Monthly Local Let Maintenance Report For Odessa District As Of Nov 12, 2021 Page 1 Of 5

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyECTOR
HighwayLP0338
FromODESSA MAINTENANCE OFFICE
ToODESSA MAINTENANCE OFFICE
CSJ6173-64-001
Proj IDSUP - 617364001
Work TypeGROUNDS MAINTENANCE
 
0.0017717.506615.0085.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-26-08
Work Began03-11-08
Work Completed
Time Computed03-01-08
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6173-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01080631
Totals7717.500.006615.0085.7

CountyMARTIN
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6197-11-001
Proj IDRMC - 619711001
Work TypeROADSIDE MOWING
 
234.30083691.9668030.0781.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-03-10
Work Began06-09-10
Work Completed
Time Computed06-09-10
Contract Working Days56
Addl Days Granted0
Working Days Charged19
Percent Time Used33
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6197-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01100606
Totals83691.960.0068030.0781.2

CountyWINKLER
HighwaySH0302
FromVARIOUS
ToVARIOUS
CSJ6234-97-001
Proj IDRMC - 623497001
Work TypeROADSIDE MOWING
 
0.00146995.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KRAFT WERKS
SUBCONTRACTOR(S) FOR CCSJ: 6234-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05120601
Totals46995.260.000.000.0

CountyWARD
HighwayBI0020D
FromVARIOUS
ToVARIOUS
CSJ6297-63-001
Proj IDRMC - 629763001
Work TypeRETROREFLECTIVITY MEASUREMENT
 
0.00121323.8721323.88100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began05-16-16
Work Completed01-31-17
Time Computed05-16-16
Contract Working Days60
Addl Days Granted0
Working Days Charged59
Percent Time Used98
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160602
Totals21323.870.0021323.88100.0

CountyREEVES
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6324-69-001
Proj IDRMC - 632469001
Work TypeROADSIDE MOWING
 
0.001220688.00415092.0099.9
Work Order02-01-18
Work Began06-20-18
Work Completed
Time Computed02-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,369
Percent Time Used93
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180601
Totals220688.0028340.00415092.0099.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6324-70-001
Proj IDRMC - 632470001
Work TypeROADSIDE MOWING
 
0.001297328.00503346.0099.9
Work Order03-01-18
Work Began07-02-18
Work Completed
Time Computed03-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,341
Percent Time Used91
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180602
Totals297328.000.00503346.0099.9

CountyMARTIN
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6324-71-001
Proj IDRMC - 632471001
Work TypeROADSIDE MOWING
 
0.001198528.00339264.0099.9
Work Order03-09-18
Work Began06-12-18
Work Completed
Time Computed04-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,310
Percent Time Used89
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180603
Totals198528.000.00339264.0099.9

CountyWARD
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6324-73-001
Proj IDRMC - 632473001
Work TypeROADSIDE MOWING
 
0.001258680.00439118.4999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-15-18
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted731
Working Days Charged1,280
Percent Time Used87
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180605
Totals258680.000.00439118.4999.9

CountyANDREWS
HighwayUS0385
FromVARIOUS
ToVARIOUS
CSJ6324-74-001
Proj IDRMC - 632474001
Work TypeROADSIDE MOWING
 
0.001181272.00333419.3099.9
Work Order03-09-18
Work Began06-05-18
Work Completed
Time Computed03-09-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,333
Percent Time Used91
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180606
Totals181272.000.00333419.3099.9

CountyREEVES
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6324-75-001
Proj IDRMC - 632475001
Work TypeROADSIDE MOWING
 
0.001286858.00480525.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-24-18
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted731
Working Days Charged1,310
Percent Time Used89
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180607
Totals286858.000.00480525.4099.9

CountyTERRELL
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6324-77-001
Proj IDRMC - 632477001
Work TypeROADSIDE MOWING
 
0.001183549.60306157.5299.9
Work Order03-26-18
Work Began08-03-18
Work Completed
Time Computed04-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,310
Percent Time Used89
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180608
Totals183549.600.00306157.5299.9

CountyTERRELL
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6326-53-001
Proj IDRMC - 632653001
Work TypePICNIC AREA MAINTENANCE
 
0.00198560.00175585.0099.9
Work Order02-01-18
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,369
Percent Time Used93
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6326-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180609
Totals98560.003680.00175585.0099.9

CountyWINKLER
HighwaySH0302
FromVARIOUS
ToVARIOUS
CSJ6327-61-001
Proj IDRMC - 632761001
Work TypeROADSIDE MOWING
 
0.001172028.00336371.0099.9
Work Order05-07-18
Work Began05-15-18
Work Completed
Time Computed05-21-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,280
Percent Time Used87
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6327-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02180601
Totals172028.000.00336371.0099.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6328-52-001
Proj IDRMC - 632852001
Work TypeLANDSCAPE MAINTENANCE
 
0.00183008.40114997.7099.9
Work Order05-22-18
Work Began06-01-18
Work Completed
Time Computed07-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,249
Percent Time Used85
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6328-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04180602
Totals83008.402635.05114997.7099.9

CountyMIDLAND
HighwayBI0020E
FromVARIOUS
ToVARIOUS
CSJ6329-50-001
Proj IDRMC - 632950001
Work TypePUMP STATION MAINTENANCE
 
0.001200204.00374558.0099.9
Work Order06-01-18
Work Began12-10-18
Work Completed
Time Computed06-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,249
Percent Time Used85
Contractor(s)
E.V.G. ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6329-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04180603
Totals200204.000.00374558.0099.9

CountyCRANE
HighwayUS0385
FromVARIOUS
ToVARIOUS
CSJ6334-10-001
Proj IDRMC - 633410001
Work TypeROADSIDE MOWING
 
0.001154744.00217562.5099.9
Work Order09-26-18
Work Began11-12-18
Work Completed
Time Computed10-01-18
Contract Working Days731
Addl Days Granted731
Working Days Charged1,127
Percent Time Used77
Contractor(s)
ABESCAPE GROUP LLC
SUBCONTRACTOR(S) FOR CCSJ: 6334-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08180602
Totals154744.000.00217562.5099.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6344-43-001
Proj IDRMC - 634443001
Work TypeROADSIDE MOWING
 
0.001249496.00236516.0099.9
Work Order06-25-19
Work Began07-31-19
Work Completed
Time Computed07-17-19
Contract Working Days731
Addl Days Granted731
Working Days Charged854
Percent Time Used58
Contractor(s)
ABESCAPE LANDSCAPING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6344-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04190601
Totals249496.000.00236516.0099.9

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6347-25-001
Proj IDRMC - 634725001
Work TypeSMALL SIGN REPLACEMENT (CALLOUT)
 
0.001183530.00175829.6995.8
Work Order02-13-20
Work Began02-17-20
Work Completed
Time Computed02-17-20
Contract Working Days366
Addl Days Granted366
Working Days Charged623
Percent Time Used85
Contractor(s)
JAMES EDWARD MOORE
SUBCONTRACTOR(S) FOR CCSJ: 6347-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08190602
Totals183530.000.00175829.6995.8

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6349-38-001
Proj IDRMC - 634938001
Work TypeLARGE SIGN REPLACEMENT
 
0.001327750.00119532.3636.4
Work Order01-31-20
Work Began05-08-20
Work Completed
Time Computed02-01-20
Contract Working Days366
Addl Days Granted365
Working Days Charged639
Percent Time Used87
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6349-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11190601
Totals327750.000.00119532.3636.4

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6349-39-001
Proj IDRMC - 634939001
Work TypeLARGE SIGN REPLACEMENT
 
0.001318250.00210374.6466.1
Work Order11-04-19
Work Began05-05-20
Work Completed
Time Computed12-01-19
Contract Working Days366
Addl Days Granted365
Working Days Charged701
Percent Time Used95
Contractor(s)
SELECT MAINTENANCE, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6349-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10190601
Totals318250.0064908.64210374.6466.1

page 1 | page 2 | page 3 | page 4 | page 5