Monthly State Let Maintenance Report For San Antonio District As Of Aug 23, 2019 Page 1 Of 2

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
Highway0000000
From4615 NW LOOP 410
ToSAN ANTONIO TX 78229
CSJ4704-01-595
Proj IDCBC - 470401595
Work TypeRENOVATION OR REPAIR
 
0.0012038650.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
QA CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-595
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164224
Totals2038650.000.000.000.0

CountyBEXAR
Highway0000000
From4615 N. W. LOOP 410 SAN ANTONIO, TEXAS
To4615 N. W. LOOP 410 SAN ANTONIO, TEXAS
CSJ4704-01-602
Proj IDCBC - 470401602
Work TypeRENVOATION OR REPAIR
 
0.001477770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SECURITAS ELECTRONIC SECURITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-602
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164223
Totals477770.000.000.000.0

CountyUVALDE
Highway0000000
From2231 US 90 WEST
ToUVALDE TX 78801
CSJ4704-01-724
Proj IDCBC - 470401724
Work TypeRENOVATION OR REPAIR
 
0.001337200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRIGGS BROTHERS ENTERPRISES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-724
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164221
Totals337200.000.000.000.0

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6311-41-001
Proj IDRMC - 631141001
Work TypeROUTINE MAINTENANCE
 
0.00114068094.0015635674.1799.9
Work Order03-23-17
Work Began04-04-17
Work Completed
Time Computed04-01-17
Contract Working Days730
Addl Days Granted731
Working Days Charged852
Percent Time Used58
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174013
Totals14068094.00579278.0015635674.1799.9

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6311-42-001
Proj IDRMC - 631142001
Work TypeROUTINE MAINTENANCE
 
0.00112422429.3216928558.1999.9
Work Order03-23-17
Work Began04-07-17
Work Completed
Time Computed04-01-17
Contract Working Days730
Addl Days Granted731
Working Days Charged852
Percent Time Used58
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174005
Totals12422429.32583041.4816928558.1999.9

CountyCOMAL
HighwayIH0035
FromIH 35 IN COMAL, GUADALUPE AND
ToBEXAR COUNTIES
CSJ6311-43-001
Proj IDRMC - 631143001
Work TypeROUTINE MAINTENANCE
 
0.0013586599.592357832.1465.7
Work Order03-21-17
Work Began04-01-17
Work Completed
Time Computed04-01-17
Contract Working Days730
Addl Days Granted731
Working Days Charged852
Percent Time Used58
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174222
Totals3586599.59175702.512357832.1465.7

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6316-99-001
Proj IDRMC - 631699001
Work TypePAVEMENT REPAIR
 
0.0012345937.824700377.92100.0
Work Order02-09-18
Work Began05-02-18
Work Completed04-01-19
Time Computed02-20-18
Contract Working Days365
Addl Days Granted0
Working Days Charged98
Percent Time Used26
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-99-001
INTERSTATE BARRICADES & MARKINGS, INC. (4.04)
Contract #08174011
Totals2345937.820.004700377.92100.0

CountyCOMAL
HighwaySH0046
FromVARIOUS LOCATIONS IN
ToTHE SAN ANTONIO DISTRICT
CSJ6322-29-001
Proj IDRMC - 632229001
Work TypeGUARDRAL REPAIR
 
0.0012123690.001536158.2572.3
Work Order03-14-18
Work Began03-22-18
Work Completed
Time Computed03-21-18
Contract Working Days730
Addl Days Granted0
Working Days Charged481
Percent Time Used65
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184014
Totals2123690.00185108.941536158.2572.3

CountyATASCOSA
HighwayIH0037
FromVARIOUS LOCATIONS IN
ToATASCOSA COUNTY
CSJ6325-77-001
Proj IDRMC - 632577001
Work TypeMOWING AND LITTER REMOVAL
 
0.001356910.00246496.0069.0
Work Order06-11-18
Work Began06-15-18
Work Completed
Time Computed06-15-18
Contract Working Days192
Addl Days Granted0
Working Days Charged61
Percent Time Used31
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184015
Totals356910.0071053.00246496.0069.0

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN FRIO, ATASCOSA
ToAND LASALLE COUNTIES
CSJ6325-79-001
Proj IDRMC - 632579001
Work TypeMOWING AND LITTER REMOVAL
 
0.001420886.40315516.8074.9
Work Order06-05-18
Work Began06-18-18
Work Completed
Time Computed06-18-18
Contract Working Days184
Addl Days Granted0
Working Days Charged44
Percent Time Used23
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6325-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184016
Totals420886.400.00315516.8074.9

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToSAN ANTONIO DISTRICT
CSJ6325-85-001
Proj IDRMC - 632585001
Work TypePAVEMENT REPAIR
 
0.0015251020.506578619.9299.9
Work Order02-22-18
Work Began03-02-18
Work Completed
Time Computed03-02-18
Contract Working Days365
Addl Days Granted171
Working Days Charged502
Percent Time Used93
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6325-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184213
Totals5251020.50750190.976578619.9299.9

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6326-45-001
Proj IDRMC - 632645001
Work TypePAV MARKINGS & MRKRS CENTERLINE TEXTURE
 
0.0011813510.702302998.3999.9
Work Order04-05-18
Work Began04-06-18
Work Completed
Time Computed04-06-18
Contract Working Days365
Addl Days Granted365
Working Days Charged482
Percent Time Used66
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184208
Totals1813510.70130565.002302998.3999.9

CountyBEXAR
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6329-90-001
Proj IDRMC - 632990001
Work TypeCALL OUT TRAFFIC CONTROL
 
0.0011647766.501311814.4979.6
Work Order10-25-18
Work Began11-02-18
Work Completed
Time Computed11-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged285
Percent Time Used78
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09184025
Totals1647766.50279068.031311814.4979.6

CountyFRIO
HighwayIH0035
FromVARIOUS
ToVARIOUS
CSJ6329-91-001
Proj IDRMC - 632991001
Work TypeCALL OUT TRAFFIC CONTROL
 
0.0011161755.001006084.6986.6
Work Order11-29-18
Work Began12-01-18
Work Completed
Time Computed12-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09184026
Totals1161755.00162210.771006084.6986.6

CountyBEXAR
HighwayIH0410
FromIH 410 AT
ToWETMORE_ROAD
CSJ6331-70-001
Proj IDRMC - 633170001
Work TypeRIPRAP
 
0.001371427.0072927.3019.6
Work Order06-17-19
Work Began06-24-19
Work Completed
Time Computed06-24-19
Contract Working Days67
Addl Days Granted0
Working Days Charged23
Percent Time Used34
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6331-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03194221
Totals371427.0071427.3072927.3019.6

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6331-75-001
Proj IDRMC - 633175001
Work TypePAV MARKINGS & MRKRS CENTERLINE TEXTURE
 
0.0011529778.821466832.7595.8
Work Order09-10-18
Work Began09-17-18
Work Completed
Time Computed09-17-18
Contract Working Days365
Addl Days Granted0
Working Days Charged318
Percent Time Used87
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6331-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184017
Totals1529778.82218976.161466832.7595.8

CountyBEXAR
HighwayFM2696
FromFM 2696
To0.58 MI N. OF WURZBACH PKWY
CSJ6332-26-001
Proj IDRMC - 633226001
Work TypeRETAINING WALL REPAIR
 
0.001389024.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HAYWARD BAKER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6332-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05194003
Totals389024.000.000.000.0

CountyBEXAR
HighwaySL0353
FromSL 0353
ToAT INDIAN CREEK
CSJ6332-51-001
Proj IDBPM - 633251001
Work TypeBRIDGE PM PROJECT
 
0.001549622.62111166.9420.2
Work Order07-23-19
Work Began07-25-19
Work Completed
Time Computed07-25-19
Contract Working Days32
Addl Days Granted0
Working Days Charged5
Percent Time Used15
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6332-51-001
GEOSOURCE, INC. (1.35)
HIGHWAY PAVEMENT SPECIALTIES, INC. (1.65)
INTERSTATE BARRICADES & MARKINGS, INC. (2.27)
Contract #06194017
Totals549622.62111166.94111166.9420.2

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToGUADALUPE,ATASCOSA,MEDINA AND FRIO CO.
CSJ6334-07-001
Proj IDRMC - 633407001
Work TypeBEBRIS REMOVAL
 
0.001350580.00472140.2599.9
Work Order00-00-00
Work Began11-16-18
Work Completed
Time Computed11-14-18
Contract Working Days365
Addl Days Granted0
Working Days Charged285
Percent Time Used78
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09184223
Totals350580.0059257.50472140.2599.9

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToGUADALUPE COUNTY
CSJ6338-00-001
Proj IDRMC - 633800001
Work TypeMOWING HWY ROW
 
0.001601862.0019950.003.3
Work Order07-09-19
Work Began06-25-19
Work Completed
Time Computed07-25-19
Contract Working Days211
Addl Days Granted0
Working Days Charged6
Percent Time Used2
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6338-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194220
Totals601862.0019950.0019950.003.3