Detail Letting Schedule for Young County (FY 2019)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Young County (FY 2019) |
CCSJ: 0134-03-032 |
|||
District: | WICHITA FALLS | Let Date: | Jan 2019 |
Highway: | US 380 | Let Status: | Actual |
Project ID: | STP 2019(439) | CSJ: | 0134-03-032 |
Description: | PAVEMENT REPAIR AND OVERLAY | Handling Code: | |
Limits From: | FM 2179 | Fund Cat: | 1 |
Limits To: | JACK COUNTY LINE | ESTIMATE: | $2,718,623 |
Length: | 8.7 | Actual | $2,678,507 |
Back... | Totals for 0134-03-032 | ||
---|---|---|---|
Length: | 8.7 | ||
Estimate: | $2,718,623 | ||
Actual: | $2,678,507 | ||
CCSJ: 0444-01-041 |
|||
District: | WICHITA FALLS | Let Date: | Jul 2019 |
Highway: | SH 114 | Let Status: | Approved |
Project ID: | NH 1902(146) | CSJ: | 0444-01-041 |
Description: | UPGRADE TO SUPER-2 | Handling Code: | |
Limits From: | 0.8 MI W OF FM 1769 | Fund Cat: | 1 |
Limits To: | JACK COUNTY LINE | ESTIMATE: | $11,000,000 |
Length: | 12.3 | Actual | $0 |
Back... | Totals for 0444-01-041 | ||
Length: | 12.3 | ||
Estimate: | $11,000,000 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |