Monthly State Let Maintenance Report For San Antonio District As Of Jan 16, 2020 Page 1 Of 3

Last Update: Friday, January 17, 2020
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
Highway0000000
From4615 NW LOOP 410
ToSAN ANTONIO TX 78229
CSJ4704-01-595
Proj IDCBC - 470401595
Work TypeRENOVATION OR REPAIR
 
0.0012038650.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
QA CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-595
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164224
Totals2038650.000.000.000.0

CountyBEXAR
Highway0000000
From4615 N. W. LOOP 410 SAN ANTONIO, TEXAS
To4615 N. W. LOOP 410 SAN ANTONIO, TEXAS
CSJ4704-01-602
Proj IDCBC - 470401602
Work TypeRENVOATION OR REPAIR
 
0.001477770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SECURITAS ELECTRONIC SECURITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-602
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164223
Totals477770.000.000.000.0

CountyUVALDE
Highway0000000
From2231 US 90 WEST
ToUVALDE TX 78801
CSJ4704-01-724
Proj IDCBC - 470401724
Work TypeRENOVATION OR REPAIR
 
0.001337200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRIGGS BROTHERS ENTERPRISES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-724
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164221
Totals337200.000.000.000.0

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6311-41-001
Proj IDRMC - 631141001
Work TypeROUTINE MAINTENANCE
 
0.00114068094.0019369135.8499.9
Work Order03-23-17
Work Began04-04-17
Work Completed
Time Computed04-01-17
Contract Working Days730
Addl Days Granted731
Working Days Charged1,005
Percent Time Used68
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174013
Totals14068094.00981383.4319369135.8499.9

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6311-42-001
Proj IDRMC - 631142001
Work TypeROUTINE MAINTENANCE
 
0.00112422429.3220501923.60100.0
Work Order03-23-17
Work Began04-07-17
Work Completed11-22-19
Time Computed04-01-17
Contract Working Days730
Addl Days Granted731
Working Days Charged1,005
Percent Time Used68
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174005
Totals12422429.32624290.0920501923.60100.0

CountyCOMAL
HighwayIH0035
FromIH 35 IN COMAL, GUADALUPE AND
ToBEXAR COUNTIES
CSJ6311-43-001
Proj IDRMC - 631143001
Work TypeROUTINE MAINTENANCE
 
0.0013586599.592847793.8479.4
Work Order03-21-17
Work Began04-01-17
Work Completed
Time Computed04-01-17
Contract Working Days730
Addl Days Granted731
Working Days Charged1,005
Percent Time Used68
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174222
Totals3586599.5982123.612847793.8479.4

CountyCOMAL
HighwaySH0046
FromVARIOUS LOCATIONS IN
ToTHE SAN ANTONIO DISTRICT
CSJ6322-29-001
Proj IDRMC - 632229001
Work TypeGUARDRAL REPAIR
 
0.0012123690.001883074.4988.6
Work Order03-14-18
Work Began03-22-18
Work Completed
Time Computed03-22-18
Contract Working Days730
Addl Days Granted0
Working Days Charged634
Percent Time Used86
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184014
Totals2123690.0059431.631883074.4988.6

CountyATASCOSA
HighwayIH0037
FromVARIOUS LOCATIONS IN
ToATASCOSA COUNTY
CSJ6325-77-001
Proj IDRMC - 632577001
Work TypeMOWING AND LITTER REMOVAL
 
0.001356910.00260024.0072.8
Work Order06-11-18
Work Began06-15-18
Work Completed
Time Computed06-15-18
Contract Working Days192
Addl Days Granted0
Working Days Charged64
Percent Time Used33
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184015
Totals356910.000.00260024.0072.8

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN FRIO, ATASCOSA
ToAND LASALLE COUNTIES
CSJ6325-79-001
Proj IDRMC - 632579001
Work TypeMOWING AND LITTER REMOVAL
 
0.001420886.40369121.3887.7
Work Order06-05-18
Work Began06-18-18
Work Completed
Time Computed06-18-18
Contract Working Days184
Addl Days Granted0
Working Days Charged48
Percent Time Used26
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6325-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184016
Totals420886.4053604.58369121.3887.7

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToSAN ANTONIO DISTRICT
CSJ6325-85-001
Proj IDRMC - 632585001
Work TypePAVEMENT REPAIR
 
0.0015251020.506686947.8099.9
Work Order02-22-18
Work Began03-02-18
Work Completed
Time Computed03-02-18
Contract Working Days365
Addl Days Granted171
Working Days Charged535
Percent Time Used99
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6325-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184213
Totals5251020.500.006686947.8099.9

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6326-45-001
Proj IDRMC - 632645001
Work TypePAV MARKINGS & MRKRS CENTERLINE TEXTURE
 
0.0011813510.703367983.4999.9
Work Order04-05-18
Work Began04-06-18
Work Completed
Time Computed04-06-18
Contract Working Days365
Addl Days Granted365
Working Days Charged635
Percent Time Used86
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184208
Totals1813510.70188165.003367983.4999.9

CountyBEXAR
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6329-90-001
Proj IDRMC - 632990001
Work TypeCALL OUT TRAFFIC CONTROL
 
0.0011647766.501932532.4899.9
Work Order10-25-18
Work Began11-02-18
Work Completed
Time Computed11-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged362
Percent Time Used99
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09184025
Totals1647766.500.001932532.4899.9

CountyFRIO
HighwayIH0035
FromVARIOUS
ToVARIOUS
CSJ6329-91-001
Proj IDRMC - 632991001
Work TypeCALL OUT TRAFFIC CONTROL
 
0.0011161755.001483438.7399.9
Work Order11-29-18
Work Began12-01-18
Work Completed
Time Computed12-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09184026
Totals1161755.000.001483438.7399.9

CountyBEXAR
HighwayIH0410
FromIH 410 AT
ToWETMORE_ROAD
CSJ6331-70-001
Proj IDRMC - 633170001
Work TypeRIPRAP
 
0.001371427.00480961.4499.9
Work Order06-17-19
Work Began06-24-19
Work Completed
Time Computed06-24-19
Contract Working Days67
Addl Days Granted0
Working Days Charged95
Percent Time Used141
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6331-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03194221
Totals371427.000.00480961.4499.9

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6331-75-001
Proj IDRMC - 633175001
Work TypePAV MARKINGS & MRKRS CENTERLINE TEXTURE
 
0.0011529778.822512324.8499.9
Work Order09-10-18
Work Began09-17-18
Work Completed
Time Computed09-17-18
Contract Working Days365
Addl Days Granted365
Working Days Charged471
Percent Time Used64
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6331-75-001
BRYDL CONTRACTING, INC. (5.71)
Contract #07184017
Totals1529778.82167035.272512324.8499.9

CountyBEXAR
HighwayFM2696
FromFM 2696
To0.58 MI N. OF WURZBACH PKWY
CSJ6332-26-001
Proj IDRMC - 633226001
Work TypeRETAINING WALL REPAIR
 
0.001389024.00348989.0092.2
Work Order00-00-00
Work Began08-22-19
Work Completed
Time Computed07-16-19
Contract Working Days35
Addl Days Granted0
Working Days Charged52
Percent Time Used148
Contractor(s)
HAYWARD BAKER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6332-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05194003
Totals389024.0092641.90348989.0092.2

CountyBEXAR
HighwaySL0353
FromSL 0353
ToAT INDIAN CREEK
CSJ6332-51-001
Proj IDBPM - 633251001
Work TypeBRIDGE PM PROJECT
 
0.001549622.62618071.33100.0
Work Order07-23-19
Work Began07-25-19
Work Completed01-09-20
Time Computed07-25-19
Contract Working Days32
Addl Days Granted0
Working Days Charged52
Percent Time Used162
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6332-51-001
GEOSOURCE, INC. (1.35)
HIGHWAY PAVEMENT SPECIALTIES, INC. (1.65)
INTERSTATE BARRICADES & MARKINGS, INC. (2.27)
Contract #06194017
Totals549622.623680.00618071.33100.0

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToGUADALUPE COUNTY
CSJ6338-00-001
Proj IDRMC - 633800001
Work TypeMOWING HWY ROW
 
0.001601862.00199563.9933.1
Work Order07-09-19
Work Began06-25-19
Work Completed
Time Computed07-25-19
Contract Working Days211
Addl Days Granted0
Working Days Charged42
Percent Time Used19
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6338-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194220
Totals601862.003630.00199563.9933.1

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToKERR COUNTY
CSJ6338-01-001
Proj IDRMC - 633801001
Work TypeMOWING AND LITTER REMOVAL
 
0.001656697.00123689.0018.8
Work Order03-25-19
Work Began04-01-19
Work Completed
Time Computed04-01-19
Contract Working Days200
Addl Days Granted0
Working Days Charged19
Percent Time Used9
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6338-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194222
Totals656697.000.00123689.0018.8

CountyMEDINA
HighwayUS0090
FromVARIOUS LOCATIONS IN MEDINA, ATASCOSA
ToAND FRIO COUNTIES
CSJ6338-02-001
Proj IDRMC - 633802001
Work TypeMOWING AND LITTER REMOVAL
 
0.001665750.00217698.0032.6
Work Order05-30-19
Work Began06-13-19
Work Completed
Time Computed06-13-19
Contract Working Days239
Addl Days Granted0
Working Days Charged14
Percent Time Used5
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6338-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194223
Totals665750.00109965.00217698.0032.6