Monthly State Let Construction Report For El Paso District As Of Aug 23, 2019 Page 1 Of 2

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwaySH 20
From1.466 MI N OF IH 10
To1.231 MI N OF IH 10
CSJ0001-02-060
Proj IDSTP 2019(705)HES
Work TypeSFT
 
0.235250085.800.000.0
CountyEL PASO
HighwaySH 20
FromAT MESA HILLS DRIVE
To.
CSJ0001-02-061
Proj IDSTP 2019(705)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200409912.450.000.0
CountyEL PASO
HighwaySH 20
FromAT ARGONAUT DR
To.
CSJ0001-02-062
Proj IDSTP 2019(705)HES
Work TypeSFT
 
0.200388952.450.000.0
CountyEL PASO
HighwaySH 20
From1.231 MI N OF IH 10
To1.085 MI N OF IH 10
CSJ0001-03-056
Proj IDSTP 2019(705)HES
Work TypeSFT
 
0.14611090.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0001-02-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193236
Totals1060040.700.000.000.0

CountyEL PASO
HighwaySH 20 ETC
FromAT MISSOURI AVE
To.
CSJ0001-03-058
Proj IDSTP 2019(963)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.2643024946.560.000.0
Work Order06-13-19
Work Began00-00-00
Work Completed
Time Computed07-13-19
Contract Working Days280
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0001-03-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193017
Totals3024946.560.000.000.0

CountyEL PASO
HighwaySH 20
FromPADRES
ToLOOP 375 (AMERICAS AVENUE)
CSJ0002-01-055
Proj IDNH 1602(497)
Work TypeRECON RDWY, INT IMPRVMNTS & REHAB
 
1.8956620004.356765248.5999.9
CountyEL PASO
HighwaySH 20
FromPADRES
ToLOOP 375 (AMERICAS AVENUE)
CSJ0002-01-094
Proj IDROW 2-1-94
Work TypeROW ACQUISITION
 
1.562473499.00481179.2999.9
Work Order06-14-17
Work Began07-17-17
Work Completed
Time Computed07-14-17
Contract Working Days385
Addl Days Granted46
Working Days Charged431
Percent Time Used100
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-055
ALLEN CONCRETE, INC. (8.22)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.12)
LOS FIERRO CONSTRUCTION (6.16)
TRAFFIC BARRICADE SERVICE, INC. (1.69)
TRI STATE ELECTRIC, LTD. (25.65)
FALC ENTERPRISES, LLC (0.26)
DLC CONSTRUCTION (0.18)
SYNERGY PROJECT CONTRACTORS, INC. (0.26)
ZTEX CONSTRUCTION, INC. (0.03)
Contract #05173017
Totals7093503.3510360.207246427.8899.9

CountyEL PASO
HighwaySH 20
From0.142 MI S OF FM 76
To0.242 MI S OF FM 76
CSJ0002-01-095
Proj IDSTP 1802(571)
Work TypePEDESTRIAN IMPROVEMENTS
 
0.100328455.00258916.3090.8
CountyEL PASO
HighwaySH 20
From0.142 MI S OF FM 76
To0.242 MI S OF FM 76
CSJ0002-01-097
Proj IDROW 2-1-97
Work TypeACQUISITION AND UTILITY ADJUSTMENTS
 
0.10021454.0021654.0099.9
Work Order10-25-18
Work Began11-26-18
Work Completed
Time Computed11-26-18
Contract Working Days55
Addl Days Granted12
Working Days Charged134
Percent Time Used200
Contractor(s)
MARIL ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-095
DLC CONSTRUCTION (5.15)
Contract #08183236
Totals349909.000.00280570.3091.4

CountyHUDSPETH
HighwayIH 10
From0.06 MI E OF FM 34
To0.02 MI W OF LASCA RD
CSJ0002-06-055
Proj IDSTP 2019(964)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
11.198915831.250.000.0
CountyHUDSPETH
HighwayIH 10
From0.04 MI E OF LASCA RD
To5.11 MI W OF RM 1111
CSJ0002-07-050
Proj IDSTP 2019(964)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.900232960.000.000.0
CountyEL PASO
HighwayIH 10
From0.48 MI E OF FM 793
To2.05 MI E OF FM 793
CSJ2121-05-047
Proj IDSTP 2019(964)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.57083650.000.000.0
Work Order06-13-19
Work Began00-00-00
Work Completed
Time Computed07-13-19
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-06-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193225
Totals1232441.250.000.000.0

CountyHUDSPETH
HighwayIH 10
From1.70 MI W OF RM 1111
To0.01 MI E OF RM 1111
CSJ0002-07-049
Proj IDBR 1802(572)
Work TypeREPLACE BRIDGES AND APPROACHES
 
2.2705416393.253263121.5560.0
CountyHUDSPETH
HighwayRM 1111
From0.03 MI S OF IH 10
To0.03 MI N OF IH 10
CSJ1282-03-009
Proj IDC 1282-3-9
Work TypeRECONSTRUCT ROADWAY
 
0.067277483.3518629.006.7
Work Order12-04-18
Work Began02-01-19
Work Completed
Time Computed01-07-19
Contract Working Days238
Addl Days Granted14
Working Days Charged80
Percent Time Used31
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-07-049
A BROTHERS MILLING, LLC (0.67)
V.C. HUFF, L.L.C. (3.47)
PENHALL COMPANY (AUSTIN) (0.21)
HARDY HOLE DRILLING (4.74)
X GOMEZ LOGISTICS LLC (2.83)
SOUTH TEXAS PAINTING COMPANY (1.04)
PMI PAVEMENT MARKING, LLC (2.02)
NATIONWIDE REBAR INC. (3.07)
CONCRETE PUMPING, INC. DBA CPI (0.18)
Contract #11183227
Totals5693876.60526725.323281750.5557.4

CountyCULBERSON
HighwayIH 10
From8.5 MI E OF VAN HORN
ToEVERGREEN RD
CSJ0003-01-055
Proj IDSTP 2019(990)TAPS
Work TypeSAFETY REST AREA
 
3.91229044962.110.000.0
CountyCULBERSON
HighwayIH 10
From8.5 MI E OF VAN HORN
ToEVERGREEN RD
CSJ0003-01-056
Proj IDNH 1902(067)
Work TypeRIGHT OF WAY
 
3.912283266.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days440
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0003-01-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193203
Totals29328228.910.000.000.0

CountyPRESIDIO
HighwayUS 67
FromPUERTO RICO ST
ToINTERNATIONAL DEMARCATION LINE
CSJ0104-10-006
Proj IDNH 1702(686)
Work TypeNEW TWO-LANE TWIN BRIDGE STRUCTURE
 
0.6596854362.505110492.7274.5
Work Order09-25-17
Work Began05-21-18
Work Completed
Time Computed10-25-17
Contract Working Days260
Addl Days Granted35
Working Days Charged268
Percent Time Used90
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0104-10-006
PRIMATE CONSTRUCTION, INC. (0.19)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.73)
CONTRACTORS SERVICE COMPANY (0.85)
MICA CORPORATION (6.41)
LANCO TURF & SEEDING, INC. (0.20)
BOWMAN ENGINEERING & CONSULTING, INC. (0.25)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.88)
BOWMAN ENGINEERING & CONSULTING, INC. (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.47)
Contract #08173207
Totals6854362.5044835.565110492.7274.5

CountyEL PASO
HighwayUS 54
FromHONDO PASS DRIVE
ToSL 375
CSJ0167-01-095
Proj IDSTP 1702(687)MM
Work TypeWIDEN BY ADDING TWO INSIDE LANES
 
1.99213995966.3714737432.4199.9
CountyEL PASO
HighwayUS 54
FromHONDO PASS DRIVE
ToSL 375
CSJ0167-01-098
Proj IDSTP 1702(687)MM
Work TypeOPERATIONAL IMPROVEMENTS
 
1.99219680182.5514877666.7675.5
Work Order09-12-17
Work Began11-09-17
Work Completed
Time Computed10-12-17
Contract Working Days460
Addl Days Granted64
Working Days Charged466
Percent Time Used88
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-095
HARDY HOLE DRILLING (1.38)
TRI STATE ELECTRIC, LTD. (33.92)
A BROTHERS MILLING, LLC (0.15)
ANTIGO CONSTRUCTION, INC. (0.19)
CONCRETE PUMPING, INC. DBA CPI (0.12)
EARTH REINFORCEMENTS LLC (2.53)
PENHALL COMPANY (0.01)
SCOTT DERR PAINTING CO, LLC (0.19)
X GOMEZ LOGISTICS LLC (1.46)
SATARAIN CONSTRUCTION, INC. (6.36)
NATIONWIDE REBAR, INC. (4.26)
PMI PAVEMENT MARKING, INC. (0.63)
HARDY HOLE DRILLING (1.18)
A BROTHERS MILLING, LLC (0.01)
GREENE CRANE & RIGGING, LLC (0.21)
BORDER DRILLING LLC (0.13)
CRANE SERVICES, INC. (0.03)
CONCRETE PUMPING, INC. DBA CPI (0.03)
THORCON SHOTCRETE AND SHORING LLC (0.66)
Contract #08173002
Totals33676148.921006547.2129615099.1787.9

CountyEL PASO
HighwayUS 54
FromLP 375 (CESAR CHAVEZ BORDER HWY)
ToYANDELL DR
CSJ0167-01-113
Proj IDNH 2019(166)
Work TypeINTERCHANGE IMPROVEMENTS
 
1.18189861277.4022512692.5425.0
CountyEL PASO
HighwayIH 110
FromUS 62
ToI 10
CSJ0167-01-118
Proj IDNH 2019(167)
Work TypeINSTALLATION OF SIGNS
 
0.900357297.000.000.0
CountyEL PASO
HighwayIH 110
FromUS 62
ToI 10
CSJ0167-01-119
Proj IDROW 167-1-119
Work TypeACQUISITION
 
0.900948024.00163923.0017.2
Work Order01-15-19
Work Began02-19-19
Work Completed
Time Computed02-02-19
Contract Working Days722
Addl Days Granted0
Working Days Charged131
Percent Time Used18
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-113
TRI STATE ELECTRIC, LTD. (17.11)
APACHE BARRICADE & SIGN (1.12)
NATIONWIDE REBAR, INC. (0.87)
HARDY HOLE DRILLING (8.97)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.74)
F A L C ENTERPRISES, LLC. (1.67)
THE GROUND LEVEL COMPANY (1.60)
BORDER DRILLING LLC (0.08)
DUSTROL, INC. (0.01)
ALLIED PAVING CO. (2.02)
ADVANCED CONCRETE SAWING & SEALING, LLC (0.09)
SCOTT DERR PAINTING CO, LLC (0.25)
HYDRATECH FIELD SERVICES, LLC (0.06)
HERNANDEZ CONCRETE PUMPING, INC. (0.57)
CRANE SERVICES, INC. (0.61)
Contract #11183001
Totals91166598.402283860.5022676615.5424.8

CountyEL PASO
HighwayBU 54-A
FromMESQUITE HILLS DR
ToNEW MEXICO STATE LINE
CSJ0167-02-051
Proj IDC 167-2-51
Work TypeOVERLAY
 
5.4361723480.00594341.8034.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-12-18
Work Began03-18-19
Work Completed
Time Computed10-12-18
Contract Working Days52
Addl Days Granted0
Working Days Charged43
Percent Time Used82
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0167-02-051
DUSTROL, INC. (2.67)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.15)
PMI PAVEMENT MARKING, LLC (5.55)
Contract #07183030
Totals1723480.000.00594341.8034.4

CountyCULBERSON ETC
HighwayUS 62 ETC
From9.2 MI E OF SH 54
To3.9 MI W OF RM 652
CSJ0233-01-044
Proj IDSTP 2017(953)HES
Work TypeMODERNIZE BRIDGE RAIL/APR GUARDRAIL
 
49.2123783684.493666505.6397.9
Work Order05-16-17
Work Began07-17-17
Work Completed
Time Computed06-06-17
Contract Working Days200
Addl Days Granted0
Working Days Charged240
Percent Time Used120
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0233-01-044
DOUBLE A CONTRACTING, L.P. (1.00)
Contract #04173211
Totals3783684.490.003666505.6397.9

CountyEL PASO
HighwayUS 62
FromGLOBAL REACH DR
ToFM 659 (ZARAGOZA RD)
CSJ0374-02-097
Proj IDNH 2019(063)
Work TypeBUILD FRONTAGE ROADS AND MAINLANES
 
7.833138160814.058934106.086.4
CountyEL PASO
HighwayUS 62
FromGLOBAL REACH DR
ToFM 659 (ZARAGOZA RD)
CSJ0374-02-103
Proj IDROW 374-2-103
Work TypeROW ACQUISITION
 
4.5605593434.000.000.0
CountyEL PASO
HighwayUS 62
FromAT TIERRA ESTE
To.
CSJ0374-02-111
Proj IDSTP 2019(064)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.200453662.600.000.0
Work Order12-17-18
Work Began04-22-19
Work Completed
Time Computed03-17-19
Contract Working Days811
Addl Days Granted24
Working Days Charged79
Percent Time Used9
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-097
TRAFFIC BARRICADE SERVICE, INC. (0.23)
SANCHEZ CONSTRUCTION & LANDSCAPING (0.50)
ZTEX CONSTRUCTION, INC. (6.67)
A BROTHERS MILLING, LLC (0.19)
HAWK CONSTRUCTION (4.50)
HARDY HOLE DRILLING (4.83)
BORDER DEMOLITION AND ENVIRONMENTAL, INC. (0.24)
PAVEMENT MARKINGS INC. (0.69)
TRI STATE ELECTRIC, LTD. (11.55)
DAMCON (1.85)
HDW CONSTRUCTION & DRILLING, LLC. (0.69)
Contract #10183227
Totals144207910.652899948.898934106.086.1

CountyEL PASO
HighwayUS 62
FromGERONIMO DR
ToSIOUX DR
CSJ0374-02-107
Proj IDCM 2019(991)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.6941033028.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-107
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193241
Totals1033028.050.000.000.0

CountyCULBERSON
HighwayUS 62
From4.79 MI SW OF SH54
To3.59 MI SW OF SH54
CSJ0374-08-021
Proj IDC 374-8-21
Work TypeCOUNTERMEASURE FOR BRIDGE SCOUR
 
1.2001434496.001387492.5096.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-18
Work Began10-18-18
Work Completed
Time Computed10-18-18
Contract Working Days100
Addl Days Granted0
Working Days Charged90
Percent Time Used90
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0374-08-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183030
Totals1434496.000.001387492.5096.7

CountyJEFF DAVIS
HighwaySH 118
From15.219 MI N OF SH 17
ToSH 17
CSJ0415-01-025
Proj IDSTP 2018(878)HES
Work TypeIMPROVE GUARDRAIL TO STANDARDS
 
15.219340160.00332020.0097.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-18-18
Work Began11-12-18
Work Completed
Time Computed07-18-18
Contract Working Days60
Addl Days Granted0
Working Days Charged61
Percent Time Used101
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0415-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183227
Totals340160.000.00332020.0097.7

CountyEL PASO
HighwayVA
FromDISTRICTWIDE
To.
CSJ0924-00-086
Proj IDSTP 2013(863)
Work TypeMETAL BEAM GUARD FENCE/SGT UPGRADES
 
3.2821408923.001239617.9599.9
Work Order10-24-13
Work Began11-14-13
Work Completed
Time Computed11-09-13
Contract Working Days188
Addl Days Granted235
Working Days Charged741
Percent Time Used175
Contractor(s)
SURETEC INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-086
DAN WILLIAMS COMPANY (0.00)
X GOMEZ LOGISTICS LLC (0.00)
Contract #07133012
Totals1408923.008750.001239617.9599.9

CountyEL PASO
HighwayVA
FromDISTRICTWIDE
To.
CSJ0924-00-099
Proj IDSTP 2018(932)
Work TypeFY 2018 BRIDGE MAINTENANCE
 
1.0002093680.002267406.4099.9
Work Order07-17-18
Work Began09-17-18
Work Completed
Time Computed08-16-18
Contract Working Days168
Addl Days Granted20
Working Days Charged154
Percent Time Used81
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-099
A BROTHERS MILLING, LLC (0.24)
X GOMEZ LOGISTICS LLC (0.21)
PMI PAVEMENT MARKING, LLC (3.61)
Contract #06183022
Totals2093680.0087938.412267406.4099.9

CountyEL PASO ETC
HighwayVA ETC
FromDISTRICTWIDE
To.
CSJ0924-00-100
Proj IDSTP 2019(575)
Work TypeFY 2019 STRIPING PROJECT
 
171.0861965159.5195911.894.8
Work Order04-03-19
Work Began05-29-19
Work Completed
Time Computed05-03-19
Contract Working Days98
Addl Days Granted0
Working Days Charged32
Percent Time Used32
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02193017
Totals1965159.5177175.4195911.894.8

CountyEL PASO
HighwayCS
FromALBERTON AVE
To200 FT S OF LTV RD
CSJ0924-06-457
Proj IDSTP 2015(455)MM
Work TypeWIDEN ROAD
 
1.2506591274.786920981.9999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-03-16
Work Began02-01-17
Work Completed
Time Computed03-03-17
Contract Working Days240
Addl Days Granted111
Working Days Charged409
Percent Time Used116
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-457
INTERNATIONAL EAGLE ENTERPRISES, INC. (42.75)
TRI STATE ELECTRIC, LTD. (10.14)
PRIME IRRIGATION & LANDSCAPE, INC. (1.94)
ABRI TRANSPORTATION SERVICES, LLC (0.37)
PMI PAVEMENT MARKING, INC. (0.82)
HENRY TRUJILLO, INC. (0.39)
FALC ENTERPRISES, LLC (0.37)
BORDER DRILLING LLC (0.01)
HARDY HOLE DRILLING (0.05)
NATIONWIDE REBAR INC (0.34)
DUSTROL, INC. (0.38)
Contract #08163204
Totals6591274.780.006920981.9999.9

page 1 | page 2