Monthly Local Let Maintenance Report For Lubbock District As Of Aug 23, 2019 Page 1 Of 3

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLUBBOCK
HighwayIH0027
FromIH-27 AT KEUKA ST
ToIH-27 AT RANDALL COUNTY LINE
CSJ6228-40-001
Proj IDRMC - 622840001
Work TypeILLUMINATION SYSTEM MAINTENANCE
 
0.00179300.0072674.5091.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-11
Work Began11-15-11
Work Completed
Time Computed11-07-11
Contract Working Days730
Addl Days Granted0
Working Days Charged594
Percent Time Used81
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6228-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07110503
Totals79300.000.0072674.5091.6

CountyLUBBOCK
HighwayUS0084
FromLUBBOCK SE & SPECIAL CREW MAINT OFFICES
ToLUBBOCK SE & SPECIAL CREW MAINT OFFICES
CSJ6232-03-001
Proj IDSUP - 623203001
Work TypeGROUNDS MAINTENANCE
 
0.00122846.0021273.0093.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-11
Work Began09-02-11
Work Completed
Time Computed09-02-11
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6232-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07110508
Totals22846.000.0021273.0093.1

CountyPARMER
HighwayUS0070
FromVARIOUS LOCATIONS IN THE LUBBOCK DISTRIC
ToT
CSJ6232-79-001
Proj IDRMC - 623279001
Work TypeMAINTENANCE OF TRAFFIC SIGNAL SYSTEMS
 
0.001175550.00114145.7065.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-12
Work Began02-01-12
Work Completed
Time Computed02-01-12
Contract Working Days730
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
CONCRETE CONNECTION
SUBCONTRACTOR(S) FOR CCSJ: 6232-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11110501
Totals175550.000.00114145.7065.0

CountyLUBBOCK
HighwayLP0289
FromLUBBOCK AE OFFICE
ToLUBBOCK AE OFFICE
CSJ6237-29-001
Proj IDSUP - 623729001
Work TypeROADSIDE MAINTENANCE
 
0.001382278.40454332.6899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-03-12
Work Began01-03-12
Work Completed
Time Computed01-03-12
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6237-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11110502
Totals382278.400.00454332.6899.9

CountyLUBBOCK
HighwayUS0084
FromLUBBOCK DISTRICT HQ
ToLUBBOCK DISTRICT HQ
CSJ6246-75-001
Proj IDSUP - 624675001
Work TypeVEHICLE WASH
 
0.0014485.001204.0026.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-27-12
Work Began09-01-12
Work Completed
Time Computed09-01-12
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6246-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07120501
Totals4485.000.001204.0026.8

CountyLUBBOCK
HighwayUS0084
FromLBB NORTHEAST PICNIC AREA
ToLBB NORTHEAST PICNIC AREA
CSJ6247-59-001
Proj IDSUP - 624759001
Work TypePICNIC AREA MAINTENANCE
 
0.00145763.0046246.51100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-28-12
Work Began09-04-12
Work Completed08-31-15
Time Computed09-04-12
Contract Working Days730
Addl Days Granted0
Working Days Charged204
Percent Time Used27
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6247-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08120505
Totals45763.000.0046246.51100.0

CountyLUBBOCK
HighwayLP0289
FromLUBBOCK SE MAINT OFFICE
ToLUBBOCK SE MAINT OFFICE
CSJ6248-08-001
Proj IDSUP - 624808001
Work TypeLITTER REMOVAL
 
0.001311846.92290260.1893.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-28-12
Work Began09-04-12
Work Completed
Time Computed09-04-12
Contract Working Days356
Addl Days Granted0
Working Days Charged194
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
L&D INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6248-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08120503
Totals311846.920.00290260.1893.0

CountyLUBBOCK
HighwayUS0062
FromLBB SOUTHEAST OFFICE
ToLBB SOUTEAST OFFICE
CSJ6248-09-001
Proj IDSUP - 624809001
Work TypeLITTER REMOVAL
 
0.00163590.5863454.3099.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-28-12
Work Began09-04-12
Work Completed
Time Computed09-04-12
Contract Working Days365
Addl Days Granted0
Working Days Charged183
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6248-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08120507
Totals63590.580.0063454.3099.7

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToIN LUBBOCK COUNTY
CSJ6253-78-001
Proj IDRMC - 625378001
Work TypeARMOR JOINT REPLACEMENT
 
0.001209630.00226438.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-13
Work Began05-13-13
Work Completed
Time Computed05-13-13
Contract Working Days102
Addl Days Granted0
Working Days Charged21
Percent Time Used20
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04130501
Totals209630.000.00226438.0099.9

CountyLAMB
HighwayUS0385
FromLITTLEFIELD_AREA
ToLITTLEFIELD AREA
CSJ6306-88-001
Proj IDSUP - 630688001
Work TypePICNIC AREA MAINTENANCE
 
0.001295328.00275675.0093.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6306-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160533
Totals295328.000.00275675.0093.3

CountyLAMB
HighwayUS0385
FromLITTLEFIELD AREA
ToLITTLEFIELD AREA
CSJ6306-92-001
Proj IDSUP - 630692001
Work TypeGROUND MAINTENANCE
 
0.00184588.0071981.0085.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6306-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160534
Totals84588.000.0071981.0085.0

CountyHALE
HighwayIH0027
FromPLAINVIEW AREA
ToPLAINVIEW AREA
CSJ6307-26-001
Proj IDSUP - 630726001
Work TypeGROUND MAINTENANCE
 
0.00184002.0063571.71100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-19-16
Work Began09-01-16
Work Completed08-31-18
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160535
Totals84002.000.0063571.71100.0

CountyHALE
HighwayIH0027
FromPLAINVIEW AREA
ToPLAINVIEW AREA
CSJ6307-27-001
Proj IDSUP - 630727001
Work TypePICNIC AND LITTER MAINTENANCE
 
0.001376820.00343640.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-16
Work Began09-01-16
Work Completed08-31-18
Time Computed09-19-16
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160536
Totals376820.000.00343640.00100.0

CountyLUBBOCK
HighwayIH0027
FromLUBBOCK SOUTHEAST
ToLUBBOCK SOUTHEAST
CSJ6307-46-001
Proj IDSUP - 630746001
Work TypeLITTER PICK UP
 
0.00174685.7460597.1781.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160539
Totals74685.740.0060597.1781.1

CountyTERRY
HighwayUS0062
FromBROWNFIELD
ToSEMINOLE
CSJ6316-58-001
Proj IDSUP - 631658001
Work TypeJANITORIAL FOR BROWNFIELD AREA OFFICES
 
0.001109291.50101809.2093.1
Work Order07-25-17
Work Began08-01-17
Work Completed
Time Computed03-08-18
Contract Working Days731
Addl Days Granted182
Working Days Charged730
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06170531
Totals109291.504050.32101809.2093.1

CountyLUBBOCK
HighwayIH0027
FromLUBBOCK NE
ToLUBBOCK SE
CSJ6316-60-001
Proj IDSUP - 631660001
Work TypeJANITORIAL FOR LUBBOCK OFFICES
 
0.00153356.5029343.1654.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-17
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged730
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06170532
Totals53356.50924.6629343.1654.9

CountyGARZA
HighwayUS0380
FromPOST RDC
ToPOST RDC
CSJ6321-45-001
Proj IDSUP - 632145001
Work TypeGROUNDS MAINTENANCE
 
0.00116416.0014136.0086.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged696
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6321-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170551
Totals16416.001140.0014136.0086.1

CountyLUBBOCK
HighwayUS0084
FromLBB SE MAINT OFFICE
ToLBB SPECIAL CREW OFFICE
CSJ6321-76-001
Proj IDSUP - 632176001
Work TypeGROUNDS MAINTENANCE
 
0.00149780.0038858.2078.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged699
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6321-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170553
Totals49780.002560.0038858.2078.0

CountyLUBBOCK
HighwayUS0084
FromLBB DISTRICT GROUNDS
ToLBB DISTRICT GROUNDS
CSJ6321-78-001
Proj IDSUP - 632178001
Work TypeGROUNDS MAINTENANCE
 
0.001100368.00128380.5599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged699
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6321-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170554
Totals100368.004500.00128380.5599.9

CountyHALE
HighwayIH0027
FromVARIOUS
ToVARIOUS
CSJ6322-80-001
Proj IDSUP - 632280001
Work TypeJANITORIAL MAINTENANCE SERVICES
 
0.001101541.28100146.4398.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged699
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170535
Totals101541.284619.57100146.4398.6

page 1 | page 2 | page 3