Detail Letting Schedule for Cameron County (FY 2021)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Cameron County (FY 2021) |
CCSJ: 0039-07-258 |
|||
District: | PHARR | Let Date: | Aug 2021 |
Highway: | IH 69E | Let Status: | Actual |
Project ID: | F 2021(932) | CSJ: | 0039-07-258 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | 0.1 MILES NORTH OF NEW HAMPSHIRE ST. | Fund Cat: | 8 |
Limits To: | 0.1 MILES SOUTH OF NEW HAMPSHIRE ST. | ESTIMATE: | $157,044 |
Length: | 0.0 | Actual | $150,583 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0039-07-258 | ||
---|---|---|---|
Length: | 0 | ||
Estimate: | $157,044 | ||
Actual: | $150,583 | ||
CCSJ: 0331-01-052 |
|||
District: | PHARR | Let Date: | Nov 2020 |
Highway: | SH 100 | Let Status: | Actual |
Project ID: | NH 2021(193) | CSJ: | 0331-01-052 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | S. MESQUITE ST. | Fund Cat: | 1 |
Limits To: | 567 FT. EAST OF EBANO ST. | ESTIMATE: | $4,633,928 |
Length: | 0.9 | Actual | $4,728,316 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0331-01-052 | ||
Length: | 0.9 | ||
Estimate: | $4,633,928 | ||
Actual: | $4,728,316 | ||
CCSJ: 0684-02-014 |
|||
District: | PHARR | Let Date: | Jun 2021 |
Highway: | FM 511 | Let Status: | Actual |
Project ID: | BR 2021(644) | CSJ: | 0684-02-014 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | .4 MI S OF SH 4 STR#0684-02-007 | Fund Cat: | 1 |
Limits To: | OVER DRAINAGE DITCH | ESTIMATE: | $986,990 |
Length: | 0.0 | Actual | $1,147,081 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0684-02-014 | ||
Length: | 0 | ||
Estimate: | $986,990 | ||
Actual: | $1,147,081 | ||
CCSJ: 0921-06-304 |
|||
District: | PHARR | Let Date: | Feb 2021 |
Highway: | CS | Let Status: | Actual |
Project ID: | STP 2020(422)TP | CSJ: | 0921-06-304 |
Description: | TRANSPORTATION NON-ROADWAY | Handling Code: | LC |
Limits From: | BMETRO EASTSIDE TRANSFER STATION | Fund Cat: | 3 |
Limits To: | @ JOSE COLUNGA JR & _BILLY MITCHELL | ESTIMATE: | $812,862 |
Length: | 0.0 | Actual | $1,035,189 |
Back... | Totals for 0921-06-304 | ||
Length: | 0 | ||
Estimate: | $812,862 | ||
Actual: | $1,035,189 | ||
CCSJ: 0921-06-345 |
|||
District: | PHARR | Let Date: | Dec 2020 |
Highway: | CR | Let Status: | Actual |
Project ID: | C 921-6-345 | CSJ: | 0921-06-345 |
Description: | TRANSPORTATION NON-ROADWAY | Handling Code: | LC |
Limits From: | ON ROBLES RD., FROM FM 1846 | Fund Cat: | 3 |
Limits To: | ARROYO COLORADO | ESTIMATE: | $5,262,841 |
Length: | 0.0 | Actual | $5,907,927 |
Back... | Totals for 0921-06-345 | ||
Length: | 0 | ||
Estimate: | $5,262,841 | ||
Actual: | $5,907,927 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |