Monthly Local Let Maintenance Report For Amarillo District As Of Feb 14, 2022 Page 6 Of 7

Last Update: Tuesday, February 15, 2022
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGRAY
HighwaySH0070
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6382-58-001
Proj IDMMC - 638258001
Work TypeWINTER WEATHER MATERIAL
 
0.01052325.000.000.0
Work Order00-00-00
Work Began10-27-21
Work Completed
Time Computed10-25-21
Contract Working Days120
Addl Days Granted0
Working Days Charged97
Percent Time Used80
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6382-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09210468
Totals52325.000.000.000.0

CountyARMSTRONG
HighwayUS0287
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6382-59-001
Proj IDMMC - 638259001
Work TypeSEAL COAT
 
0.01024565.500.000.0
Work Order00-00-00
Work Began10-25-21
Work Completed
Time Computed08-10-21
Contract Working Days120
Addl Days Granted120
Working Days Charged99
Percent Time Used41
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6382-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07210448
Totals24565.500.000.000.0

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS SEE PLAN SHEETS
ToVARIOUS LOCATIONS SEE PLAN SHEETS
CSJ6385-06-001
Proj IDRMC - 638506001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010257535.00106000.0041.1
Work Order00-00-00
Work Began09-27-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged127
Percent Time Used34
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6385-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07210401
Totals257535.0011175.00106000.0041.1

CountyRANDALL
HighwayUS0060
FromCANYON MAINTENANCE OFFICE
ToCANYON MAINTENANCE OFFICE
CSJ6388-38-001
Proj IDSUP - 638838001
Work TypeSTATE USE CONTRACT
 
0.01010650.145229.7049.1
Work Order00-00-00
Work Began08-01-21
Work Completed
Time Computed08-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6388-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07210420
Totals10650.14762.975229.7049.1

CountyGRAY
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6388-45-001
Proj IDRMC - 638845001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010127933.0653854.0242.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-18-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged106
Percent Time Used29
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6388-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09210401
Totals127933.0626927.0153854.0242.0

CountyRANDALL
HighwayIH0027
FromAMARILLO DISTRICT HQ
ToAMARILLO DISTRICT HQ
CSJ6389-27-001
Proj IDSUP - 638927001
Work TypeJANITORIAL MAINTENANCE
 
0.01078817.4033358.7942.3
Work Order00-00-00
Work Began09-01-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6389-27-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08210420
Totals78817.406049.9133358.7942.3

CountyPOTTER
HighwaySL0335
FromPOTTER COUNTY MAINTENANCE OFFICE
ToPOTTER COUNTY MAINTENANCE OFFICE
CSJ6390-19-001
Proj IDSUP - 639019001
Work TypeJANITORIAL MAINTENANCE
 
0.0108961.723734.0541.6
Work Order00-00-00
Work Began09-01-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6390-19-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08210421
Totals8961.72746.813734.0541.6

CountyRANDALL
HighwayFM1541
FromAMARILLO AE/ EWAY MAINTENANCE OFFICE
ToAMARILLO AE/EWAY MAINTENANCE OFFICE
CSJ6390-20-001
Proj IDSUP - 639020001
Work TypeJANITORIAL MAINTENANCE
 
0.01020360.747218.2035.4
Work Order00-00-00
Work Began09-01-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6390-20-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08210422
Totals20360.741443.647218.2035.4

CountyMOORE
HighwayFM2203
FromDUMAS AE AND MAINTENANCE OFFICE
ToDUMAS AE AND MAINTENANCE OFFICE
CSJ6390-21-001
Proj IDSUP - 639021001
Work TypeJANITORIAL MAINTENANCE
 
0.01015341.886392.4541.6
Work Order00-00-00
Work Began09-01-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6390-21-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08210423
Totals15341.881278.496392.4541.6

CountyMOORE
HighwayUS0087
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6391-09-001
Proj IDRMC - 639109001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010349351.0038141.0010.9
Work Order00-00-00
Work Began11-17-21
Work Completed
Time Computed11-22-21
Contract Working Days365
Addl Days Granted0
Working Days Charged76
Percent Time Used20
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6391-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10210401
Totals349351.009080.0038141.0010.9

CountyCARSON
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6392-02-001
Proj IDSUP - 639202001
Work TypePICNIC AREA MAINTENANCE
 
0.010156689.1234990.7822.3
Work Order00-00-00
Work Began10-01-21
Work Completed
Time Computed10-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
WORKQUEST
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6392-02-001
FRESH START OF MONROE INC. (0.00)
Contract #09210420
Totals156689.125653.9034990.7822.3

CountyGRAY
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6393-16-001
Proj IDRMC - 639316001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010369250.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6393-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11210401
Totals369250.000.000.000.0

CountyGRAY
HighwayUS0060
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6393-31-001
Proj IDRMC - 639331001
Work TypeTREE REMOVAL
 
0.010232615.0073430.0031.5
Work Order00-00-00
Work Began01-24-22
Work Completed
Time Computed12-20-21
Contract Working Days60
Addl Days Granted0
Working Days Charged3
Percent Time Used5
Contractor(s)
GV LANDSCAPE AND CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6393-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11210403
Totals232615.0073430.0073430.0031.5

CountyDEAF SMITH
HighwayUS0385
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6393-33-001
Proj IDRMC - 639333001
Work TypeTREE REMOVAL
 
0.01056045.0065010.0099.9
Work Order00-00-00
Work Began01-11-22
Work Completed
Time Computed12-27-21
Contract Working Days40
Addl Days Granted0
Working Days Charged9
Percent Time Used22
Contractor(s)
FOWLER CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6393-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11210402
Totals56045.0065010.0065010.0099.9

CountyPOTTER
HighwayIH0040
FromAMARILLO DISTRICT PAVEMENT MARKINGS
ToAMARILLO DISTRICT PAVEMENT MARKINGS
CSJ6395-18-001
Proj IDMMC - 639518001
Work TypePAVEMENT MARKINGS
 
0.010152815.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6395-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01220443
Totals152815.000.000.000.0

CountyARMSTRONG
HighwayUS0287
FromAMARILLO AREA MAINT SECT. SEAL COAT AGGR
ToAMARILLO AREA MAINT SECT. SEAL COAT AGGR
CSJ6395-90-001
Proj IDMMC - 639590001
Work TypeSEAL COAT
 
0.010328343.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6395-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220440
Totals328343.500.000.000.0

CountyDALLAM
HighwayUS0054
FromDUMAS AREA MAINT SECT. SEAL COAT AGGR
ToDUMAS AREA MAINT SECT. SEAL COAT AGGR
CSJ6395-91-001
Proj IDMMC - 639591001
Work TypeSEAL COAT
 
0.010333845.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6395-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220441
Totals333845.450.000.000.0

CountyCARSON
HighwayIH0040
FromPAMPA AREA MAINT SECT. SEAL COAT AGGR
ToPAMPA AREA MAINT SECT. SEAL COAT AGGR
CSJ6395-92-001
Proj IDMMC - 639592001
Work TypeSEAL COAT
 
0.010332334.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6395-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220442
Totals332334.000.000.000.0

CountyDEAF SMITH
HighwayUS0385
FromAMARILLO AREA MAINT SECTIONS HMAC PU/DEL
ToAMARILLO AREA MAINT SECTIONS HMAC PU/DEL
CSJ6395-93-001
Proj IDMMC - 639593001
Work TypeHOT MIX
 
0.010281390.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6395-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220443
Totals281390.000.000.000.0

CountyMOORE
HighwayUS0087
FromDUMAS AREA MAINTENANCE HMAC PU/DEL
ToDUMAS AREA MAINTENANCE HMAC PU/DEL
CSJ6396-04-001
Proj IDMMC - 639604001
Work TypeHOT MIX
 
0.010310800.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220444
Totals310800.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7