Monthly State Let Construction Report For El Paso District As Of Feb 14, 2020 Page 1 Of 3

Last Update: Friday, February 14, 2020
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwaySH 20
FromSUNLAND PARK DRIVE
ToBALTIMORE DRIVE
CSJ0001-02-055
Proj IDNH 2019(781)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.02911138603.300.000.0
CountyEL PASO
HighwaySH 20
FromSUNLAND PARK DRIVE
ToBALTIMORE DRIVE
CSJ0001-02-065
Proj IDROW 1-2-65
Work TypeRIGHT OF WAY
 
4.029318645.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-30-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0001-02-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11193207
Totals11457248.300.000.000.0

CountyEL PASO
HighwaySH 20
From1.466 MI N OF IH 10
To1.231 MI N OF IH 10
CSJ0001-02-060
Proj IDSTP 2019(705)HES
Work TypeSFT
 
0.235250085.800.000.0
CountyEL PASO
HighwaySH 20
FromAT MESA HILLS DRIVE
To.
CSJ0001-02-061
Proj IDSTP 2019(705)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200409912.450.000.0
CountyEL PASO
HighwaySH 20
FromAT ARGONAUT DR
To.
CSJ0001-02-062
Proj IDSTP 2019(705)HES
Work TypeSFT
 
0.200388952.450.000.0
CountyEL PASO
HighwaySH 20
From1.231 MI N OF IH 10
To1.085 MI N OF IH 10
CSJ0001-03-056
Proj IDSTP 2019(705)HES
Work TypeSFT
 
0.14611090.000.000.0
Work Order09-18-19
Work Began00-00-00
Work Completed
Time Computed12-17-19
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0001-02-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193236
Totals1060040.700.000.000.0

CountyEL PASO
HighwaySH 20 ETC
FromAT MISSOURI AVE
To.
CSJ0001-03-058
Proj IDSTP 2019(963)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.2643024946.560.000.0
Work Order06-13-19
Work Began00-00-00
Work Completed
Time Computed07-13-19
Contract Working Days280
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0001-03-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193017
Totals3024946.560.000.000.0

CountyEL PASO
HighwaySH 20
FromPADRES
ToLOOP 375 (AMERICAS AVENUE)
CSJ0002-01-055
Proj IDNH 1602(497)
Work TypeRECON RDWY, INT IMPRVMNTS & REHAB
 
1.8956620004.356826099.2999.9
CountyEL PASO
HighwaySH 20
FromPADRES
ToLOOP 375 (AMERICAS AVENUE)
CSJ0002-01-094
Proj IDROW 2-1-94
Work TypeROW ACQUISITION
 
1.562473499.00481179.2999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began07-17-17
Work Completed
Time Computed07-14-17
Contract Working Days385
Addl Days Granted46
Working Days Charged431
Percent Time Used100
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-055
ALLEN CONCRETE, INC. (8.22)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.12)
LOS FIERRO CONSTRUCTION (6.16)
TRAFFIC BARRICADE SERVICE, INC. (1.69)
TRI STATE ELECTRIC, LTD. (25.65)
FALC ENTERPRISES, LLC (0.26)
DLC CONSTRUCTION (0.18)
SYNERGY PROJECT CONTRACTORS, INC. (0.26)
ZTEX CONSTRUCTION, INC. (0.03)
Contract #05173017
Totals7093503.350.007307278.5899.9

CountyHUDSPETH ETC
HighwayIH 10 ETC
From2.18 MI E OF FM 34
ToLASCA ROAD
CSJ0002-06-054
Proj IDNH 2020(577)
Work TypeSEAL COAT
 
45.0493670432.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-14-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-06-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12193020
Totals3670432.400.000.000.0

CountyHUDSPETH
HighwayIH 10
From0.06 MI E OF FM 34
To0.02 MI W OF LASCA RD
CSJ0002-06-055
Proj IDSTP 2019(964)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
11.198915831.250.000.0
CountyHUDSPETH
HighwayIH 10
From0.04 MI E OF LASCA RD
To5.11 MI W OF RM 1111
CSJ0002-07-050
Proj IDSTP 2019(964)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.900232960.000.000.0
CountyEL PASO
HighwayIH 10
From0.48 MI E OF FM 793
To2.05 MI E OF FM 793
CSJ2121-05-047
Proj IDSTP 2019(964)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.57083650.000.000.0
Work Order06-13-19
Work Began00-00-00
Work Completed
Time Computed07-13-19
Contract Working Days80
Addl Days Granted0
Working Days Charged1
Percent Time Used1
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-06-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193225
Totals1232441.250.000.000.0

CountyHUDSPETH
HighwayIH 10
From1.70 MI W OF RM 1111
To0.01 MI E OF RM 1111
CSJ0002-07-049
Proj IDBR 1802(572)
Work TypeREPLACE BRIDGES AND APPROACHES
 
2.2705416393.255575935.2199.9
CountyHUDSPETH
HighwayRM 1111
From0.03 MI S OF IH 10
To0.03 MI N OF IH 10
CSJ1282-03-009
Proj IDC 1282-3-9
Work TypeRECONSTRUCT ROADWAY
 
0.067277483.3578650.0028.3
Work Order12-04-18
Work Began02-01-19
Work Completed
Time Computed01-07-19
Contract Working Days238
Addl Days Granted14
Working Days Charged221
Percent Time Used87
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-07-049
A BROTHERS MILLING, LLC (0.67)
V.C. HUFF, L.L.C. (3.47)
PENHALL COMPANY (AUSTIN) (0.21)
HARDY HOLE DRILLING (4.74)
X GOMEZ LOGISTICS LLC (2.83)
SOUTH TEXAS PAINTING COMPANY (1.04)
PMI PAVEMENT MARKING, LLC (2.02)
NATIONWIDE REBAR INC. (3.07)
CONCRETE PUMPING, INC. DBA CPI (0.18)
Contract #11183227
Totals5693876.60323835.215654585.2198.7

CountyCULBERSON
HighwayIH 10
From8.5 MI E OF VAN HORN
ToEVERGREEN RD
CSJ0003-01-055
Proj IDSTP 2019(990)TAPS
Work TypeSAFETY REST AREA
 
3.91229044962.110.000.0
CountyCULBERSON
HighwayIH 10
From8.5 MI E OF VAN HORN
ToEVERGREEN RD
CSJ0003-01-056
Proj IDNH 1902(067)
Work TypeRIGHT OF WAY
 
3.912283266.800.000.0
Work Order09-18-19
Work Began00-00-00
Work Completed
Time Computed11-17-19
Contract Working Days440
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0003-01-055
L & J CONSTRUCTION, INC. (0.16)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.57)
BOWMAN ENGINEERING & CONSULTING, INC. (0.67)
PAVEMENT MARKINGS INC. (0.17)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.20)
ACCENT LANDSCAPE CONTRACTORS, INC. (2.18)
A BROTHERS MILLING, LLC (0.04)
HENRY TRUJILLO, INC. (1.25)
Contract #08193203
Totals29328228.910.000.000.0

CountyPRESIDIO
HighwayUS 67
FromPUERTO RICO ST
ToINTERNATIONAL DEMARCATION LINE
CSJ0104-10-006
Proj IDNH 1702(686)
Work TypeNEW TWO-LANE TWIN BRIDGE STRUCTURE
 
0.6596854362.505936324.0486.9
Work Order09-25-17
Work Began05-21-18
Work Completed
Time Computed10-25-17
Contract Working Days260
Addl Days Granted92
Working Days Charged375
Percent Time Used106
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0104-10-006
PRIMATE CONSTRUCTION, INC. (0.19)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.73)
CONTRACTORS SERVICE COMPANY (0.85)
MICA CORPORATION (6.41)
LANCO TURF & SEEDING, INC. (0.20)
BOWMAN ENGINEERING & CONSULTING, INC. (0.25)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.88)
BOWMAN ENGINEERING & CONSULTING, INC. (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.47)
HAWK CONSTRUCTION (0.93)
Contract #08173207
Totals6854362.5083134.925936324.0486.9

CountyEL PASO
HighwayUS 54
FromHONDO PASS DRIVE
ToSL 375
CSJ0167-01-095
Proj IDSTP 1702(687)MM
Work TypeWIDEN BY ADDING TWO INSIDE LANES
 
1.99213995966.3714937545.5699.9
CountyEL PASO
HighwayUS 54
FromHONDO PASS DRIVE
ToSL 375
CSJ0167-01-098
Proj IDSTP 1702(687)MM
Work TypeOPERATIONAL IMPROVEMENTS
 
1.99219680182.5519388209.4398.5
Work Order09-12-17
Work Began11-09-17
Work Completed
Time Computed10-12-17
Contract Working Days460
Addl Days Granted128
Working Days Charged578
Percent Time Used98
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-095
HARDY HOLE DRILLING (1.38)
TRI STATE ELECTRIC, LTD. (33.92)
A BROTHERS MILLING, LLC (0.15)
ANTIGO CONSTRUCTION, INC. (0.19)
CONCRETE PUMPING, INC. DBA CPI (0.12)
EARTH REINFORCEMENTS LLC (2.53)
PENHALL COMPANY (0.01)
SCOTT DERR PAINTING CO, LLC (0.19)
X GOMEZ LOGISTICS LLC (1.46)
SATARAIN CONSTRUCTION, INC. (6.36)
NATIONWIDE REBAR, INC. (4.26)
PMI PAVEMENT MARKING, INC. (0.63)
HARDY HOLE DRILLING (1.18)
A BROTHERS MILLING, LLC (0.01)
GREENE CRANE & RIGGING, LLC (0.21)
BORDER DRILLING LLC (0.13)
CRANE SERVICES, INC. (0.03)
CONCRETE PUMPING, INC. DBA CPI (0.03)
THORCON SHOTCRETE AND SHORING LLC (0.66)
Contract #08173002
Totals33676148.92283346.0734325754.9999.9

CountyEL PASO
HighwayUS 54
FromLP 375 (CESAR CHAVEZ BORDER HWY)
ToYANDELL DR
CSJ0167-01-113
Proj IDNH 2019(166)
Work TypeINTERCHANGE IMPROVEMENTS
 
1.18189861277.4036478826.0340.5
CountyEL PASO
HighwayIH 110
FromUS 62
ToI 10
CSJ0167-01-118
Proj IDNH 2019(167)
Work TypeINSTALLATION OF SIGNS
 
0.900357297.000.000.0
CountyEL PASO
HighwayIH 110
FromUS 62
ToI 10
CSJ0167-01-119
Proj IDROW 167-1-119
Work TypeACQUISITION
 
0.900948024.00196783.0020.7
Work Order01-15-19
Work Began02-19-19
Work Completed
Time Computed02-02-19
Contract Working Days722
Addl Days Granted0
Working Days Charged275
Percent Time Used38
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-113
TRI STATE ELECTRIC, LTD. (17.11)
APACHE BARRICADE & SIGN (1.12)
NATIONWIDE REBAR, INC. (0.87)
HARDY HOLE DRILLING (8.97)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.74)
F A L C ENTERPRISES, LLC. (1.67)
THE GROUND LEVEL COMPANY (1.60)
BORDER DRILLING LLC (0.08)
DUSTROL, INC. (0.01)
ALLIED PAVING CO. (2.02)
ADVANCED CONCRETE SAWING & SEALING, LLC (0.09)
SCOTT DERR PAINTING CO, LLC (0.25)
HYDRATECH FIELD SERVICES, LLC (0.06)
HERNANDEZ CONCRETE PUMPING, INC. (0.57)
CRANE SERVICES, INC. (0.61)
SOUTHEAST GRINDING & GROOVING, LLC (0.07)
CHOCTAW ERECTORS, INC. (0.21)
Contract #11183001
Totals91166598.402031482.6336675609.0340.2

CountyEL PASO
HighwayUS 54
FromMCCOMBS
ToTEXAS/NEW MEXICO STATE LINE
CSJ0167-01-128
Proj IDNH 2020(602)
Work TypeRESTORATION
 
7012063.670.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02203005
Totals7012063.670.000.000.0

CountyEL PASO
HighwayBU 54-A
FromMESQUITE HILLS DR
ToNEW MEXICO STATE LINE
CSJ0167-02-051
Proj IDC 167-2-51
Work TypeOVERLAY
 
5.4361723480.00942008.6454.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-12-18
Work Began03-18-19
Work Completed
Time Computed10-12-18
Contract Working Days52
Addl Days Granted0
Working Days Charged51
Percent Time Used98
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0167-02-051
DUSTROL, INC. (2.67)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.15)
PMI PAVEMENT MARKING, LLC (5.55)
Contract #07183030
Totals1723480.000.00942008.6454.6

CountyEL PASO
HighwayBU 54-A
FromSANDERS
ToS ANGORA LOOP
CSJ0167-02-063
Proj IDNH 2020(444)
Work TypeREHABILITATION OF EXISTING ROAD
 
2497616.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-14-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0167-02-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12193215
Totals2497616.540.000.000.0

CountyCULBERSON ETC
HighwayUS 62 ETC
From9.2 MI E OF SH 54
To3.9 MI W OF RM 652
CSJ0233-01-044
Proj IDSTP 2017(953)HES
Work TypeMODERNIZE BRIDGE RAIL/APR GUARDRAIL
 
49.2123783684.493666505.6397.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-17
Work Began07-17-17
Work Completed
Time Computed06-06-17
Contract Working Days200
Addl Days Granted0
Working Days Charged240
Percent Time Used120
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0233-01-044
DOUBLE A CONTRACTING, L.P. (1.00)
Contract #04173211
Totals3783684.490.003666505.6397.9

CountyEL PASO
HighwayUS 62
FromGLOBAL REACH DR
ToFM 659 (ZARAGOZA RD)
CSJ0374-02-097
Proj IDNH 2019(063)
Work TypeBUILD FRONTAGE ROADS AND MAINLANES
 
7.833138160814.0522779924.6216.4
CountyEL PASO
HighwayUS 62
FromGLOBAL REACH DR
ToFM 659 (ZARAGOZA RD)
CSJ0374-02-103
Proj IDROW 374-2-103
Work TypeROW ACQUISITION
 
4.5605593434.001384786.0724.7
CountyEL PASO
HighwayUS 62
FromAT TIERRA ESTE
To.
CSJ0374-02-111
Proj IDSTP 2019(064)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.200453662.600.000.0
Work Order12-17-18
Work Began04-22-19
Work Completed
Time Computed03-17-19
Contract Working Days811
Addl Days Granted24
Working Days Charged219
Percent Time Used26
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-097
TRAFFIC BARRICADE SERVICE, INC. (0.23)
SANCHEZ CONSTRUCTION & LANDSCAPING (0.50)
ZTEX CONSTRUCTION, INC. (6.67)
A BROTHERS MILLING, LLC (0.19)
HAWK CONSTRUCTION (4.50)
HARDY HOLE DRILLING (4.83)
BORDER DEMOLITION AND ENVIRONMENTAL, INC. (0.24)
PAVEMENT MARKINGS INC. (0.69)
TRI STATE ELECTRIC, LTD. (11.55)
DAMCON (1.85)
HDW CONSTRUCTION & DRILLING, LLC. (0.69)
F A L C ENTERPRISES, LLC. (0.45)
CRANE SERVICES, INC. (0.30)
HARDY HOLE DRILLING (0.39)
Contract #10183227
Totals144207910.651442858.0424164710.6916.7

CountyEL PASO
HighwayUS 62
FromGERONIMO DR
ToSIOUX DR
CSJ0374-02-107
Proj IDCM 2019(991)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.6941033028.05975164.0394.3
Work Order07-16-19
Work Began09-03-19
Work Completed
Time Computed08-15-19
Contract Working Days100
Addl Days Granted0
Working Days Charged98
Percent Time Used98
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-107
F A L C ENTERPRISES, LLC. (1.14)
TRI STATE ELECTRIC, LTD. (37.08)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.19)
Contract #06193241
Totals1033028.05271549.95975164.0394.3

CountyCULBERSON
HighwayUS 62
From4.79 MI SW OF SH54
To3.59 MI SW OF SH54
CSJ0374-08-021
Proj IDC 374-8-21
Work TypeCOUNTERMEASURE FOR BRIDGE SCOUR
 
1.2001434496.001387492.5096.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-18
Work Began10-18-18
Work Completed
Time Computed10-18-18
Contract Working Days100
Addl Days Granted0
Working Days Charged90
Percent Time Used90
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0374-08-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183030
Totals1434496.000.001387492.5096.7

CountyJEFF DAVIS
HighwaySH 118
From15.219 MI N OF SH 17
ToSH 17
CSJ0415-01-025
Proj IDSTP 2018(878)HES
Work TypeIMPROVE GUARDRAIL TO STANDARDS
 
15.219340160.00341330.0099.9
Work Order06-18-18
Work Began11-12-18
Work Completed
Time Computed07-18-18
Contract Working Days60
Addl Days Granted0
Working Days Charged61
Percent Time Used101
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0415-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183227
Totals340160.000.00341330.0099.9

CountyEL PASO
HighwayFM 3255
FromNEW MEXICO STATE LINE
To0.208 MI N OF US 54
CSJ0665-01-009
Proj IDNH 2020(424)
Work TypeOVERLAY
 
5.2073220964.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLIED PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0665-01-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01203202
Totals3220964.880.000.000.0

page 1 | page 2 | page 3