This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Wharton County (FY 2023) |
CCSJ: 0089-06-092 |
|||
District: | YOAKUM | Let Date: | Jul 2023 |
Highway: | US 59 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0089-06-092 |
Description: | INSTALL RAISED MEDIAN | Handling Code: | |
Limits From: | FM 1163 | Fund Cat: | 8 |
Limits To: | 900 FT N OF CR 355 | ESTIMATE: | $2,877,769 |
Length: | 2.5 | Actual | $0 |
District: | YOAKUM | Let Date: | Jul 2023 |
Highway: | US 59 | Let Status: | Tentative |
Project ID: | STP ( )HES | CSJ: | 0089-07-164 |
Description: | INSTALL RAISED MEDIAN | Handling Code: | |
Limits From: | FM 960 | Fund Cat: | 8 |
Limits To: | FM 1163 | ESTIMATE: | $1,354,244 |
Length: | 4.4 | Actual | $0 |
District: | YOAKUM | Let Date: | Jul 2023 |
Highway: | US 77 | Let Status: | Tentative |
Project ID: | STP( )HES | CSJ: | 0371-01-093 |
Description: | INSTALL RAISED MEDIAN | Handling Code: | |
Limits From: | 750 FT N OF COLETO CREEK BRIDGE | Fund Cat: | 8 |
Limits To: | FLEMING PRAIRIE RD | ESTIMATE: | $580,357 |
Length: | 0.8 | Actual | $0 |
Back... | Totals for 0089-06-092 | ||
---|---|---|---|
Length: | 7.7 | ||
Estimate: | $4,812,370 | ||
Actual: | |||
CCSJ: 0089-10-026 |
|||
District: | YOAKUM | Let Date: | Oct 2022 |
Highway: | SH 60 | Let Status: | Approved |
Project ID: | F 2023(060) | CSJ: | 0089-10-026 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | US 59 | Fund Cat: | 1 |
Limits To: | FM 1301 | ESTIMATE: | $2,300,000 |
Length: | 3.0 | Actual | $0 |
District: | YOAKUM | Let Date: | Oct 2022 |
Highway: | SH 60 | Let Status: | Approved |
Project ID: | F 2023(061) | CSJ: | 0240-03-037 |
Description: | SURFACING/ROADWAY RESTORATION | Handling Code: | |
Limits From: | UA 90 | Fund Cat: | 1 |
Limits To: | FM 2919 | ESTIMATE: | $1,000,000 |
Length: | 1.8 | Actual | $0 |
Back... | Totals for 0089-10-026 | ||
Length: | 4.8 | ||
Estimate: | $3,300,000 | ||
Actual: | |||
CCSJ: 1412-03-038 |
|||
District: | YOAKUM | Let Date: | Oct 2022 |
Highway: | FM 1301 | Let Status: | Approved |
Project ID: | CC 1412-3-38 | CSJ: | 1412-03-038 |
Description: | HIGHWAY IMPROVEMENT | Handling Code: | |
Limits From: | SH 60 IN WHARTON | Fund Cat: | 3 |
Limits To: | US 59 | ESTIMATE: | $13,000,000 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 1412-03-038 | ||
Length: | 0 | ||
Estimate: | $13,000,000 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |