Detail Letting Schedule for Upton County (FY 2021)

Last Update: Tuesday, August 13, 2024

Bid Tabulations Dashboard

This report will no longer be updated, please access links on the Contract Letting page.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Upton County (FY 2021)

CCSJ: 0076-06-037

District:ODESSALet Date:Oct 2019
Highway:US 67Let Status:Tentative
Project ID:STP 1902(150)CSJ:0076-06-037
Description:ROADWAY WIDENING TO A MODIFIED SUPER 2Handling
Code:
 
Limits From:SH 329Fund Cat:11
Limits To:US 385ESTIMATE:$29,946,000
Length:18.0Actual$0
 
Back...
Totals for 0076-06-037
Length:18
Estimate:$29,946,000
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract