Detail Letting Schedule for El Paso County (FY 2023)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
El Paso County (FY 2023) |
CCSJ: 0001-02-067 |
|||
District: | EL PASO | Let Date: | Jun 2023 |
Highway: | SH 20 | Let Status: | Tentative |
Project ID: | C 1-2-67 | CSJ: | 0001-02-067 |
Description: | REHABILITATE EXISTING ROADWAY | Handling Code: | |
Limits From: | DONIPHAN DRIVE | Fund Cat: | 1 |
Limits To: | SUNLAND PARK | ESTIMATE: | $10,550,481 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Jun 2023 |
Highway: | SH 20 | Let Status: | Tentative |
Project ID: | C 1-2-68 | CSJ: | 0001-02-068 |
Description: | REHABILITATE EXISTING ROADWAY | Handling Code: | |
Limits From: | BALTIMORE ST | Fund Cat: | 1 |
Limits To: | CINCINNATI AVE | ESTIMATE: | $137,030 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Jun 2023 |
Highway: | SH 20 | Let Status: | Tentative |
Project ID: | C 1-3-60 | CSJ: | 0001-03-060 |
Description: | REHABILITATE EXISTING ROADWAY | Handling Code: | |
Limits From: | CINCINNATI AVE | Fund Cat: | 1 |
Limits To: | E YANDELL DR | ESTIMATE: | $2,731,010 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0001-02-067 | ||
---|---|---|---|
Length: | 0 | ||
Estimate: | $13,418,520 | ||
Actual: | |||
CCSJ: 0001-02-074 |
|||
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | SH 20 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0001-02-074 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | AT BELVIDERE ST | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $281,205 |
Length: | 0.2 | Actual | $0 |
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | SH 20 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0002-01-106 |
Description: | TRAFFIC SIGNAL IMPROVEMENTS | Handling Code: | |
Limits From: | AT FM 76 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $402,967 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | US 67 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0020-08-049 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | AT US 90 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $107,268 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | SH 17 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0104-03-041 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 118 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $101,034 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | SH 17 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0104-03-042 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | AT SH 118 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $118,928 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | SH 17 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0104-05-027 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | AT W LINCOLN ST | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $58,509 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | SH 166 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0415-04-014 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | AT SH 17 | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $125,959 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | FM 659 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 1046-01-045 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | AT GEORGE DIETER DR | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $186,256 |
Length: | 0.2 | Actual | $0 |
Back... | Totals for 0001-02-074 | ||
Length: | 0.4 | ||
Estimate: | $1,382,126 | ||
Actual: | |||
CCSJ: 0167-02-079 |
|||
District: | EL PASO | Let Date: | Apr 2023 |
Highway: | BU 54-A | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0167-02-079 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.88 MI N OF SL 375 | Fund Cat: | 8 |
Limits To: | 2.88 MI N OF SL 375 | ESTIMATE: | $1,173,253 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Apr 2023 |
Highway: | SL 375 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 2552-04-054 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | COLES ST | Fund Cat: | 8 |
Limits To: | FRANCIS ST | ESTIMATE: | $1,481,812 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0167-02-079 | ||
Length: | 0 | ||
Estimate: | $2,655,065 | ||
Actual: | |||
CCSJ: 0374-02-122 |
|||
District: | EL PASO | Let Date: | Mar 2023 |
Highway: | US 62 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0374-02-122 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | 0.1 MI W OF KILLARMEY ST | Fund Cat: | 8 |
Limits To: | 0.1 MI E OF WEDGEWOOD DR | ESTIMATE: | $101,256 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Mar 2023 |
Highway: | SH 20 | Let Status: | Tentative |
Project ID: | STP()HES | CSJ: | 0001-02-075 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | COLONY COVE CT | Fund Cat: | 8 |
Limits To: | . | ESTIMATE: | $66,698 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0374-02-122 | ||
Length: | 0 | ||
Estimate: | $167,954 | ||
Actual: | |||
CCSJ: 0665-02-002 |
|||
District: | EL PASO | Let Date: | Apr 2023 |
Highway: | SS 320 | Let Status: | Tentative |
Project ID: | F () | CSJ: | 0665-02-002 |
Description: | CONSTRUCT FRONTAGE ROADS | Handling Code: | |
Limits From: | BU54 (DYER STREET ) | Fund Cat: | 1 |
Limits To: | RAILROAD DRIVE | ESTIMATE: | $19,709,165 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0665-02-002 | ||
Length: | 0 | ||
Estimate: | $19,709,165 | ||
Actual: | |||
CCSJ: 0924-00-109 |
|||
District: | EL PASO | Let Date: | Mar 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | F() | CSJ: | 0924-00-109 |
Description: | BRIDGE MAINTENANCE | Handling Code: | |
Limits From: | DISTRICTWIDE | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $1,442,308 |
Length: | 1.0 | Actual | $0 |
Back... | Totals for 0924-00-109 | ||
Length: | 1 | ||
Estimate: | $1,442,308 | ||
Actual: | |||
CCSJ: 0924-00-110 |
|||
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | F() | CSJ: | 0924-00-110 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | DISTRICTWIDE | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $2,884,615 |
Length: | 362.3 | Actual | $0 |
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | CR | Let Status: | Tentative |
Project ID: | STP ()HESG | CSJ: | 0924-06-646 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | (ON ASCENCION ST) GREG DR | Fund Cat: | 3 |
Limits To: | HORIZON BLVD | ESTIMATE: | $139,491 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0924-00-110 | ||
Length: | 362.3 | ||
Estimate: | $3,024,106 | ||
Actual: | |||
CCSJ: 0924-00-130 |
|||
District: | EL PASO | Let Date: | Mar 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | F() | CSJ: | 0924-00-130 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | DISTRICTWIDE | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $480,769 |
Length: | 1.0 | Actual | $0 |
Back... | Totals for 0924-00-130 | ||
Length: | 1 | ||
Estimate: | $480,769 | ||
Actual: | |||
CCSJ: 0924-00-145 |
|||
District: | EL PASO | Let Date: | May 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | CSJ: | 0924-00-145 | |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | DISTRICTWIDE | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $480,769 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0924-00-145 | ||
Length: | 0 | ||
Estimate: | $480,769 | ||
Actual: | |||
CCSJ: 0924-00-150 |
|||
District: | EL PASO | Let Date: | Jul 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | F() | CSJ: | 0924-00-150 |
Description: | PREVENTIVE MAINTENANCE | Handling Code: | |
Limits From: | DISTRICTWIDE | Fund Cat: | 1 |
Limits To: | DISTRICTWIDE | ESTIMATE: | $1,442,308 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0924-00-150 | ||
Length: | 0 | ||
Estimate: | $1,442,308 | ||
Actual: | |||
CCSJ: 0924-00-155 |
|||
District: | EL PASO | Let Date: | Jul 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | F() | CSJ: | 0924-00-155 |
Description: | LANDSCAPE DEVELOPMENT | Handling Code: | |
Limits From: | DISTRICTWIDE | Fund Cat: | 10 |
Limits To: | . | ESTIMATE: | $721,154 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0924-00-155 | ||
Length: | 0 | ||
Estimate: | $721,154 | ||
Actual: | |||
CCSJ: 0924-00-161 |
|||
District: | EL PASO | Let Date: | Aug 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | F () | CSJ: | 0924-00-161 |
Description: | INFRASTRUCTURE IMPROVEMENTS | Handling Code: | |
Limits From: | DISTRICTWIDE (ITS) | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $480,769 |
Length: | 1.0 | Actual | $0 |
Back... | Totals for 0924-00-161 | ||
Length: | 1 | ||
Estimate: | $480,769 | ||
Actual: | |||
CCSJ: 0924-06-564 |
|||
District: | EL PASO | Let Date: | Mar 2023 |
Highway: | CS | Let Status: | Tentative |
Project ID: | STP 2021(088)MM | CSJ: | 0924-06-564 |
Description: | INFRASTRUCTURE IMPROVEMENTS | Handling Code: | LC |
Limits From: | PELLICANO DRIVE | Fund Cat: | 3 |
Limits To: | MONTWOOD | ESTIMATE: | $11,965,759 |
Length: | 3.0 | Actual | $0 |
Back... | Totals for 0924-06-564 | ||
Length: | 3 | ||
Estimate: | $11,965,759 | ||
Actual: | |||
CCSJ: 0924-06-566 |
|||
District: | EL PASO | Let Date: | Mar 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | CM () | CSJ: | 0924-06-566 |
Description: | TRAFFIC MANAGEMENT CENTER UPGRADE | Handling Code: | LC |
Limits From: | CITY OF EL PASO CITY LIMITS | Fund Cat: | 3 |
Limits To: | . | ESTIMATE: | $146,798 |
Length: | 1.0 | Actual | $0 |
Back... | Totals for 0924-06-566 | ||
Length: | 1 | ||
Estimate: | $146,798 | ||
Actual: | |||
CCSJ: 0924-06-574 |
|||
District: | EL PASO | Let Date: | Jul 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | CM ( ) | CSJ: | 0924-06-574 |
Description: | TRANSPORTATION SERVICE OPERATIONS | Handling Code: | TR |
Limits From: | DOWNTOWN TERMINAL-SANTA FE | Fund Cat: | 3 |
Limits To: | FAR EAST TERMINAL-RC POE & EDGEMERE | ESTIMATE: | $1,917,593 |
Length: | 1.0 | Actual | $0 |
Back... | Totals for 0924-06-574 | ||
Length: | 1 | ||
Estimate: | $1,917,593 | ||
Actual: | |||
CCSJ: 0924-06-611 |
|||
District: | EL PASO | Let Date: | May 2023 |
Highway: | CS | Let Status: | Tentative |
Project ID: | STP ()MM | CSJ: | 0924-06-611 |
Description: | BRIDGE REPLACEMENT | Handling Code: | LC |
Limits From: | NATHAN BAY DRIVE | Fund Cat: | 3 |
Limits To: | DYER STREET | ESTIMATE: | $17,945,351 |
Length: | 0.7 | Actual | $0 |
Back... | Totals for 0924-06-611 | ||
Length: | 0.7 | ||
Estimate: | $17,945,351 | ||
Actual: | |||
CCSJ: 0924-06-619 |
|||
District: | EL PASO | Let Date: | May 2023 |
Highway: | CS | Let Status: | Tentative |
Project ID: | C 924-6-619 | CSJ: | 0924-06-619 |
Description: | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | Handling Code: | LC |
Limits From: | AT THE INTER. BRIDGE OF THE AMERICAS | Fund Cat: | 3 |
Limits To: | ZARAGOZA POE | ESTIMATE: | $14,907,295 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0924-06-619 | ||
Length: | 0 | ||
Estimate: | $14,907,295 | ||
Actual: | |||
CCSJ: 0924-06-640 |
|||
District: | EL PASO | Let Date: | Nov 2022 |
Highway: | CS | Let Status: | Tentative |
Project ID: | STP ()TP | CSJ: | 0924-06-640 |
Description: | BICYCLE AND PEDESTRIAN IMPROVEMENTS | Handling Code: | LC |
Limits From: | ALONG MAGOFFIN SAN ANTONIO AVENUE | Fund Cat: | 3 |
Limits To: | COTTON STREET | ESTIMATE: | $796,888 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0924-06-640 | ||
Length: | 0 | ||
Estimate: | $796,888 | ||
Actual: | |||
CCSJ: 0924-06-644 |
|||
District: | EL PASO | Let Date: | Jan 2023 |
Highway: | CS | Let Status: | Tentative |
Project ID: | STP ()HESG | CSJ: | 0924-06-644 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | ALBERTON AVE | Fund Cat: | 3 |
Limits To: | 0.04 MI S OF LTV RD | ESTIMATE: | $751,207 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0924-06-644 | ||
Length: | 0 | ||
Estimate: | $751,207 | ||
Actual: | |||
CCSJ: 0924-06-648 |
|||
District: | EL PASO | Let Date: | Feb 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | STP () TAPS | CSJ: | 0924-06-648 |
Description: | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | Handling Code: | LC |
Limits From: | ONG AVE.,WALKER AVE., 5TH ST., MIKEMAROS | Fund Cat: | 3 |
Limits To: | AND ON ASPEN HILL ST. | ESTIMATE: | $1,636,650 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0924-06-648 | ||
Length: | 0 | ||
Estimate: | $1,636,650 | ||
Actual: | |||
CCSJ: 3451-01-033 |
|||
District: | EL PASO | Let Date: | Apr 2023 |
Highway: | FM 1281 | Let Status: | Tentative |
Project ID: | F() | CSJ: | 3451-01-033 |
Description: | REHABILITATE EXISTING ROADWAY | Handling Code: | |
Limits From: | FM 76 | Fund Cat: | 1 |
Limits To: | ASCENSION RD | ESTIMATE: | $13,395,223 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 3451-01-033 | ||
Length: | 0 | ||
Estimate: | $13,395,223 | ||
Actual: | |||
CCSJ: 3451-01-040 |
|||
District: | EL PASO | Let Date: | Jul 2023 |
Highway: | FM 1281 | Let Status: | Tentative |
Project ID: | F () | CSJ: | 3451-01-040 |
Description: | INTERSECTION IMPROVEMENT | Handling Code: | |
Limits From: | HORIZON BLVD AT DARRINGTON INTERSECTION | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $5,769,231 |
Length: | 0.0 | Actual | $0 |
District: | EL PASO | Let Date: | Jul 2023 |
Highway: | CS | Let Status: | Tentative |
Project ID: | STP()MM | CSJ: | 0924-06-587 |
Description: | RECONSTRUCT EXISTING ROADWAY | Handling Code: | |
Limits From: | EASTLAKE BOULEVARD | Fund Cat: | 7 |
Limits To: | OXBOW DRIVE | ESTIMATE: | $11,710,436 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 3451-01-040 | ||
Length: | 0 | ||
Estimate: | $17,479,667 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |