Monthly State Let Construction Report For Laredo District As Of Oct 16, 2017 Page 1 Of 2

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLASALLE
HighwayIH 35
From@ FM 468
To.
CSJ0017-08-102
Proj IDSTP 2017(581)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.800541921.2061812.7011.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-08-102
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173021
Totals541921.2061812.7061812.7011.4

CountyLASALLE
HighwayIH 35
From0.128 MI N OF FM 133
To0.015 MI S OF FM 133
CSJ0018-01-076
Proj IDNH 2017(325)
Work TypeREHABILITATION OF EXISTING HIGHWAY
 
0.5871622860.210.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-09-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0018-01-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173019
Totals1622860.210.000.000.0

CountyLASALLE
HighwayIH 35
FromSH 44 EAST FRONTAGE ROAD
ToCAIMAN CREEK INTERCHANGE
CSJ0018-02-064
Proj IDIM 0351(094)
Work TypeGRADE,BASE,STRUCT,ACP,PAV MKS, SIGN
 
9.3566908417.386928730.4999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-16
Work Began10-26-16
Work Completed
Time Computed00-00-00
Contract Working Days195
Addl Days Granted26
Working Days Charged209
Percent Time Used94
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-02-064
BEAVER CONTRACTORS, LLC (11.14)
D&S TEXAS ICON CONSTRUCTION (1.40)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.32)
MV HENKE COMPANY, LLC (0.50)
FLASHER EQUIPMENT COMPANY (2.24)
Contract #08163056
Totals6908417.38264644.936928730.4999.9

CountyWEBB
HighwayIH 35
From0.945 MI N OF CALLAGHAN INT (EFR)
ToWEBB/LA SALLE COUNTY LINE
CSJ0018-03-056
Proj IDNH 2018(105)
Work TypeSEALCOAT & PAV MRKS
 
33.6471393636.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days97
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0018-03-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173005
Totals1393636.950.000.000.0

CountyVAL VERDE
HighwayUS 90 ETC
FromAT 2ND ST
To.
CSJ0022-10-064
Proj IDSTP 1702(310)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.400419937.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0022-10-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173034
Totals419937.400.000.000.0

CountyKINNEY ETC
HighwayUS 90 ETC
From0.375 MI EAST OF SH 131
ToKINNEY/UVALDE COUNTY LINE
CSJ0023-04-065
Proj IDNH 2017(587)
Work TypeACP OVERLAY, PAV MRKS
 
47.10310014131.22716620.967.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged16
Percent Time Used5
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0023-04-065
FLASHER EQUIPMENT COMPANY (2.82)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.67)
PRIMATE CONSTRUCTION, INC. (1.37)
STRIPE-A-ZONE, INC. (0.73)
D&S TEXAS ICON CONSTRUCTION (0.00)
CLARK CONSTRUCTION OF TEXAS, INC. (3.22)
Contract #04173202
Totals10014131.22716620.96716620.967.1

CountyDIMMIT ETC
HighwayUS 83 ETC
FromAT FM 790
To.
CSJ0037-05-051
Proj IDSTP 1702(317)HES
Work TypeINSTALL INTERSECTION FLASHING BEACO
 
1.600452670.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days133
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0037-05-051
PAVEMENT MARKINGS INC. (6.91)
Contract #06173213
Totals452670.200.000.000.0

CountyWEBB
HighwayUS 83
FromESPEJO MOLINA ROAD(NB &SB LANE)
ToZAPATA/WEBB COUNTY LINE
CSJ0038-01-086
Proj IDNH 2017(582)
Work TypeTHIN OVERLAY MIXTURE, PAV MRKS
 
15.5587577537.745200674.6568.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-10-17
Work Began05-23-17
Work Completed
Time Computed00-00-00
Contract Working Days161
Addl Days Granted0
Working Days Charged87
Percent Time Used54
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0038-01-086
BEAVER CONTRACTORS, LLC (4.84)
CHEROKEE SERVICES (0.11)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.87)
FLASHER EQUIPMENT COMPANY (1.68)
HIGHWAY BARRICADES AND SERVICES, LLC (0.33)
Contract #02173230
Totals7577537.74962776.615200674.6568.6

CountyWEBB
HighwayUS 83 ETC
FromIH 35
ToKCS RAILROAD CROSSING
CSJ0086-01-084
Proj IDSTP 1602(295)
Work TypeTOM OVERLAY & PAV MRKS
 
7.8164395787.294372054.2699.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-20-16
Work Began04-03-17
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged72
Percent Time Used96
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0086-01-084
CHEROKEE SERVICES (0.60)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.67)
FLASHER EQUIPMENT COMPANY (0.40)
STRIPE-A-ZONE, INC. (4.45)
FLASHER EQUIPMENT COMPANY (4.83)
Contract #07163212
Totals4395787.2961018.304372054.2699.4

CountyDUVAL ETC
HighwaySH 359 ETC
From2.260 MI NORTH OF FM 2295
ToFM 1329
CSJ0086-10-049
Proj IDSTP 2016(475)
Work TypeACP, OVERLAY PAV MRK
 
43.11314344014.4513944199.1497.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-16
Work Began07-05-16
Work Completed
Time Computed00-00-00
Contract Working Days263
Addl Days Granted0
Working Days Charged258
Percent Time Used98
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-10-049
CLARK CONSTRUCTION OF TEXAS, INC. (11.01)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.00)
D. I. J. CONSTRUCTION, INC. (2.10)
FLASHER EQUIPMENT COMPANY (0.20)
RELMCO, INC. (7.90)
WEST TEXAS RUMBLE STRIP (0.11)
ROVAN TEXAS, LLC (0.21)
BEAVER CONTRACTORS, LLC (0.16)
Contract #01163004
Totals14344014.4542850.0013944199.1497.2

CountyWEBB
HighwaySL 20
From0.457 MI S OF SS 400 (KCS RR OVP)
To0.450 MI N OF US 59 (STA. 140+00)
CSJ0086-14-046
Proj IDCBI 2013(281)
Work TypeGRAD, WID STRS, BASE AND PAV
 
1.75133883949.2029304148.9386.4
CountyWEBB
HighwaySL 20
From0.457 MI S OF SS 400 (KCS RR OVP)
To0.450 MI N OF US 59 (STA. 140+00)
CSJ0086-14-056
Proj IDROW 86-14-56
Work TypeACQUISITION & UTILITY ADJUSTMENTS
 
1.7511993938.701736764.9287.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-03-14
Work Began07-27-15
Work Completed
Time Computed00-00-00
Contract Working Days535
Addl Days Granted26
Working Days Charged526
Percent Time Used93
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-046
ANGEL BROTHERS ENTERPRISES, LTD. (19.52)
CABCOS CONTRACTORS LLC (3.32)
HIGHWAY BARRICADES AND SERVICES, LLC (0.80)
LAREDO STRIPING INC. (0.78)
SOIL-TECH, INC. (0.55)
STAR OPERATIONS, INC. (3.77)
VOGES DRILLING CO. (0.61)
WEBBER BARRIER SERVICES, LLC. (0.72)
SAN ANTONIO TELEPHONE COMPANY INC. (0.07)
REIM CONSTRUCTION, INC. (0.78)
AARON CONCRETE CONTRACTORS, L.P. (2.09)
FRANK JR REINFORCEMENT LLC (0.03)
RAMOS MASONRY (0.11)
V.C. HUFF, L.L.C. (2.37)
IVY ROSALVA CRUZ DBA IVY"S TRUCKING (0.09)
SOUTH TEXAS PAINTING COMPANY (0.18)
SCOTT DERR PAINTING CO, LLC (0.29)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.07)
Contract #08143002
Totals35877887.901004783.8431040913.8586.5

CountyWEBB
HighwaySL 20
FromSH 359
ToSPUR 400
CSJ0086-14-061
Proj IDSTP 1502(617)MM
Work TypeGRADING, BASE, STRUCTURES & SURFACE
 
2.40525541056.4012881200.2250.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-04-15
Work Began03-07-16
Work Completed
Time Computed00-00-00
Contract Working Days596
Addl Days Granted0
Working Days Charged362
Percent Time Used60
Contractor(s)
OSCAR RENDA CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-061
ANGEL BROTHERS ENTERPRISES, LTD. (11.40)
HIGHWAY BARRICADES AND SERVICES, LLC (1.53)
LAREDO STRIPING INC. (2.36)
S & S BRIDGE PAINTING, INC. (0.19)
SOIL-TECH, INC. (1.05)
W. W. FOUNDATION DRILLING, LTD. (2.97)
TEXAS STEEL (1.85)
CANTU ELECTRIC CO., INC. (2.46)
RRR SEALCOAT & STRIPING, LLC (0.05)
Contract #08153003
Totals25541056.40330839.0912881200.2250.4

CountyWEBB
HighwaySL 20
From0.330 MILES WEST OF IH 35
To0.160 MILES WEST OF MCPHERSON
CSJ0086-14-065
Proj IDCBI 1602(504)
Work TypeFLEX BASE,SURF,BRIDGE AND PAV MRK
 
4.38025596044.490.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days724
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173004
Totals25596044.490.000.000.0

CountyWEBB
HighwaySL 20
From0.45 MI EAST OF INTERNATIONAL BLVD
To0.25 MI WEST OF MCPHERSON ROAD
CSJ0086-14-066
Proj IDNH 2016(400)
Work TypeFLEX BSE, SURF, BRIDGE, PAV MRK ETC
 
1.41721976081.1518955115.2586.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-16
Work Began05-23-16
Work Completed
Time Computed00-00-00
Contract Working Days387
Addl Days Granted65
Working Days Charged460
Percent Time Used101
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-066
AARON CONCRETE CONTRACTORS, L.P. (0.75)
ALTUS TRAFFIC MANAGEMENT LLC (0.15)
ATS DRILLING, INC. (0.82)
D&S TEXAS ICON CONSTRUCTION (1.25)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.19)
FLASHER EQUIPMENT COMPANY (0.35)
FOREMOST PAVING, INC. (9.45)
FUQUAY, INC. (0.25)
PENHALL COMPANY (0.05)
PRIMATE CONSTRUCTION, INC. (0.06)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.14)
SOUTH TEXAS PAINTING COMPANY (0.12)
THE LEVY COMPANY, L.P. (4.89)
CUATRO T CONSTRUCTION, INC. (3.59)
INDUS CONSTRUCTION, L.P. (0.06)
Contract #12153003
Totals21976081.153408342.6518955115.2586.3

CountyVAL VERDE ETC
HighwayUS 277 ETC
From7.953 MI SOUTH OF EDWARDS CL
To12.336 MI SOUTH OF EDWARDS CL
CSJ0160-04-049
Proj IDNH 2018(088)
Work TypeSEALCOAT & PAV MRKS
 
54.3902245195.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0160-04-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173014
Totals2245195.910.000.000.0

CountyWEBB
HighwaySH 44
FromLOS OLMOS CREEK
ToIN WEBB COUNTY
CSJ0237-03-030
Proj IDBR 1602(506)
Work TypeREPLACEMENT OF AN EXISTING BRIDGE
 
0.3023538171.861616817.6945.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-16
Work Began03-27-17
Work Completed
Time Computed00-00-00
Contract Working Days256
Addl Days Granted0
Working Days Charged122
Percent Time Used47
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0237-03-030
RIO GRANDE REBAR PLACING, LTD. (2.26)
D&S TEXAS ICON CONSTRUCTION (0.43)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.13)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.36)
FLASHER EQUIPMENT COMPANY (1.22)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25)
MUNOZ FOUNDATION DRILLING, INC. (0.71)
SCOTT DERR PAINTING CO, LLC (0.01)
ANDERSON COLUMBIA CO., INC. (7.19)
Contract #08163016
Totals3538171.86146816.451616817.6945.6

CountyWEBB ETC
HighwaySH 44 ETC
From13.947 MILES EAST OF LA SALLE CL
ToDUVAL COUNTY LINE
CSJ0237-03-032
Proj IDSTP 1502(157)
Work TypeACP OVERLAY, MBGF, PAV MRK
 
65.96612273762.9311274997.5092.0
Work Order06-30-15
Work Began10-05-15
Work Completed
Time Computed07-31-15
Contract Working Days228
Addl Days Granted90
Working Days Charged339
Percent Time Used106
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0237-03-032
CLARK CONSTRUCTION OF TEXAS, INC. (15.51)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.24)
FLASHER EQUIPMENT COMPANY (2.63)
PRIMATE CONSTRUCTION, INC. (0.24)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.24)
D&S TEXAS ICON CONSTRUCTION (1.08)
Contract #05153006
Totals12273762.93143934.4111274997.5092.0

CountyDIMMIT
HighwayFM 133
FromUS 83
To5.0 MILES EAST OF US 83
CSJ0237-07-013
Proj IDSTP 1702(496)
Work TypeBASE,GRADE,ACP,PAV MARK
 
18.7309690620.280.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days185
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0237-07-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173208
Totals9690620.280.000.000.0

CountyMAVERICK ETC
HighwayUS 57 ETC
From2.887 MI EAST OF FM 481
ToZAVALA COUNTY LINE
CSJ0276-02-028
Proj IDSTP 2017(027)
Work TypeSEAL COAT & PAV MRKS
 
51.9941770045.301979126.3999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-16
Work Began04-18-17
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged81
Percent Time Used55
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0276-02-028
FLASHER EQUIPMENT COMPANY (1.90)
MPB, INC. (1.06)
VIZCAINO, L.P. (16.87)
Contract #09163004
Totals1770045.300.001979126.3999.9

CountyMAVERICK ETC
HighwayUS 277
FromKINNEY/MAVERICK COUNTY LINE
To0.273 MI S OF FM 1665 SOUTHERN INT
CSJ0299-03-050
Proj IDNH 1702(691)
Work TypeBASE,WIDEN,GRAD,SURF,PAVMRK&SIGN
 
92.75320795394.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days575
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0299-03-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173203
Totals20795394.700.000.000.0

page 1 | page 2