The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Atlanta District (FY 2019)
Bowie | Camp | Cass | Harrison | Marion | Morris | Panola | Titus | Upshur |

Bowie County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0062-01-035SH 8ActualApr 2019$1,966,0506BRIDGE REPLACEMENT8.0
0010-13-092US 67ActualDec 2018$705,0541RESURFACE EXISTING 3-LANE ROADWAY0.0
0010-11-072US 67ActualOct 2018$7,808,1571SEAL COAT0.0
0218-01-096US 59ActualNov 2018$4,788,9101RESURFACE EXSTING 4-LANE ROADWAY0.0
0046-05-050US 82ActualNov 2018$470,8671RESURFACE EXISTING 2-LANE HIGHWAY0.0
1231-01-071FM 989TentativeAug 2019$250,0008RAILROAD CROSSING UPGRADES0.0
0919-19-081CSTentativeAug 2019$250,0008RAILROAD CROSSING UPGRADES0.0

Camp County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0083-08-053SH 11ApprovedJun 2019$744,2148TRAFFIC SIGNAL IMPROVEMENTS0.0
0083-07-043SH 11ActualDec 2018$1,143,4748INSTALL LED FLASHING CHEVRONS ON CURVE0.0
0083-07-044SH 11ActualOct 2018$849,8138IMPROVE GUARDRAIL TO DESIGN STANDARDS5.0

Cass County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0919-00-079VAApprovedJul 2019$1,731,0001Surfacing/Roadway Restoration0.0
0919-14-027CRTentativeAug 2019$250,0008RAILROAD CROSSING UPGRADES0.0
0062-03-042SH 8ActualSep 2018$1,844,4098PROFILE EDGELINE MARKINGS0.0

Harrison County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
1575-04-017SL 390ActualJan 2019$310,8498INSTALL TRAF SIG, INST ADV WARNING SIG (INTERSECTION0.0
0632-04-034FM 9ActualDec 2018$3,069,2821REHABILITATE EXISTING 2-LANE HIGHWAY4.0
0495-08-117IH 20ApprovedAug 2019$417,6216Bridge Maintenance0.0
0096-09-077US 80ActualMar 2019$427,8248IMPROVE TRAFIC SIGNAL0.0
0495-08-116IH 20ApprovedMay 2019$2,121,9411REHABILITATE SOUTH FRONTAGE ROAD0.0
0208-02-045SH 43ApprovedMay 2019$4,921,0591SURFACING/ROADWAY RESTORATION4.0
0919-03-061CRTentativeAug 2019$250,0008RAILROAD CROSSING UPGRADES0.0
0632-04-032FM 451ActualMar 2019$5,283,8821PROVIDE ADDITIONAL PAVED SURFACE WIDTH, MILLED EDGELINE0.0

Marion County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0062-06-058US 59ApprovedAug 2019$2,267,1188HAZARD ELIMINATION & SAFETY0.0
0222-05-048SH 49ApprovedJun 2019$101,9018INSTALL ILLUMINATION0.0
0062-06-057US 59TentativeAug 2019$50,0003CONSTRUCT RIGHT TURN/DECELLERATION LANE0.0

Morris County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0010-08-055US 67ActualNov 2018$417,1878SAFETY LIGHTING0.0
0010-08-056US 67ActualApr 2019$5,716,9608IMPROVE GUARDRAIL TO DESIGN STANDARDS3.0

Panola County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0247-01-057US 79ActualApr 2019$9,887,68511RESURFACE EXISTING 4-LANE HIGHWAY0.0
0063-04-060US 59ApprovedJul 2019$3,400,37211Surfacing/Roadway Restoration0.0
0247-03-032US 79ApprovedMay 2019$4,709,5811INSTALL CONTINUOUS TURN LANE, MILLED EDGELINE RUMBLE STRIPS0.0

Titus County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0010-06-042US 67ActualMar 2019$3,235,8318SAFETY TREAT FIXED OBJECTS0.0
0222-01-058SH 49ApprovedMay 2019$2,470,9631SURFACING/ROADWAY RESTORATION1.5
1176-02-019FM 899ActualMar 2019$1,275,4646REPLACE BRIDGE AND APPROACHES3.0

Upshur County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0520-05-050SH 155ActualFeb 2019$4,133,4481RESTORE EXISTING 2-LANE HIGHWAY0.0
0248-04-071US 271ApprovedJul 2019$12,692,4941Surfacing/Roadway Restoration0.0
0392-02-096US 259ActualJan 2019$10,828,8671REHABILITATION OF EXISTING 4-LANE ROADWAY0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract