Monthly Local Let Maintenance Report For Abilene District As Of Jul 14, 2017 Page 3 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySTONEWALL
HighwayUS0380
FromVARIOUS LOCATIONS
ToIN STONEWALL COUNTY
CSJ6311-09-001
Proj IDRMC - 631109001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.01096096.0035308.0036.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged7
Percent Time Used23
Contractor(s)
KENNETH THOMASON
SUBCONTRACTOR(S) FOR CCSJ: 6311-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170812
Totals96096.0035308.0035308.0036.7

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS
ToIN TAYLOR COUNTY(RURAL)
CSJ6311-10-001
Proj IDRMC - 631110001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010226756.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days47
Addl Days Granted0
Working Days Charged8
Percent Time Used17
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6311-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170813
Totals226756.200.000.000.0

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS
ToIN TAYLOR COUNTY(URBAN)
CSJ6311-11-001
Proj IDRMC - 631111001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010458235.3849273.0310.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days144
Addl Days Granted0
Working Days Charged8
Percent Time Used5
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170814
Totals458235.3849273.0349273.0310.7

CountyNOLAN
HighwayIH0020
FromVARIOUS LOCATIONS
ToIN NOLAN COUNTY
CSJ6313-90-001
Proj IDRMC - 631390001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010371295.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days97
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170809
Totals371295.000.000.000.0

CountyTAYLOR
HighwayIH0020
FromTAYLOR, JONES AND
ToNOLAN COUNTIES
CSJ6315-03-001
Proj IDSUP - 631503001
Work TypeSTATE USE LITTER PICKUP
 
0.010181363.0069903.1938.5
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged137
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6315-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170830
Totals181363.0018365.2069903.1938.5

CountyHOWARD
HighwayIH0020
FromVARIOUS LOCATIONS IN HOWARD,
ToMITCHELL AND SCURRY COUNTIES
CSJ6315-04-001
Proj IDSUP - 631504001
Work TypeSTATE USE LITTER REMOVAL AND PICKUP
 
0.01094740.4044790.2047.2
Work Order02-01-17
Work Began00-00-00
Work Completed
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged129
Percent Time Used35
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6315-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170831
Totals94740.400.0044790.2047.2

CountyCALLAHAN
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToCALLAHAN COUNTY
CSJ6315-54-001
Proj IDSUP - 631554001
Work TypeLITTER PICKUP AND DISPOSAL
 
0.01065871.0024479.0037.1
Work Order02-16-17
Work Began02-23-17
Work Completed
Time Computed02-16-17
Contract Working Days365
Addl Days Granted0
Working Days Charged128
Percent Time Used35
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170830
Totals65871.003783.0024479.0037.1

CountyBORDEN
HighwayUS0180
FromVARIOUS LOCATIONS
ToIN BORDEN, KENT, AND SCURRY COUNTIES
CSJ6316-55-001
Proj IDRMC - 631655001
Work TypePICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.10041763.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-17
Work Began00-00-00
Work Completed
Time Computed06-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS LAND & MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6316-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170801
Totals41763.520.000.000.0

CountyMITCHELL
HighwayIH0020
FromMITCHELL COUNTY AND
ToHOWARD COUNTY
CSJ6316-95-001
Proj IDSUP - 631695001
Work TypeSTATE USE PICNIC AREA MAINTENANCE
 
0.010126240.0010355.018.2
Work Order04-01-17
Work Began04-01-17
Work Completed
Time Computed04-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged31
Percent Time Used4
Contractor(s)
TIBH INDUSTRIES, INC.
MARIAN MOSS ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6316-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03170830
Totals126240.005425.0110355.018.2

CountySHACKELFORD
HighwayUS0283
FromVARIOUS LOCATIONS IN SHACKELFORD
ToVARIOUS LOCATIONS IN JONES
CSJ6319-32-001
Proj IDSUP - 631932001
Work TypePICNIC AREA MAINTENANCE
 
0.00167566.405778.008.5
Work Order06-01-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days375
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6319-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170830
Totals67566.405778.005778.008.5

page 1 | page 2 | page 3