Monthly State Let Maintenance Report For Pharr District As Of Dec 12, 2017 Page 2 Of 3

Last Update: Tuesday, December 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ6286-48-001
Proj IDRMC - 628648001
Work TypePAVEMENT REPAIRS
 
0.0103599099.365947941.8299.9
Work Order07-13-15
Work Began00-00-00
Work Completed
Time Computed08-03-15
Contract Working Days220
Addl Days Granted220
Working Days Charged213
Percent Time Used48
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154207
Totals3599099.360.005947941.8299.9

CountyCAMERON
HighwayFM0106
From0.05 MI WEST OF ARROYO BLVD
ToROBERTSON RD
CSJ6287-23-001
Proj IDRMC - 628723001
Work TypeREHABILITATION
 
0.010482939.00375549.8478.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged102
Percent Time Used102
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6287-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174013
Totals482939.0091465.39375549.8478.0

CountyHIDALGO
HighwayIH0002
FromHIDALGO COUNTY
ToHIDALGO COUNTY
CSJ6288-85-001
Proj IDRMC - 628885001
Work TypeCLEANING AND SWEEPING, DEBRIS REMOVAL
 
0.010994971.601058101.6099.9
Work Order11-16-15
Work Began01-04-16
Work Completed
Time Computed01-01-16
Contract Working Days378
Addl Days Granted378
Working Days Charged414
Percent Time Used54
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154014
Totals994971.6057262.801058101.6099.9

CountyCAMERON
HighwayIH0069E
FromCAMERON COUNTY
ToTO IH 69E/IH 2 (US 77/US 83)
CSJ6288-87-001
Proj IDRMC - 628887001
Work TypeCLEANING AND SWEEPING, DEBRIS REMOVAL
 
0.010914541.60961170.0099.9
Work Order11-24-15
Work Began01-04-16
Work Completed
Time Computed01-01-16
Contract Working Days378
Addl Days Granted378
Working Days Charged470
Percent Time Used62
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154015
Totals914541.6041790.00961170.0099.9

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6291-59-001
Proj IDRMC - 629159001
Work TypePAVEMENT MARKINGS
 
0.0101338301.152034822.0799.9
Work Order03-15-16
Work Began03-15-16
Work Completed
Time Computed03-15-16
Contract Working Days120
Addl Days Granted120
Working Days Charged162
Percent Time Used67
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154211
Totals1338301.15203723.032034822.0799.9

CountyHIDALGO
HighwaySH0336
FromEDCOUCH, MISSION & PHARR MAINTENANCE
ToVARIOUS ROADWAYS (FM ROADS)
CSJ6291-90-001
Proj IDRMC - 629190001
Work TypeCLEANING & SWEEPING OF HIGHWAYS
 
0.0101215303.101272606.5099.9
Work Order12-09-15
Work Began01-11-16
Work Completed
Time Computed01-04-16
Contract Working Days420
Addl Days Granted420
Working Days Charged323
Percent Time Used38
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154215
Totals1215303.1047472.351272606.5099.9

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS
CSJ6295-89-001
Proj IDRMC - 629589001
Work TypeMAINTENANCE & REPAIR OF SAFETY LIGHTING
 
0.010353685.00395684.3099.9
Work Order04-04-16
Work Began04-04-16
Work Completed
Time Computed04-04-16
Contract Working Days220
Addl Days Granted110
Working Days Charged325
Percent Time Used98
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154217
Totals353685.000.00395684.3099.9

CountyCAMERON
HighwayFM1419
FromVARIOUS
ToVARIOUS
CSJ6295-90-001
Proj IDBPM - 629590001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010455673.00480626.7099.9
Work Order04-24-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days120
Addl Days Granted0
Working Days Charged99
Percent Time Used82
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174214
Totals455673.0014250.00480626.7099.9

CountyHIDALGO
HighwaySH0336
FromSH 336 OVER HACKNEY LAKE FLOODWAY
ToFM 2061 OVER MCALLEN LATERAL DRAIN
CSJ6295-91-001
Proj IDBPM - 629591001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.010344250.00146720.0042.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-19-17
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted15
Working Days Charged46
Percent Time Used48
Contractor(s)
VALLEY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174234
Totals344250.000.00146720.0042.6

CountyCAMERON
HighwaySH0004
From4,850 FT. EAST OF FM 1419
ToEND OF STATE MAINTENANCE
CSJ6295-93-001
Proj IDRMC - 629593001
Work TypeREHABILITATION ON SH 04
 
0.0103036343.552636381.6886.8
Work Order11-22-16
Work Began01-09-17
Work Completed
Time Computed01-02-17
Contract Working Days120
Addl Days Granted38
Working Days Charged149
Percent Time Used94
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164217
Totals3036343.550.002636381.6886.8

CountyCAMERON
HighwayBU0083S
FromVARIOUS LOCATIONS
ToCAMERON COUNTY (SAN BENITO/BROWNSVILLE)
CSJ6296-66-001
Proj IDRMC - 629666001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
0.010634812.75541222.0085.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-08-16
Work Completed
Time Computed00-00-00
Contract Working Days380
Addl Days Granted140
Working Days Charged446
Percent Time Used85
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154016
Totals634812.7524601.00541222.0085.2

CountyCAMERON
HighwayBU0077X
FromDISTRICT WIDE
ToVARIOUS
CSJ6296-77-001
Proj IDRMC - 629677001
Work TypeOVERLAY, PLANING AND PAVEMENT MARKINGS
 
0.0104207370.104303634.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-03-16
Work Began10-30-16
Work Completed
Time Computed10-31-16
Contract Working Days100
Addl Days Granted17
Working Days Charged114
Percent Time Used97
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164205
Totals4207370.100.004303634.4099.9

CountyHIDALGO
HighwayUS0281
FromVARIOUS LOCATIONS
ToIN PHARR DISTRICT
CSJ6296-78-001
Proj IDRMC - 629678001
Work TypeSEAL COAT
 
0.0102846120.052650914.6493.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-07-16
Work Began03-31-17
Work Completed
Time Computed04-01-17
Contract Working Days60
Addl Days Granted0
Working Days Charged35
Percent Time Used58
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6296-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164217
Totals2846120.050.002650914.6493.1

CountyHIDALGO
HighwayFM1015
FromHIDALGO COUNTY
ToZAPATA COUNTY
CSJ6296-79-001
Proj IDRMC - 629679001
Work TypeACP OVERLAY WORK
 
0.0104485273.801594850.1735.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-13-17
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged12
Percent Time Used15
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174209
Totals4485273.801594850.171594850.1735.5

CountyHIDALGO
HighwayIH0069C
FromVARIUOS LOCATIONS
ToDISTRICT WIDE
CSJ6306-96-001
Proj IDRMC - 630696001
Work TypeCRACK SEAL
 
0.010436478.00410719.8094.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-03-16
Work Began02-13-17
Work Completed
Time Computed01-30-17
Contract Working Days50
Addl Days Granted0
Working Days Charged47
Percent Time Used94
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6306-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164018
Totals436478.000.00410719.8094.0

CountyHIDALGO
HighwayFM0490
FromHIDALGO COUNTY
ToVARIOUS ROADWAYS
CSJ6309-44-001
Proj IDRMC - 630944001
Work TypeFM MOWING
 
0.010522619.67342283.9765.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-06-17
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged28
Percent Time Used18
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6309-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164220
Totals522619.670.00342283.9765.4

CountyCAMERON
HighwayFM1847
FromCAMERON_COUNTY
ToWILLACY COUNTY
CSJ6309-45-001
Proj IDRMC - 630945001
Work TypeFM MOWING
 
0.010576600.95384333.6166.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-06-17
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged19
Percent Time Used12
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6309-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164219
Totals576600.950.00384333.6166.6

CountyCAMERON
HighwayUS0083
FromVARIOUS HIGHWAYS IN PHARR DISTRICT
ToVARIOUS HIGHWAYS IN PHARR DISTRICT
CSJ6316-29-001
Proj IDRMC - 631629001
Work TypeDEBRIS REMOVAL AND DISPOSAL
 
0.001599300.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
T.F.R. ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174216
Totals599300.000.000.000.0

CountyHIDALGO
HighwayFM1426
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ6316-43-001
Proj IDRMC - 631643001
Work TypeSEAL COAT
 
0.0102005741.239500.000.4
Work Order11-10-17
Work Began00-00-00
Work Completed
Time Computed11-30-17
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09174014
Totals2005741.239500.009500.000.4

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6321-71-001
Proj IDRMC - 632171001
Work TypePAVEMENT REPAIR
 
0.0104016934.130.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174219
Totals4016934.130.000.000.0

page 1 | page 2 | page 3