Letting Schedule for Dallas District (FY 2023)

Last Update: Monday, January 24, 2022

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Dallas District (FY 2023)
Collin | Dallas | Denton | Ellis | Kaufman | Navarro | Rockwall |

Collin County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
1391-01-022FM 1377TentativeJul 2023$6,479,4678HAZARD ELIMINATION & SAFETY0.0
0135-02-069US 380TentativeNov 2022$1,559,1663INSTALL ILLUMINATION0.0
0918-24-253CSTentativeAug 2023$402,0003TRAFFIC SIGNAL IMPROVEMENTS0.0
0918-24-251CSTentativeAug 2023$1,867,0003TRAFFIC SIGNAL IMPROVEMENTS0.0
0047-06-158US 75TentativeDec 2022$30,547,4157HIGHWAY IMPROVEMENT0.0
1391-01-021FM 1377TentativeMar 2023$5,995,9931REPAIR ROADWAY0.0
0619-01-026FM 6TentativeOct 2022$7,017,8831ADDING SHOULDERS WITH NO ADDED CAPACITY0.0
2461-01-010FM 2170TentativeSep 2022$2,457,8621REHABILITATE EXISTING ROADWAY0.0
0816-05-025FM 2862TentativeJun 2023$4,922,6298HAZARD ELIMINATION & SAFETY0.0
3427-03-007FM 3356TentativeApr 2023$3,342,0511REHABILITATE EXISTING ROADWAY0.0
1392-01-044FM 1378TentativeMay 2023$5,786,6967INTERSECTION IMPROVEMENT0.0

Dallas County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0918-47-240CSTentativeSep 2022$24,100,3263INTERSECTION IMPROVEMENT0.0
0918-47-239CSTentativeAug 2023$10,525,0003CONSTRUCT NEW ROADWAY LANES0.0
0918-47-328VATentativeAug 2023$800,0007TRANSPORTATION NON-ROADWAY0.0
0918-47-342CSTentativeApr 2023$2,080,3338TRAFFIC SIGNAL IMPROVEMENTS0.0
0047-07-245US 75TentativeMar 2023$1,334,7318INSTALL/REHABILITATE ITS0.0
0918-47-327VATentativeAug 2023$325,6613BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
0918-47-366CSTentativeAug 2023$5,437,5007TRANSPORTATION NON-ROADWAY0.0
0581-01-156SL 12TentativeNov 2022$8,540,4781REHABILITATE EXISTING ROADWAY0.0
1068-04-178IH 30TentativeOct 2022$310,0003LANDSCAPE DEVELOPMENT0.0
0918-47-372VATentativeAug 2023$750,0003BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
2964-01-052SH 161TentativeAug 2023$1,050,2203INSTALL/REHABILITATE ITS0.0
0918-47-347CSTentativeFeb 2023$2,176,0818TRAFFIC SIGNAL IMPROVEMENTS0.0
0918-47-329VATentativeAug 2023$245,0007TRANSPORTATION NON-ROADWAY0.0
0918-47-362VATentativeAug 2023$5,100,0005BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
0918-47-365VATentativeAug 2023$8,000,0003TRANSPORTATION NON-ROADWAY0.0
0918-47-364VATentativeAug 2023$4,000,0007TRANSPORTATION NON-ROADWAY0.0
0918-00-315VATentativeAug 2023$780,0003TRANSPORTATION NON-ROADWAY0.0
0918-00-341VATentativeAug 2023$5,850,0007TRANSPORTATION NON-ROADWAY0.0
0918-47-298VATentativeAug 2023$2,999,6843BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
0581-01-157SL 12TentativeAug 2023$1,000,0003INTERSECTION IMPROVEMENT0.0
0918-00-298VATentativeAug 2023$1,560,0005TRANSIT SYSTEM OPERATIONS0.0
0918-00-363VATentativeAug 2023$1,496,2503TRANSPORTATION NON-ROADWAY0.0
0918-47-273VATentativeAug 2023$4,000,0003TRAFFIC SIGNAL IMPROVEMENTS0.0
0918-47-272VATentativeAug 2023$4,545,7253BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
0918-47-286VATentativeAug 2023$18,090,0003ROADWAY REHABILITATION/RECONSTRUCTION WITH NO ADDED CAPACITY0.0
0918-00-378VATentativeAug 2023$3,100,0007TRANSPORTATION NON-ROADWAY0.0
0918-47-294VATentativeAug 2023$400,0007TRANSPORTATION NON-ROADWAY0.0
0918-47-309VATentativeAug 2023$7,250,0003BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
0092-02-137IH 45TentativeJun 2023$3,125,0005INSTALL/REHABILITATE ITS0.0
0918-00-351VATentativeSep 2022$2,500,0001INSTALL TRAFFIC SIGNAL0.0
0918-47-326VATentativeAug 2023$1,962,9803BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
0009-03-048SH 66TentativeMay 2023$2,939,8993INTERSECTION IMPROVEMENT0.0
0918-47-236VATentativeAug 2023$3,750,0003BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
0918-47-325VATentativeAug 2023$3,836,0923TRANSPORTATION NON-ROADWAY0.0
0918-47-359FDTentativeJul 2023$8,342,98610REHABILITATE EXISTING ROADWAY0.0
0092-14-098IH 45TentativeJul 2023$11,967,2751BRIDGE MAINTENANCE0.0
2374-03-098IH 20TentativeJun 2023$17,191,1601REHABILITATE EXISTING ROADWAY0.0
0918-47-323VATentativeAug 2023$1,702,9483BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0

Denton County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0081-05-051FM 3524TentativeOct 2022$9,188,4911SEAL COAT0.0
0918-46-327CSTentativeJun 2023$1,249,2088TRAFFIC SIGNAL IMPROVEMENTS0.0
0918-46-306CSTentativeAug 2023$953,1353BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
0816-02-083FM 455TentativeFeb 2023$3,103,7736BRIDGE REPLACEMENT0.0
0918-46-314VATentativeAug 2023$455,0003TRANSPORTATION NON-ROADWAY0.0
2250-02-020SL 288TentativeApr 2023$4,152,7841REHABILITATE EXISTING ROADWAY0.0
0918-46-267CSTentativeAug 2023$330,6003CONSTRUCT PEDESTRIAN INFRASTRUCTURE0.0
1315-01-028FM 1385TentativeApr 2023$4,726,7401REHABILITATE EXISTING ROADWAY0.0
0918-46-305CSTentativeAug 2023$952,8883BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
1311-01-060FM 1171TentativeJul 2023$535,0003CONSTRUCT NEW ROADWAY LANES0.0
0196-02-128IH 35ETentativeJan 2023$62,438,2741INTERCHANGE IMPROVEMENT0.0
1567-01-042FM 720TentativeDec 2022$1,056,5871REPAIR ROADWAY0.0
0918-46-282CSTentativeAug 2023$3,739,1323BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0

Ellis County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0172-05-124US 287TentativeAug 2023$1,795,0908INTERSECTION IMPROVEMENT0.0
0918-22-168VATentativeAug 2023$700,0005BICYCLE AND PEDESTRIAN IMPROVEMENTS0.0
0092-03-057IH 45TentativeJan 2023$2,161,1891REPAIR ROADWAY0.0
1159-02-037FM 879TentativeAug 2023$4,841,3311REHABILITATE EXISTING ROADWAY0.0
0260-02-051US 67TentativeAug 2023$2,416,9728HAZARD ELIMINATION & SAFETY0.0

Kaufman County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0173-04-057SH 34TentativeOct 2022$12,936,4431RECONSTRUCT EXISTING ROADWAY0.0
0095-04-074US 80TentativeMay 2023$5,208,7101REPAIR ROADWAY0.0
1975-02-013FM 1895TentativeFeb 2023$8,992,3581REHABILITATE EXISTING ROADWAY0.0
0918-11-100CRTentativeMay 2023$11,417,4916BRIDGE REPLACEMENT0.0
0095-03-080US 80TentativeNov 2022$110,301,11111RECONSTRUCT EXISTING ROADWAY0.0
0095-14-033IH 20TentativeMay 2023$1,474,1231INSTALL/REPLACE SIGNS0.0
2588-01-021FM 548TentativeJun 2023$3,348,6951RESURFACE ROADWAY0.0
0173-02-077SH 34TentativeJun 2023$7,416,4268REPAIR ROADWAY0.0

Navarro County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
3090-01-012FM 3041TentativeApr 2023$4,243,1011RECONSTRUCT EXISTING ROADWAY0.0

Rockwall County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
1290-02-023SH 276TentativeMar 2023$605,0971RESURFACE ROADWAY0.0
0009-12-219IH 30TentativeNov 2022$278,318,2881WIDEN ROAD - ADD LANES0.0
0009-12-220IH 30TentativeOct 2022$250,864,7041WIDEN ROAD - ADD SHOULDERS0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract