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | GREGG C/L, S | Fund Cat: | 8 |
Limits To: | FM 850 | ESTIMATE: | $118,863 |
Length: | 9.9 | Actual | $83,917 |
Back... | Totals for 0345-03-023 | ||
Length: | 49.3 | ||
Estimate: | $777,263 | ||
Actual: | $491,834 | ||
CCSJ: 0926-01-023 |
|||
District: | TYLER | Let Date: | Jan 2019 |
Highway: | FM 343 | Let Status: | Actual |
Project ID: | STP 2019(429)HES | CSJ: | 0926-01-023 |
Description: | IMPROVE DRAINAGE AND CULVERTS FOR SAFETY | Handling Code: | |
Limits From: | US 69 | Fund Cat: | 1 |
Limits To: | 2.76 MI E OF US 69 | ESTIMATE: | $402,795 |
Length: | 2.8 | Actual | $383,366 |
District: | TYLER | Let Date: | Jan 2019 |
Highway: | FM 1861 | Let Status: | Actual |
Project ID: | STP 2019(429)HES | CSJ: | 1673-03-009 |
Description: | IMPROVE DRAINAGE AND CULVERTS FOR SAFETY | Handling Code: | |
Limits From: | FM 316, E | Fund Cat: | 8 |
Limits To: | VAN ZANDT COUNTY LINE | ESTIMATE: | $339,102 |
Length: | 1.7 | Actual | $255,232 |
Back... | Totals for 0926-01-023 | ||
Length: | 4.5 | ||
Estimate: | $741,897 | ||
Actual: | $638,598 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |