Detail Letting Schedule for Montgomery County (FY 2023)
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Montgomery County (FY 2023) |
CCSJ: 0177-05-112 |
|||
District: | HOUSTON | Let Date: | Oct 2022 |
Highway: | IH 69 | Let Status: | Tentative |
Project ID: | C 177-5-112 | CSJ: | 0177-05-112 |
Description: | ADVANCED TRAFFIC MANAGEMENT SYSTEM | Handling Code: | |
Limits From: | HARRIS COUNTY LINE | Fund Cat: | 1 |
Limits To: | LIBERTY COUNTY LINE | ESTIMATE: | $13,600,371 |
Length: | 17.7 | Actual | $0 |
Back... | Totals for 0177-05-112 | ||
---|---|---|---|
Length: | 17.7 | ||
Estimate: | $13,600,371 | ||
Actual: | |||
CCSJ: 0912-37-240 |
|||
District: | HOUSTON | Let Date: | Jan 2023 |
Highway: | CR | Let Status: | Tentative |
Project ID: | BR 2021(232) | CSJ: | 0912-37-240 |
Description: | BRIDGE REPLACEMENT | Handling Code: | |
Limits From: | FAULKNER RD (CR 9295) AT PEACH CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $716,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0912-37-240 | ||
Length: | 0 | ||
Estimate: | $716,000 | ||
Actual: | |||
CCSJ: 0912-37-242 |
|||
District: | HOUSTON | Let Date: | Jan 2023 |
Highway: | VA | Let Status: | Tentative |
Project ID: | CSJ: | 0912-37-242 | |
Description: | ADAPTIVE SIGNAL COORD AND SYNC | Handling Code: | XX |
Limits From: | VARIOUS LOCATIONS ON SH 242 | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $250,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0912-37-242 | ||
Length: | 0 | ||
Estimate: | $250,000 | ||
Actual: | |||
CCSJ: 1402-03-012 |
|||
District: | HOUSTON | Let Date: | Feb 2023 |
Highway: | FM 1375 | Let Status: | Tentative |
Project ID: | STP ( ) | CSJ: | 1402-03-012 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 149 | Fund Cat: | 1 |
Limits To: | WALKER C/L | ESTIMATE: | $13,500,000 |
Length: | 6.0 | Actual | $0 |
Back... | Totals for 1402-03-012 | ||
Length: | 6 | ||
Estimate: | $13,500,000 | ||
Actual: | |||
CCSJ: 1416-03-018 |
|||
District: | HOUSTON | Let Date: | Feb 2023 |
Highway: | FM 1486 | Let Status: | Tentative |
Project ID: | C 1416-3-18 | CSJ: | 1416-03-018 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 1774 | Fund Cat: | 1 |
Limits To: | SH 105 | ESTIMATE: | $5,300,000 |
Length: | 10.6 | Actual | $0 |
Back... | Totals for 1416-03-018 | ||
Length: | 10.6 | ||
Estimate: | $5,300,000 | ||
Actual: | |||
CCSJ: 1706-02-008 |
|||
District: | HOUSTON | Let Date: | Sep 2022 |
Highway: | FM 1791 | Let Status: | Approved |
Project ID: | F 2023(021) | CSJ: | 1706-02-008 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | WALKER C/L | Fund Cat: | 1 |
Limits To: | FM 149 | ESTIMATE: | $10,589,662 |
Length: | 3.3 | Actual | $0 |
Back... | Totals for 1706-02-008 | ||
Length: | 3.3 | ||
Estimate: | $10,589,662 | ||
Actual: | |||
CCSJ: 1912-01-022 |
|||
District: | HOUSTON | Let Date: | Nov 2022 |
Highway: | FM 2090 | Let Status: | Tentative |
Project ID: | C 1912-1-22 | CSJ: | 1912-01-022 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | FM 3083 | Fund Cat: | 1 |
Limits To: | IH 69 | ESTIMATE: | $7,000,000 |
Length: | 10.6 | Actual | $0 |
Back... | Totals for 1912-01-022 | ||
Length: | 10.6 | ||
Estimate: | $7,000,000 | ||
Actual: | |||
CCSJ: 1986-01-070 |
|||
District: | HOUSTON | Let Date: | Aug 2023 |
Highway: | FM 1314 | Let Status: | Tentative |
Project ID: | CSJ: | 1986-01-070 | |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | |
Limits From: | SH 99 | Fund Cat: | 8 |
Limits To: | SL 494 | ESTIMATE: | $4,075,288 |
Length: | 4.6 | Actual | $0 |
Back... | Totals for 1986-01-070 | ||
Length: | 4.6 | ||
Estimate: | $4,075,288 | ||
Actual: | |||
CCSJ: 3050-02-036 |
|||
District: | HOUSTON | Let Date: | Sep 2022 |
Highway: | FM 2978 | Let Status: | Approved |
Project ID: | C 3050-2-36 | CSJ: | 3050-02-036 |
Description: | ADVANCED TRAFFIC MANAGEMENT SYSTEM | Handling Code: | |
Limits From: | FM 1488 | Fund Cat: | 1 |
Limits To: | HARRIS C/L | ESTIMATE: | $1,050,000 |
Length: | 6.5 | Actual | $0 |
District: | HOUSTON | Let Date: | Sep 2022 |
Highway: | FM 2978 | Let Status: | Approved |
Project ID: | C 3050-3-23 | CSJ: | 3050-03-023 |
Description: | ADVANCED TRAFFIC MANAGEMENT SYSTEM | Handling Code: | |
Limits From: | MONTGOMERY C/L | Fund Cat: | 1 |
Limits To: | FM 2920 | ESTIMATE: | $450,000 |
Length: | 2.3 | Actual | $0 |
Back... | Totals for 3050-02-036 | ||
Length: | 8.8 | ||
Estimate: | $1,500,000 | ||
Actual: | |||
CCSJ: 3510-07-015 |
|||
District: | HOUSTON | Let Date: | Feb 2023 |
Highway: | SH 99 | Let Status: | Tentative |
Project ID: | CSJ: | 3510-07-015 | |
Description: | LANDSCAPE DEVELOPMENT | Handling Code: | |
Limits From: | SPRING CREEK (HARRIS/MONTGOMERY C/L) | Fund Cat: | 3 |
Limits To: | IH 69 | ESTIMATE: | $2,750,000 |
Length: | 12.1 | Actual | $0 |
Back... | Totals for 3510-07-015 | ||
Length: | 12.1 | ||
Estimate: | $2,750,000 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |