The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Beaumont District (FY 2021)
Chambers | Hardin | Jasper | Jefferson | Liberty | Newton | Orange | Tyler |

Chambers County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0389-02-048SH 146ApprovedMay 2021$255,8136BRIDGE MAINTENANCE0.0
1464-01-018FM 1663ApprovedMay 2021$856,9731HAZARD ELIMINATION & SAFETY2.5
1023-01-035FM 563ActualMar 2021$5,069,7261SURFACING/ROADWAY RESTORATION3.0

Hardin County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
1194-02-019FM 943ApprovedJul 2021$1,993,8311SURFACING/ROADWAY RESTORATION0.0
0339-03-039SH 105ApprovedAug 2021$432,3248CONSTRUCT NEW ROAD0.0
1096-01-065FM 770ActualApr 2021$2,513,1558HAZARD ELIMINATION & SAFETY4.0

Jasper County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0920-12-044PWActualMar 2021$1,753,5531STATE PARK IMPROVEMENTS0.0
0877-01-043RE 255ApprovedJul 2021$1,950,0001SURFACING/ROADWAY RESTORATION0.0

Jefferson County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0920-00-145VAApprovedJun 2021$438,0708HAZARD ELIMINATION & SAFETY0.0
0932-02-052FM 365ApprovedMay 2021$1,813,0506BRIDGE REPLACEMENT6.0
0920-00-143VATentativeAug 2021$953,4391ADVANCED TRAFFIC MANAGEMENT SYSTEM0.0
0028-07-058US 90ActualJan 2021$804,2088INSTALL/UPGRADE ROADWAY LIGHTING0.0
0920-00-132VAActualJan 2021$1,255,6951HAZARD ELIMINATION & SAFETY0.0
0065-07-068US 69ApprovedAug 2021$1,451,2668HAZARD ELIMINATION & SAFETY0.0
0920-00-135VAActualOct 2020$873,09010LANDSCAPE DEVELOPMENT0.0
0920-00-134VAActualSep 2020$647,5981INSTALL/REPLACE SIGNS0.0
0200-15-026US 69ApprovedAug 2021$7,897,1048HAZARD ELIMINATION & SAFETY2.0
0368-04-033SH 124ActualMar 2021$2,417,3806BRIDGE REPLACEMENT4.0
0307-01-149SH 87ActualOct 2020$3,045,5941SURFACING/ROADWAY RESTORATION0.0
0368-03-037SH 124ActualApr 2021$426,6998CONSTRUCT NEW ROADWAY LANES4.0
0028-06-083US 90ApprovedMay 2021$5,019,3508TRAFFIC SIGNAL IMPROVEMENTS2.5
0920-00-131VAActualFeb 2021$2,368,8381HAZARD ELIMINATION & SAFETY0.0
0920-00-146VAApprovedJul 2021$730,6008TRAFFIC SURVEILLANCE0.0

Liberty County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0028-03-110US 90ActualOct 2020$1,313,07310CONSTRUCT PEDESTRIAN INFRASTRUCTURE4.0
0593-01-130SH 105ApprovedAug 2021$900,7638HAZARD ELIMINATION & SAFETY0.0
0028-03-107US 90ApprovedAug 2021$17,206,9541HAZARD ELIMINATION & SAFETY0.0
1061-01-033FM 1010ApprovedJul 2021$125,7778HAZARD ELIMINATION & SAFETY0.0
0388-03-081SH 146ActualApr 2021$389,9118HAZARD ELIMINATION & SAFETY0.0
0920-02-096VAApprovedMay 2021$390,1533CONSTRUCT PEDESTRIAN INFRASTRUCTURE2.0

Newton County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0499-02-031SH 12ApprovedJul 2021$1,586,50511SURFACING/ROADWAY RESTORATION0.0
0305-01-035SH 87ActualFeb 2021$1,707,12611SURFACING/ROADWAY RESTORATION0.0

Orange County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0028-14-118IH 10ActualSep 2020$10,449,1151SEAL COAT0.0
2562-01-023FM 1442ApprovedAug 2021$3,690,3548CONSTRUCT NEW ROAD0.0
0882-02-059FM 1006ActualApr 2021$597,3148HAZARD ELIMINATION & SAFETY0.0
0028-14-116IH 10ApprovedAug 2021$10,948,4226BRIDGE MAINTENANCE6.0
0305-07-071SH 87ApprovedJul 2021$2,950,0001SURFACING/ROADWAY RESTORATION0.0
0883-02-089FM 105ActualApr 2021$29,4668RAILROAD CROSSING IMPROVEMENTS0.0

Tyler County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
1585-01-025FM 1746ActualJan 2021$4,027,60811SURFACING/ROADWAY RESTORATION5.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract