Monthly State Let Construction Report For Laredo District As Of Aug 23, 2019 Page 1 Of 2

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLASALLE
HighwayIH 35
From0.09 MI N OF IH35 UPRR UNDERPASS
To0.188 MI N OF FM 3408
CSJ0018-01-091
Proj IDNH 2018(779)
Work TypeBASE,ACP,GRAD,STR,PAV MRK
 
7.78111655295.274677872.8740.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-18
Work Began07-16-18
Work Completed
Time Computed00-00-00
Contract Working Days465
Addl Days Granted0
Working Days Charged207
Percent Time Used44
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-01-091
PENHALL COMPANY (0.10)
FLASHER LIMITED (0.40)
AREA WIDE PROTECTIVE, INC. (0.45)
AARON CONCRETE CONTRACTORS, L.P. (0.52)
ROADWAY SPECIALTIES, INC. (0.58)
DIAMOND M FIELD SERVICES LLC (1.24)
PAVEMENT MARKINGS INC. (1.27)
TRAF-TEX, INC. (4.13)
BEAVER CONTRACTORS, LLC (29.91)
Contract #04183017
Totals11655295.27501788.164677872.8740.1

CountyLASALLE
HighwayIH 35
FromFM 133 (WFR)
To0.30 MI N BI-35 WFR (COCHINA RD INT
CSJ0018-01-093
Proj IDNH 2019(164)
Work TypeBASE, SEAL COAT, PAV MRKS
 
10.21210878129.781825744.8616.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-25-19
Work Began04-10-19
Work Completed
Time Computed00-00-00
Contract Working Days497
Addl Days Granted0
Working Days Charged70
Percent Time Used14
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-01-093
H J HENKE COMPANY (0.44)
DIAMOND M FIELD SERVICES LLC (0.78)
AREA WIDE PROTECTIVE, INC. (0.42)
RPV CONSTRUCTION, LLC (1.54)
HIGHWAY BARRICADES AND SERVICES, LLC (2.60)
BEAVER CONTRACTORS, LLC (15.13)
Contract #11183207
Totals10878129.78292962.091825744.8616.7

CountyLASALLE
HighwayIH 35
FromFM 133
To1.031 MI S OF BI 35C (SOUTH INT)
CSJ0018-01-097
Proj IDC 18-1-97
Work TypePLANING, ACP, PAV MRK
 
10.7085687629.006518284.5999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-18
Work Began01-07-19
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged107
Percent Time Used100
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-01-097
AREA WIDE PROTECTIVE, INC. (0.13)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.32)
CHEROKEE SERVICES (1.08)
INTERSTATE BARRICADES & MARKINGS, INC. (1.63)
DEPENDABLE FENCE & WELDING CO. INC. (4.23)
Contract #07183037
Totals5687629.0043766.156518284.5999.9

CountyLASALLE
HighwayIH 35
FromWEBB COUNTY LINE
ToFM 133
CSJ0018-02-085
Proj IDBR 1802(408)
Work TypeBRIDGE RAIL,SET,MBGF,SGT
 
17.743567072.61115879.7220.4
CountyWEBB
HighwayVA
FromDISTRICTWIDE
To.
CSJ0922-00-064
Proj IDSTP 1802(313)
Work TypeBRIDGE RAIL,SET,MBGF,SGT
 
0.1001464381.24706694.8648.2
CountyMAVERICK
HighwayFM 1021
FromFM 3443
To0.383 MI NORTH OF FM 2644
CSJ1229-01-066
Proj IDBR 1802(314)
Work TypeBRIDGE RAIL,SET,MBGF,SGT
 
15.896450736.1456434.4012.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-17-18
Work Began01-24-19
Work Completed
Time Computed00-00-00
Contract Working Days308
Addl Days Granted0
Working Days Charged135
Percent Time Used43
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-02-085
FLASHER EQUIPMENT COMPANY (2.86)
DEPENDABLE FENCE & WELDING CO. INC. (10.65)
Contract #07183231
Totals2482189.99108132.36879008.9835.4

CountyWEBB
HighwayIH 35
From1.086 MI S OF SAN ROMAN
To1.300 MI N OF SAN ROMAN
CSJ0018-03-058
Proj IDSTP 2019(607)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.966503366.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days98
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F & W ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-03-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193030
Totals503366.750.000.000.0

CountyWEBB ETC
HighwayIH 35 ETC
From1.298 MI NORTH OF US 83 (WFR)
To0.907 MI NORTH OF CALLAGHAN INTCHG
CSJ0018-04-056
Proj IDNH 2019(033)
Work TypeSURF TREAT,PAV MRKS
 
106.1764275901.344078354.7695.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days117
Addl Days Granted0
Working Days Charged54
Percent Time Used46
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0018-04-056
CHEROKEE SERVICES (1.95)
FLASHER EQUIPMENT COMPANY (1.41)
VIZCAINO, L.P. (15.45)
Contract #09183010
Totals4275901.34440.004078354.7695.3

CountyWEBB ETC
HighwayIH 35 ETC
From@ SH 255
To.
CSJ0018-04-060
Proj IDSTP 1802(358)HES
Work TypeINSTALL FLASHING BEACON
 
6.813521314.85241083.7046.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged50
Percent Time Used27
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-04-060
PAVEMENT MARKINGS INC. (7.54)
J.D. ABRAMS, L.P. (20.29)
S & S BRIDGE PAINTING, INC. (0.05)
Contract #08183049
Totals521314.8573076.23241083.7046.2

CountyWEBB ETC
HighwayIH 35 ETC
From1.190 MILES S OF CARRIER RD (EFR)
To0.169 MILES N OF UNIROYAL DR (EFR)
CSJ0018-05-095
Proj IDNH 2019(375)
Work TypeACP, PAV REPAIR, PAV MRKS
 
27.14012256476.314260169.5134.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-20-19
Work Began04-19-19
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted0
Working Days Charged64
Percent Time Used17
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-05-095
BEAVER CONTRACTORS, LLC (5.37)
A BROTHERS MILLING, LLC (1.40)
BLACKTOP INDUSTRIES LLC (3.19)
CHEROKEE SERVICES (0.13)
HIGHWAY BARRICADES AND SERVICES, LLC (0.22)
PAVEMENT MARKINGS INC. (1.38)
SOIL-TECH, INC. (0.08)
TEXAS R & G CONSTRUCTION SERVICES LLC (7.58)
WEST TEXAS ROCK RESOURCES, LLC (0.24)
Contract #01193204
Totals12256476.312808749.104260169.5134.7

CountyVAL VERDE
HighwayUS 90
From200 FT NORTHWEST OF PECOS BRIDGE
To200 FT SOUTHEAST OF PECOS BRIDGE
CSJ0022-06-051
Proj IDC 22-6-51
Work TypeAPCH SLAB, BASE, ACP, SURF, PAV MRK
 
0.325476631.60463528.2997.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-27-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged40
Percent Time Used100
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0022-06-051
FLASHER EQUIPMENT COMPANY (10.12)
Contract #06183257
Totals476631.600.00463528.2997.2

CountyVAL VERDE ETC
HighwayUS 90 ETC
From1.195 MI W OF PR 67
To0.5 MI E OF SH 163
CSJ0022-07-030
Proj IDSTP 2019(819)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
100.291911560.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-02-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0022-07-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193026
Totals911560.500.000.000.0

CountyVAL VERDE
HighwayUS 90
From0.03 MI N OF QUAIL ROAD
To0.04 MI N OF GARNER
CSJ0022-10-070
Proj IDSTP 1902(254)HES
Work TypeSFT
 
5.009692972.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0022-10-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193237
Totals692972.360.000.000.0

CountyZAVALA ETC
HighwayUS 83 ETC
FromUS 57
ToDIMMIT COUNTY LINE
CSJ0037-03-083
Proj IDSTP 2019(820)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
91.978687075.490.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0037-03-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193232
Totals687075.490.000.000.0

CountyDIMMIT ETC
HighwayUS 83 ETC
From1.394 MI N OF FM 133
ToWEBB COUNTY LINE
CSJ0037-08-041
Proj IDSTP 2019(960)HES
Work TypePROFILE EDGE MRK, PROFILE CL MRK
 
92.6411275015.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-19
Work Began08-07-19
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged13
Percent Time Used21
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0037-08-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193038
Totals1275015.850.000.000.0

CountyWEBB
HighwayUS 83
FromDIMMIT CO. LINE
To3.442 MILES SOUTH OF SH 44
CSJ0037-09-033
Proj IDNH 2019(048)
Work TypeBASE, ACP, PAV MRKS
 
16.47948720816.803098465.316.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-15-18
Work Began05-28-19
Work Completed
Time Computed00-00-00
Contract Working Days734
Addl Days Granted0
Working Days Charged47
Percent Time Used6
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0037-09-033
EGGEMEYER LAND CLEARING, LLC (0.25)
DEPENDABLE FENCE & WELDING CO. INC. (1.25)
BLACKTOP INDUSTRIES LLC (0.37)
D&S TEXAS ICON CONSTRUCTION (1.27)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.07)
TRAF-TEX, INC. (0.08)
HIGHWAY BARRICADES AND SERVICES, LLC (1.28)
BEAVER CONTRACTORS, LLC (16.51)
Contract #10183202
Totals48720816.802603396.163098465.316.3

CountyWEBB
HighwayUS 83
From3.442 MILES SOUTH OF SH 44
ToIH35/US83 INTERSECTION WEST FRTG RD
CSJ0037-10-037
Proj IDNH 2019(047)
Work TypeRER
 
68572893.010.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,049
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0037-10-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193001
Totals68572893.010.000.000.0

CountyWEBB
HighwaySH 359 ETC
FromJUDITH GUTIERREZ PARKWAY
To8.892 MILES EAST OF SL 20
CSJ0086-01-091
Proj IDSTP 1802(248)HES
Work TypePROFILE EDGE MRK, PROFILE CL MRK
 
79.01128248453.6617245085.1661.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-18
Work Began02-04-19
Work Completed
Time Computed00-00-00
Contract Working Days371
Addl Days Granted0
Working Days Charged121
Percent Time Used32
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-01-091
CHEROKEE SERVICES (0.09)
FLASHER EQUIPMENT COMPANY (1.11)
FUQUAY, INC. (0.06)
HIGHWAY BARRICADES AND SERVICES, LLC (0.09)
BEAVER CONTRACTORS, LLC (2.37)
APEX HIGHWAY SERVICES, LLC (0.21)
RPV CONSTRUCTION, LLC (2.18)
A K FUQUAY CONSTRUCTION (0.06)
(INACTIVE)WEST TEXAS RUMBLE STRIP (0.18)
Contract #06183256
Totals28248453.66222618.4817245085.1661.0

CountyDUVAL ETC
HighwaySH 359 ETC
FromWEBB COUNTY LINE
ToJIM HOGG COUNTY LINE
CSJ0086-05-018
Proj IDSTP 2019(749)HES
Work TypePROFILE EDGE MRK, PROFILE CL MRK
 
87.681877187.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-05-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193226
Totals877187.660.000.000.0

CountyWEBB
HighwaySL 20
FromSH 359
ToSPUR 400
CSJ0086-14-061
Proj IDSTP 1502(617)MM
Work TypeGRADING, BASE, STRUCTURES & SURFACE
 
2.40525541056.4024325195.1096.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-04-15
Work Began03-07-16
Work Completed
Time Computed00-00-00
Contract Working Days596
Addl Days Granted28
Working Days Charged763
Percent Time Used122
Contractor(s)
OSCAR RENDA CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-061
ANGEL BROTHERS ENTERPRISES, LTD. (11.40)
HIGHWAY BARRICADES AND SERVICES, LLC (1.53)
LAREDO STRIPING INC. (2.36)
S & S BRIDGE PAINTING, INC. (0.19)
SOIL-TECH, INC. (1.05)
W. W. FOUNDATION DRILLING, LTD. (2.97)
TEXAS STEEL (1.85)
CANTU ELECTRIC CO., INC. (2.46)
RRR SEALCOAT & STRIPING, LLC (0.05)
Contract #08153003
Totals25541056.4012077.2724325195.1096.6

CountyWEBB
HighwaySL 20
From0.330 MILES WEST OF IH 35
To0.160 MILES WEST OF MCPHERSON
CSJ0086-14-065
Proj IDCBI 1602(504)
Work TypeFLEX BASE,SURF,BRIDGE AND PAV MRK
 
4.38025596044.4921444848.5283.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-17
Work Began01-02-18
Work Completed
Time Computed00-00-00
Contract Working Days724
Addl Days Granted0
Working Days Charged545
Percent Time Used75
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-065
ANGEL BROTHERS HOLDINGS CORP. (3.51)
CANTU ELECTRIC CO., INC. (5.77)
HIGHWAY BARRICADES AND SERVICES, LLC (0.57)
ATS DRILLING, INC. (3.31)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.59)
MONTALVO BRIDGE SYSTEMS, LLC (1.93)
BOWMAN ENGINEERING & CONSULTING, INC (0.24)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.07)
AARON CONCRETE CONTRACTORS, L.P. (1.05)
Contract #07173004
Totals25596044.49392602.9821444848.5283.7

CountyWEBB ETC
HighwayUS 59 ETC
FromAT DEL MAR BLVD
To.
CSJ0086-14-073
Proj IDSTP 2019(608)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
3.360579929.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days132
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-073
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193032
Totals579929.390.000.000.0

page 1 | page 2