Senate District 23 Construction Report
Last Update: Sunday, November 10, 2024
|
  |
Projects Under Construction |
  |
TxDOT District | County | CCSJ | Project ID | Obligated Amount | Other Sharing Districts |
Dallas | Dallas | 300001028 | F 2B24(225) | $16,188,626.00 | 016, 023 |
Dallas | Dallas | 000902074 | F 2B24(321) | $861,720.00 | 023 |
Dallas | Dallas | 035305128 | F 2B24(290) | $14,715,096.44 | 016, 023 |
Dallas | Dallas | 091847360 | C 918-47-360 | $3,669,509.03 | 023 |
Dallas | Dallas | 058101164 | STP 2025(182)VRU | $3,333,333.32 | 023, 016 |
Dallas | Dallas | 009201052 | NH 2013(596) | $78,665,971.49 | 023 |
Dallas | Dallas | 009202141 | BR 2023(441) | $4,336,407.90 | 023, 002 |
Dallas | Dallas | 091847248 | STP 2022(431)HES | $1,824,000.00 | 002, 023 |
Dallas | Dallas | 004707237 | STP 2022(617)HES | $2,951,302.78 | 023, 016 |
Dallas | Dallas | 296410008 | F 2021(858) | $77,975,540.90 | 023, 022 |
Dallas | Dallas | 091847249 | STP 2022(338)HES | $1,724,000.00 | 016, 023, 002 |
Dallas | Dallas | 237404085 | F 2022(153) | $79,838,372.30 | 023 |
Dallas | Dallas | 009202138 | STP 2B24(163)VRU | $2,894,528.77 | 023 |
Dallas | Dallas | 019603294 | F 2B24(167) | $8,080,871.80 | 016, 023 |
Dallas | Dallas | 237404086 | C 2374-4-86 | $18,745,268.24 | 023 |
Dallas | Dallas | 004707243 | STP 2B24(162)VRU | $8,247,829.80 | 023, 016, 002 |
Dallas | Dallas | 058101161 | STP 2B24(143)VRU | $3,166,592.92 | 008, 016, 023 |
Dallas | Dallas | 019702137 | C 197-2-137 | $28,303,655.62 | 016, 023 |
Dallas | Dallas | 009202135 | F 2B23(093) | $7,294,650.85 | 023 |
Dallas | Dallas | 009214108 | C 92-14-108 | $3,175,651.00 | 023 |
Dallas | Dallas | 104703079 | STP 2024(350)TP | $4,250,000.00 | 023 |
Dallas | Dallas | 009214103 | F 2024(581) | $7,188,411.94 | 023 |
Dallas | Dallas | 237403099 | BR 2024(745) | $5,746,216.52 | 016, 023 |
Dallas | Dallas | 019702135 | F 2022(999) | $26,852,159.34 | 016, 023 |
Dallas | Dallas | 009214086 | BR 2024(349) | $21,883,782.80 | 023 |
Dallas | Dallas | 004801069 | F 2023(983) | $7,856,752.26 | 023 |
Dallas | Dallas | 009214104 | F 2B23(095) | $3,534,464.30 | 023 |
Dallas | Dallas | 237403098 | C 2374-3-98 | $20,222,498.00 | 016, 023 |
Dallas | Dallas | 091847342 | STP 2023(705)HESG | $2,762,362.50 | 016, 023, 012 |
Dallas | Dallas | 091847347 | STP 2023(440)HESG | $1,765,418.20 | 023 |
Dallas | Dallas | 009202137 | CM 2023(611) | $4,499,999.97 | 002, 023 |
Dallas | Kaufman | 009514033 | C 95-14-33 | $2,192,309.35 | 023, 016, 002 |
Dallas | Kaufman | 009505063 | F 2022(826) | $2,155,024.00 | 023, 002 |
  |
|
  |
Total number of projects under construction: 33 |
Total obligated amount: $ 476,902,328.34 |
  |
|