DIVISION VI - LIGHTING AND SIGNING (Items 610 to 636)

Table of Contents

610 ROADWAY ILLUMINATION ASSEMBLIES
613 HIGH MAST ILLUMINATION POLES
614 HIGH MAST ILLUMINATION ASSEMBLIES
616 PERFORMANCE TESTING OF LIGHTING SYSTEMS
617 TEMPORARY ROADWAY ILLUMINATION
618 CONDUIT
620 ELECTRICAL CONDUCTORS
621 TRAY CABLE
622 DUCT CABLE
624 GROUND BOXES
625 ZINC-COATED STEEL WIRE STRAND
627 TREATED TIMBER POLES
628 ELECTRICAL SERVICES
634 PLYWOOD SIGNS
636 ALUMINUM SIGNS

 

ITEM NO - TITLE AND REQUIREMENTS

610 - ROADWAY ILLUMINATION ASSEMBLIES

SPECIFICATION REQUIREMENTS
1) Show locations and types of roadway illumination assemblies to be installed on plans.
2)  Show locations and types of roadway illumination assemblies to be relocated on plans. The roadway illumination assemblies will be reinstalled at the locations shown on plans.
3)  Show locations and types of roadway illumination assemblies to be removed on plans.
4)  Pay for the foundations of roadway illumination assemblies under Item 416.
5)  New drilled shaft foundations will be paid for under Item 416, “Drilled Shaft Foundations.” New concrete riprap placed around foundations will be paid for under Item 432, “Riprap.” New conduit will be paid for under Item 618, “Conduit.” New conductors, except the conductors internal to the pole, will be paid for under Item 620, “Electrical Conductors.” New duct cable will be paid for under Item 622, “Duct Cable.” New ground boxes will be paid for under Item 624, “Ground Boxes.” New electrical services will be paid for under Item 628, “Electrical Services.”.
6)  Use the following Statewide Standard Details Sheets for the fabrication, installation, relocation, and removal of roadway illumination assemblies:

 

ED (1) Electrical Details - Conduit
ED (2) Electrical Details - Conductors
RID (1) Roadway Illumination Details – Poles
RID (2) Roadway Illumination Details- Fixtures
RID (3) Roadway Illumination Details- Fixtures & Foundations
RID (4) Roadway Illumination Details- Underpass Lighting - Cobra Head
RID (5) Roadway Illumination Details - Underpass Lighting - Induction Fluorescent
RID (6) Roadway Illumination Details - Foundations

 

PAYMENT DESCRIPTION UNITS
1) "INS RD IL AM (Type Specified)" EA
2) "RELOCATE RD IL ASM (Type Specified)" EA
3) "REMOVE RD IL ASM (Type Specified)" EA

REFERENCE ITEMS
(421), (441), (442), (445), (446), (449), (616), (620)

Go to Top

613 - HIGH MAST ILLUMINATION POLES

SPECIFICATION REQUIREMENTS
1)  Show locations and heights of the high mast illumination poles on plans.
2)  The airway-highway clearance must be approved by the FAA if located near an airport and the high mast illumination assemblies protrude into the navigable air space.  This should be handled in the early stages of plan development.
3)  Pay for the foundations of the high mast illumination poles under Item 416.
4)  All pole shaft sections will be match-marked as shown on plans.
5)  Show riprap around pole foundations on plans.
6)  New drilled shaft foundations will be paid for under Item 416, “Drilled Shaft Foundations.” New riprap will be paid for under Item 432, “Riprap.” New high mast illumination assemblies will be paid for under Item 614, “High Mast Illumination Assemblies.” New ground boxes will be paid for under Item 624, “Ground Boxes.” New electrical Services will be paid for under Item 628, “Electrical Services.”
7)  Use the following Statewide Standard Details Sheets for the fabrication and installation of high mast illumination poles:

 

HMIP (1) High Mast Illumination Poles- Poles
HMIP (2) High Mast Illumination Poles- Poles
HMIF (1) High Mast Illumination Foundations- Foundations
HMIF (2) High Mast Illumination Foundations- Foundations

 

PAYMENT DESCRIPTION UNITS
"HI MST IL POLE (Height Specified) (Wind Design Specified)" EA

REFERENCE ITEMS
(421), (441), (442), (445), (449), (618)

Go to Top

614 - HIGH MAST ILLUMINATION ASSEMBLIES

SPECIFICATION REQUIREMENTS
1)  Show locations and types of high mast illumination assemblies on plans.
2)  New poles for high mast illumination assemblies will be paid for under Item 613, “High Mast Illumination Poles.” New electrical services will be paid for under Item 628, “Electrical Services.”
3)  Use the following Statewide Standard Details Sheets for the high mast illumination assemblies:

 

HMID (1) High Mast Illumination Details- Ring Details
HMID (2) High Mast Illumination Details- Electrical Cable Pulley
HMID (3) High Mast Illumination Details- Ring Details
HMID (4) High Mast Illumination Details- Winch and Power Drive
HMID (5) High Mast Illumination Details- Schematic
HMID (6) High Mast Illumination Details- Z-Pattern
HMID (7) High Mast Illumination Details- Light Settings
HMID (8) High Mast Illumination Details- Fixtures
HMID (9) High Mast Illumination Details- Fixtures & Winch
HMID (10) High Mast Illumination Details - Power Drive Assembly

 

PAYMENT DESCRIPTION UNITS
1) "HI MST IL ASM (Type Specified)" EA

REFERENCE ITEMS
(441), (442), (445), (446), (616), (620)

Go to Top

616 - PERFORMANCE TESTING OF LIGHTING SYSTEMS

SPECIFICATION REQUIREMENTS
None

PAYMENT AND MEASUREMENT
Subsidiary to the various bid items in the contract.

REFERENCE ITEMS
(618), (620), (622)

Go to Top

617 - TEMPORARY ROADWAY ILLUMINATION

SPECIFICATION REQUIREMENTS
1)  Any equipment furnished by the department will be picked up by the contractor at locations shown on plans.
2)  Locations and types of temporary roadway illumination to be installed or relocated must be shown on plans.
3)  Any unused or salvageable equipment will be returned to the department by the contractor at the location shown on plans.
4)  The following Statewide Standard Details Sheets may be required for the temporary lighting system:

ED (1) Electrical Details - Conduit

ED (2)

Electrical Details - Conductors

ED (3)

Electrical Details - Ground Boxes

ED (4)

Electrical Details – Electrical Services

ED (5)

Electrical Details – Electrical Services

ED (6)

Electrical Details – Electrical Services

ED (8)

Electrical Details – Electrical Services

ED (9)

Electrical Details – Electrical Services

ED (10)

Electrical Details – Duct Cable

ED (12)

Electrical Details – Electrical Services

RID (1)

Roadway Illumination Details – Poles

RID (2)

Roadway Illumination Details- Fixtures

RID (3)

Roadway Illumination Details- Fixtures & Foundations

RID (4)

Roadway Illumination Details- Underpass Lighting

HMIP (1)

High Mast Illumination Poles- Poles

HMIP (2)

High Mast Illumination Poles- Poles

HMIF (1)

High Mast Illumination Foundations- Foundations

HMIF (2)

High Mast Illumination Foundations- Foundations

HMID (1)

High Mast Illumination Details- Ring Details

HMID (2)

High Mast Illumination Details- Electrical Cable Pulley

HMID (3)

High Mast Illumination Details- Ring Details

HMID (4)

High Mast Illumination Details- Winch and Power Drive

HMID (5)

High Mast Illumination Details- Schematic

HMID (6)

High Mast Illumination Details- Z-Pattern

HMID (7)

High Mast Illumination Details- Light Settings

HMID (8)

High Mast Illumination Details – Fixtures

HMID (9)

High Mast Illumination Details- Fixtures & Winch

HMID (10)

High Mast Illumination Details- Power Drive Assembly

 

PAYMENT DESCRIPTION UNITS
1) "TEMP RD IL (INSTALL) (FIXTURES)" EA
2) "TEMP RD IL (RELOCATE) (FIXTURES)" EA
3) "TEMP RD IL (MAINTAIN) (FIXTURES))" MO

REFERENCE ITEMS
(416), (610), (613), (614), (618), (620), (621), (622), (624), (627). (628)

Go to Top

618 - CONDUIT

SPECIFICATION REQUIREMENTS
1)  Show types, sizes and length of conduit on plans.
2)  Show locations for the placement of conduits on plans.
3)  This is a plans quantity measurement item.
4)  Use the following Statewide Standard Details Sheets for the placement of conduit:

ED (1)

Electrical Details - Conduit

ED (2)

Electrical Details - Conductors

ED (3)

Electrical Details - Ground Boxes

 

PAYMENT DESCRIPTION UNITS
1) "CONDT (Type Specified) (Size Specified)" LF

REFERENCE ITEMS
(400), (445), (476), (622)

Go to Top

620 - ELECTRICAL CONDUCTORS

SPECIFICATION REQUIREMENTS
1)  Show the size, type and length of electrical conductors on plans.
2)  Show splice locations on the plans.
3)  This is a plans quantity measurement item.
4)  Conductors used in connecting the components of electrical services will be paid for under Item 628, “Electrical Services.”  Conductors inside roadway illumination assemblies will be paid for under Item 610, “Roadway Illumination Assemblies.”
5)  Use the following Statewide Standard Details Sheets for the placement of electrical conductors:

ED (1)

Electrical Details - Conduit

ED (2)

Electrical Details - Conductors

PAYMENT DESCRIPTION UNITS
1) "ELEC CONDR (Size Specified) (Type Specified)" LF

REFERENCE ITEMS
None

Go to Top

621 - TRAY CABLE

SPECIFICATION REQUIREMENTS
1)  The size, type and length of the tray cable must be shown on plans.
2)  Show splice locations on the plans.
3)  This is a plans quantity measurement item.
4)  Tray cable will be added to the Electrical Detail sheets.

PAYMENT DESCRIPTION UNITS
1) "TRAY CABLE (Type Specified) (Size Specified)" LF

REFERENCE ITEMS
None

Go to Top

622 - DUCT CABLE

SPECIFICATION REQUIREMENTS
1)  The types, sizes and length of duct cable must be shown on plans.
2)  If the duct cable is placed by open trench methods, the location and depth of trench must be shown on plans.
3)  This is a plans quantity measurement item.
4)  The following Statewide Standard Details Sheets are required for the placement of duct cable:

ED (1)

Electrical Details - Conduit

ED (2)

Electrical Details - Conductors

ED (3) Electrical Details - Ground Boxes

ED (10)

Electrical Details - Duct Cable

PAYMENT DESCRIPTION UNITS
1) "DUCT CABLE (Size Specified) (Type Specified)" LF

REFERENCE ITEMS
(400), (620)

Go to Top

624 - GROUND BOXES

SPECIFICATION REQUIREMENTS
1) Show the types and sizes of the ground boxes complete with lids on plans.
2) Show locations of the ground boxes on plans.
3)  A concrete apron can be provided when shown on plans.
4) Use the following Statewide Standard Details Sheets for design details and installation of ground boxes:

ED (1) Electrical Details - Conduit

ED (2)

Electrical Details - Conductors

ED (3)

Electrical Details - Ground Boxes

PAYMENT DESCRIPTION UNITS
1) "GROUND BOXES (Type Specified) (Size Specified)" EA

REFERENCE ITEMS
(421), (440)

Go to Top

625 - ZINC-COATED STEEL WIRE STRAND

SPECIFICATION REQUIREMENTS
1)  Show the diameter sizes of the zinc-coated steel wire strands on plans.
2)  Show the installation of the zinc-coated steel wire strands on plans.

PAYMENT AND MEASUREMENT
Subsidiary to the various bid items in the contract.
* If Special Provision 625---001 is used, the following payment and measurement apply:

PAYMENT DESCRIPTION UNITS
*"ZNC CTD STL WIRE STRND (Size Specified)" LF

REFERENCE ITEMS
None

Go to Top

627 - TREATED TIMBER POLES

SPECIFICATION REQUIREMENTS
1)  Show the types and lengths of the treated timber poles on plans.
2)  Show the locations of the treated timber poles on plans.

PAYMENT AND MEASUREMENT
Subsidiary to the various bid items in the contract.

REFERENCE ITEMS
None

Go to Top

628 - ELECTRICAL SERVICES

SPECIFICATION REQUIREMENTS
1)  Show the types and locations of electrical services installed or removed on plans.
2)  Use the following Statewide Standard Details Sheets for the installation of electrical services:

ED (1) Electrical Details - Conduit
ED (2) Electrical Details - Conductors
ED (3) Electrical Details - Ground Boxes
ED (4) Electrical Details - Service Notes & Type T Schematic
ED (5) Electrical Details - Service Notes & Type A, C, D Schem.

3)  The following Statewide Standard Details Sheets are available for the installation of electrical services of the types shown on the plans:

ED (6)

Electrical Details - SF & SP Service Support

ED (7)

Electrical Details – Traffic Signal Service

ED (8)

Electrical Details – Electrical Services

ED (9)

Electrical Details – Electrical Services

ED (12)

Electrical Details – Electrical Services

4)  Any materials removed and designated for reuse or retention by the state must be shown on plans.

PAYMENT DESCRIPTION UNITS
1) "ELC SRV (Type Specified)" EA
2) "REMOVE ELECTRICAL SERVICES" EA

REFERENCE ITEMS
(441), (445), (449), (618), (620), (627), (656)

Go to Top

634 - PLYWOOD SIGNS

SPECIFICATION REQUIREMENTS
1)  Show the location and details of the fabrication and erection of the plywood signs must be shown on plans.
2)  Show the types and sizes of the plywood signs must be shown on plans.
3)  Show the colors and types of sign faces on plans.
4)  Show sign messages (sizes, types and colors) on plans.
5)  Show sign blanks sizes and shapes on plans.
6)  Show the locations of the existing roadside signs to be replaced or refurbished on plans.
7)  Refurbishing the roadside signs can include new messages and mounting hardware when shown on plans.
8)  Show new reflectorized legends and/or supplemental signs on plans.
9)  Show any sign components that are removed and are to be reused on plans.
10) Show any sign components that are removed and are to be salvaged and become property of the state on plans.
11) This is a plans quantity measurement item. 

PAYMENT DESCRIPTION UNITS
1) "PLYWOOD SIGNS" SF
2) "REPLACE EXISTING PLYWOOD SIGNS" SF
3) "REFURBISH PLYWOOD SIGN" EA

REFERENCE ITEMS
(636), (643)

Go to Top

636 - ALUMINUM SIGNS

SPECIFICATION REQUIREMENTS
1)  Show the location and details of the fabrication and erection of the aluminum and fiberglass signs on plans.
2)  Show the types and sizes of the aluminum and fiberglass signs on plans.
3)  When specifying fiberglass signs, submit a sole source justification letter explaining why fiberglass signs are needed. (ex. theft problem with aluminum signs).
4)  Show the colors and types of sign faces on plans.
5)  Show the sizes, types and colors of sign messages on plans.
6)  Show on the plans whenever parent sign face attachments (route markers, yellow exit panels, etc.) are to be Type A aluminum signs rather than direct applied sheeting.
7)  Show the sizes, types and shapes of sign blanks on plans.
8)  Show the locations of the existing roadside signs to be replaced or refurbished on plans.
9)  Refurbishing the roadside signs can include new messages and mounting hardware when shown on plans.
10)  Show new reflectorized legends and/or supplemental signs on plans.
11)  Show any sign components that are removed and are to be reused on plans.
12) Show any sign components that are removed and are to be salvaged and become property of the state on plans.
13)  This is a plans quantity measurement item. 

PAYMENT DESCRIPTION UNITS
1) "SIGNS (Type Specified)" SF
2) "ALUMINUM SIGNS (Type Specified)" SF
3) "FIBERGLASS SIGNS (Type Specified)" SF
4) "REPLACE EXISTING ALUMINUM SIGNS (Type Specified)" SF
5) "REPLACE EXISTING FIBERGLASS SIGNS (Type Specified)" SF
6) "REFURBISH ALUMINUM SIGNS (Type Specified)" EA
7) "REFURBISH FIBERGLASS SIGNS (Type Specified)" EA

REFERENCE ITEMS
(643)