Monthly State Let Construction Report For Atlanta District As Of Jul 13, 2015 Page 2 Of 3

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCASS
Highway US 59
From AT INTERSECTION OF FM 3129
To .
CSJ 0218-03-076
Proj ID STP 1102(039)SB
Work Type GRADING, STRUCTURES, BASE & SURFACING
 
3.241 15425865.78 79429.60 16432800.57 99.9
CountyUPSHUR
Highway US 271
From AT INTERSECTION OF SH 155(S)
To .
CSJ 0248-05-055
Proj ID STP 1102(039)SB
Work Type GRADING, STRUCTURES, BASE & SURFACING
 
0.304 4690776.56 2000.00 4675478.69 99.8
CountyUPSHUR
Highway US 271
From AT INTERSECTION OF SH 155(S)
To .
CSJ 0248-05-058
Proj ID STP 1102(041)
Work Type INSTALL TREES, SHRUBS AND IRRIGATION
 
0.304 73847.00 0.00 75589.00 99.9
Work Order 08-11-11
Work Began 09-01-11
Work Completed  
Time Computed 09-01-11
Contract Working Days 770
Addl Days Granted 159
Working Days Charged 836
Percent Time Used 89
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0248-05-055
STRIPING TECHNOLOGY, L.P.(5.10%)
DUSTROL, INC.(0.07%)
HIGHWAY TECHNOLOGIES, INC. (0.68%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.63%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.34%)
ATS DRILLING, L.P. (0.48%)
CARTHAGE DRILLING, INC.(0.15%)
R & R TELCO ENTERPRISES, INC.(0.03%)
MAC TRANSPORTATION, LTD, L.L.P.(3.93%)
RICK HARGROVE TRUCKING (3.93%)
TEX OP CONSTRUCTION, LP(0.27%)
DUSTIN ALLEN, INC. (0.73%)
AQUA BORE(0.01%)
WEBBER BARRIER SERVICES, INC.(0.29%)
SCOTT DERR PAINTING CO, LLC(0.11%)
SOUTHEAST GRINDING & GROOVING, LLC (0.02%)
COKER TREE SERVICE (0.01%)
PENHALL COMPANY(0.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.03%)
AARON CONCRETE CONTRACTORS, L.P. (0.98%)
INDUS CONSTRUCTION, L.P. (0.06%)
Contract # 06113017
Totals 20190489.34 81429.60 21183868.26 99.9

CountyCASS
Highway US 59
From 0.1 MI N OF FM 3129
To BOWIE C/L (NORTHBOUND LANES ONLY)
CSJ 0218-03-083
Proj ID NH 1502(134)
Work Type PLANING, ACP, CPCD & PAV MARKINGS
 
2.225 5059588.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-15-15
Work Began 00-00-00
Work Completed  
Time Computed 08-15-15
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
INTERSTATE HIGHWAY CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0218-03-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153211
Totals 5059588.95 0.00 0.00 0.0

CountyCASS
Highway US 59
From AT BLACK BAYOU
To .
CSJ 0218-04-114
Proj ID BR 1502(419)
Work Type BRIDGE RAIL & MBGF
 
0.198 755932.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0218-04-114
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153214
Totals 755932.75 0.00 0.00 0.0

CountyTITUS
Highway US 271
From CAMP C/L
To 0.3 MI. SOUTH OF FM 3417
CSJ 0248-01-070
Proj ID STP 2014(031)
Work Type ACP SURF, MBGF & PAV MARKS
 
1.423 779081.21 0.00 690770.05 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-13-13
Work Began 09-22-14
Work Completed 02-11-15
Time Computed 04-12-14
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 108
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0248-01-070
STRIPING TECHNOLOGY, L.P.(2.51%)
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
HIGHWAY 19 CONSTRUCTION, LLC (0.84%)
DUSTIN ALLEN, INC. (1.88%)
DUSTROL, INC.(1.09%)
VANCE BROTHERS, INC. (6.61%)
TEX OP CONSTRUCTION, LP(1.15%)
Contract # 09133232
Totals 779081.21 0.00 690770.05 100.0

CountyMORRIS
Highway SH 77
From US 259
To 0.3 MI. WEST OF US 67
CSJ 0277-01-028
Proj ID C 277-1-28
Work Type GR, BASE, SURFACING & PVMT MARKERS
 
7.726 2668954.21 0.00 2783221.75 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-17-12
Work Began 10-03-12
Work Completed 03-30-15
Time Computed 10-01-12
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 70
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0277-01-028
SOUTHWEST ENVIRONMENT SERVICES LLC (1.17%)
STRIPING TECHNOLOGY, L.P.(3.05%)
BAHENA CONSTRUCTION CO.,INC. (0.56%)
PANOLA SIGN & BARRICADE, INC.(0.42%)
RK HALL, LLC (1.95%)
Contract # 08123230
Totals 2668954.21 0.00 2783221.75 100.0

CountyCASS
Highway SH 77
From 0.2 MILE WEST OF FM 251
To 0.3 MILE EAST OF FM 1841
CSJ 0278-01-044
Proj ID STP 2015(702)
Work Type GR, STR, BASE, C & G, ACP, ILL & PVT
 
1.098 8162284.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-15
Work Began 00-00-00
Work Completed  
Time Computed 09-19-15
Contract Working Days 370
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0278-01-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153207
Totals 8162284.82 0.00 0.00 0.0

CountyUPSHUR
Highway US 259
From FM 557
To GREGG C/L
CSJ 0392-02-086
Proj ID STP 2014(500)HESG
Work Type TEXTURIZE SHOULDERS & CL TEXTURING
 
43.744 1748201.24 0.00 1610147.86 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 06-20-14
Work Completed 02-11-15
Time Computed 06-10-14
Contract Working Days 155
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 78
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0392-02-086
BRYDL CONTRACTING, INC.(1.17%)
COWBELL TRAFFIC SERVICES, INC. (1.64%)
Contract # 03143029
Totals 1748201.24 0.00 1610147.86 100.0

CountyUPSHUR
Highway US 259
From AT INTERSECTION OF SH 155
To .
CSJ 0392-02-088
Proj ID STP 1402(101)
Work Type INSTALL TREES AND IRRIGATION
 
0.680 135934.98 1000.00 129234.98 95.0
Work Order 09-22-14
Work Began 11-10-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 109
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 18
Contractor(s)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0392-02-088
FLEX SUPPLY, LLC (6.27%)
SOUTH TEXAS ILLUMINATION, LLC(3.08%)
Contract # 08143244
Totals 135934.98 1000.00 129234.98 95.0

CountyUPSHUR
Highway SH 154
From 0.7 MI WEST OF US 259
To US 259
CSJ 0402-02-024
Proj ID C 402-2-24
Work Type SUBGR WID, SURF, STRS, PVT MRKS
 
0.666 1272043.75 0.00 1311689.01 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-18-14
Work Began 03-11-14
Work Completed 03-30-15
Time Computed 03-11-14
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 77
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0402-02-024
PANOLA SIGN & BARRICADE, INC.(0.50%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.85%)
STRIPING TECHNOLOGY, L.P.(2.96%)
RK HALL, LLC ( 17.04%)
Contract # 10133024
Totals 1272043.75 0.00 1311689.01 100.0

CountyHARRISON
Highway IH 20
From AT FM 450 UNDERPASS
To .
CSJ 0495-08-086
Proj ID BR 2013(619)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.010 4874784.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153256
Totals 4874784.26 0.00 0.00 0.0

CountyHARRISON
Highway IH 20
From 0.5 MI. W. OF SH 43
To EAST END OF EIGHT MILE CREEK_BRIDGE
CSJ 0495-09-049
Proj ID IM 0207(072)
Work Type PLANING, CONC PV REP, ACP & PAV MRKS
 
6.923 7961243.19 0.00 6934893.75 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-13
Work Began 05-19-14
Work Completed 02-19-15
Time Computed 03-04-14
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 80
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-09-049
PANOLA SIGN & BARRICADE, INC.(0.21%)
O. TREVINO CONSTRUCTION, LLC (4.57%)
STRIPING TECHNOLOGY, L.P.(1.68%)
VANCE BROTHERS, INC. (6.81%)
COWBELL TRAFFIC SERVICES, INC. (0.24%)
DUSTIN ALLEN, INC. (2.64%)
EAST TEXAS BRIDGE, INC.(1.21%)
Contract # 09133020
Totals 7961243.19 0.00 6934893.75 100.0

CountyUPSHUR
Highway SH 155
From AT SABINE RIVER & SABINE RIVER RELI
To SOUTH OF BIG SANDY
CSJ 0520-02-037
Proj ID BR 2013(823)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.692 12644943.11 177477.38 7239821.15 57.2
CountyUPSHUR
Highway SH 155
From AT UNION PACIFIC RAILROAD OVERPASS
To S. OF BIG SANDY
CSJ 0520-02-038
Proj ID BR 2013(823)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.117 2277242.66 4052.88 642992.24 28.2
CountyUPSHUR
Highway SH 155
From SABINE RIVER RELIEF BRIDGE
To U.P.R.R. OVERPASS
CSJ 0520-02-039
Proj ID C 520-2-39
Work Type GR, STR, BASE, SURF
 
1.274 3947700.40 29602.24 1449569.21 36.7
Work Order 09-09-13
Work Began 09-30-13
Work Completed  
Time Computed 09-30-13
Contract Working Days 780
Addl Days Granted 0
Working Days Charged 298
Percent Time Used 38
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0520-02-037
MAC TRANSPORTATION, LTD, L.L.P.(6.50%)
STRIPING TECHNOLOGY, L.P.(1.11%)
AMERICAN REMEDIATION OPTIONS, INC. (0.56%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.31%)
ODUM SERVICES, L.P.(1.00%)
PANOLA SIGN & BARRICADE, INC.(0.16%)
HIGHWAY 19 CONSTRUCTION, LLC (0.62%)
ATS DRILLING, INC. (7.12%)
MCL CONTRACTING, LLC (0.20%)
TEX OP CONSTRUCTION, LP(0.02%)
Contract # 07133204
Totals 18869886.17 211132.50 9332382.60 49.4

CountyUPSHUR
Highway SH 155
From 0.9 MILE SOUTH OF FM 1002
To US 80
CSJ 0520-02-054
Proj ID STP 2014(838)
Work Type ACP SURF & PAV MKS
 
1.510 788081.15 0.00 574805.77 72.9
Work Order 07-10-14
Work Began 09-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 79
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0520-02-054
BANNER SIGN & BARRICADE, INC. (HOOKS)(0.19%)
DUSTROL, INC.(0.62%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.63%)
STRIPING TECHNOLOGY, L.P.(3.67%)
LONGVIEW BRIDGE AND ROAD, LTD. ( 12.51%)
Contract # 06143041
Totals 788081.15 0.00 574805.77 72.9

CountyCASS
Highway FM 125
From SH 43
To LOUISIANA STATE LINE
CSJ 0546-09-039
Proj ID STP 1502(226)HES
Work Type GR, STR, BS, SURF, HFST & PAV MRKS
 
37.671 3490097.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 260
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-09-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153214
Totals 3490097.96 0.00 0.00 0.0

CountyTITUS
Highway IH 30
From FRANKLIN COUNTY LINE
To MORRIS COUNTY LINE
CSJ 0610-03-079
Proj ID NH 2015(407)
Work Type PAV REP, ACP SURFACING AND PAV MARK
 
97.964 33725327.54 1196968.90 4200861.50 12.4
Work Order 02-10-15
Work Began 04-15-15
Work Completed  
Time Computed 04-11-15
Contract Working Days 595
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 7
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-03-079
DUSTROL, INC.(3.91%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.33%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.32%)
DUSTIN ALLEN, INC. (3.58%)
STRIPE-A-ZONE, INC.(7.29%)
JM YANEZ CONSTRUCTION(1.60%)
SCR CONSTRUCTION CO., INC. (1.48%)
EAST TEXAS BRIDGE, INC.(9.22%)
STRAIGHT LINE SAWING & SEALING (0.36%)
SAMMY GIST ENTERPRISES, INC. (0.20%)
Contract # 12143202
Totals 33725327.54 1196968.90 4200861.50 12.4

CountyBOWIE
Highway IH 30
From SH 98
To SP 86
CSJ 0610-06-078
Proj ID IM 0303(126)
Work Type PAV REP, PLANING, ACP & PAV MRKS
 
17.707 8894155.74 1177871.31 7453331.17 83.8
Work Order 05-06-14
Work Began 07-08-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 113
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 96
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-06-078
SOUTHWEST ENVIRONMENT SERVICES LLC (0.02%)
COWBELL TRAFFIC SERVICES, INC. (0.13%)
DUSTROL, INC.(8.10%)
SCR CONSTRUCTION CO., INC. (8.95%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23%)
DUSTIN ALLEN, INC. (2.50%)
STRIPING TECHNOLOGY, L.P.(1.27%)
Contract # 04143025
Totals 8894155.74 1177871.31 7453331.17 83.8

CountyBOWIE
Highway IH 30 ETC
From AT US 59/71 (STATELINE) INTERCHANGE
To .
CSJ 0610-07-085
Proj ID IMD 0303(120)
Work Type REPLACE BRIDGE AND APPROACHES
 
9.080 153539064.68 0.00 160103327.24 99.9
Work Order 10-03-06
Work Began 10-17-06
Work Completed  
Time Computed 10-19-06
Contract Working Days 717
Addl Days Granted 98
Working Days Charged 815
Percent Time Used 100
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0610-07-085
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.41%)
RENAISSANCE CONTRACTORS PARTNERSHIP(3.44%)
ADVANCE CONSTRUCTION SERVICES, INC.(8.84%)
JACKSON LOGGING(0.03%)
W. W. FOUNDATION DRILLING, LTD.(3.32%)
CAPROCK SPECIALITY CONTRACTORS (0.20%)
DUSTROL, INC. (ROANOKE)(0.01%)
ODUM SERVICES, L.P.(0.63%)
GIBSON & ASSOCIATES, INC.(0.24%)
STRIPING TECHNOLOGY, L.P.(0.90%)
J & V COMMUNICATION SERVICES, INC. (5.32%)
CRAIG OLDEN, INC.(0.15%)
RG PAINTING(0.13%)
RK HALL, LLC ( 19.56%)
INDUS CONSTRUCTION, L.P. (0.74%)
QUALITY TRUCKING, LLC(0.00%)
RICK HARGROVE TRUCKING (0.16%)
CARTHAGE DRILLING, INC.(0.54%)
LIL DAN TRUCKING (0.16%)
INDUS CONSTRUCTION, L.P. (0.19%)
GREG'S TRUCKING(0.14%)
SHABUCK CONSTRUCTION (0.03%)
3-BAR-S CONSTRUCTION (0.05%)
HBL CONTRACTING, INC.(0.05%)
CODE J TRANSPORT, INC. (0.03%)
ROLL & ROCK(0.05%)
E. WALKER CONSTRUCTION CO., INC. (0.13%)
RK HALL, LLC (0.15%)
JODEEO TRUCKING(0.00%)
ADAMS EXCAVATION (0.00%)
RICK HARGROVE TRUCKING (0.05%)
TEC, INC.(0.04%)
WRIGHT BROTHERS EXCAVATING CO. (0.03%)
MIKE LEMLEY CONSTRUCTION (0.01%)
DAVID J. PICKETT (0.00%)
THOMAS HALL TRUCKING (0.01%)
THOMPSON HAULING (0.00%)
BELLEW TRUCKING(0.00%)
EXTREME TRUCKING LLC (0.06%)
RTI RELIABLE TRANSPORT, INC. (0.00%)
JODEEO TRUCKING(0.02%)
CODE J TRANSPORT, INC. (0.02%)
M-C TRUCKING LTD (0.02%)
M-C TRUCKING LTD (0.00%)
WEBBER BARRIER SERVICES, INC.(0.70%)
FRANK PEBBLES, INC.(0.00%)
H.O.W.B. TRANSPORTATION AND MATERIALS, LLC (0.00%)
XTREME TWIN CITY TRUCKING, INC.(0.00%)
H.O.W.B. TRANSPORTATION AND MATERIALS, LLC (0.08%)
RTI RELIABLE TRANSPORT, INC. (0.01%)
DUWAYNE PARKER (0.01%)
SCOTT DERR PAINTING CO (0.06%)
RIVER CITIES SAWING LLC(0.24%)
SEABERS SERVICES, L.L.C. (0.01%)
ENGINEERED EXPLOSIVE SERVICES(0.04%)
ATFH, INC. (0.01%)
KEVIN FATHERREE(0.01%)
KEVIN FATHERREE(0.01%)
DAVID DANIEL (0.01%)
JP TRUCKING(0.00%)
J W TRUCKING (0.01%)
J W TRUCKING (0.00%)
ROCKY'S TRUCKING (0.01%)
ROGER TIDWELL(0.01%)
WEAVER TRUCKING(0.01%)
MIKE MCREYNOLDS(0.01%)
M & J TRUCKING (0.01%)
LAFAYETTE TRUCKING (0.01%)
TYKES TRUCKING (0.01%)
TJT CONSTRUCTION (0.01%)
JM-A TRANSPORT (0.01%)
R & D TRUCKING (0.01%)
AMOS TRUCKING(0.01%)
ANDRE JONES(0.00%)
WILLIAMS EXCAVATING, LLC (0.03%)
ARNOLD TRUCKING, INC. (HUB)(0.02%)
RED RIVER HYDRO-SEEDING, INC.(0.43%)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.12%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.01%)
FIRST SERVE CONSTRUCTION, LLC(0.13%)
AMOS TRUCKING(0.01%)
ROCKY'S TRUCKING (0.01%)
RICK HARGROVE TRUCKING (0.00%)
3-BAR-S CONSTRUCTION (0.00%)
JP TRUCKING(0.00%)
RORIE STONE CONSTRUCTION, LLC(0.03%)
TX DOWN UNDER CONSTRUCTION LLC (0.00%)
H & N LANDSCAPING(0.00%)
TEX OP CONSTRUCTION, LP(0.01%)
CONCRETE CUTTING BY BOND (0.00%)
NIXON ENGINEERING, L.L.C.(0.07%)
TEXARKANA FENCE AND ACCESS CONTROL (0.05%)
W.O.E. CONSTRUCTION(0.08%)
GREEN ONSITE SERVICES(0.00%)
Contract # 07063001
Totals 153539064.68 0.00 160103327.24 99.9

CountyBOWIE
Highway IH 30
From AT FM 2253 UNDERPASS
To .
CSJ 0610-07-098
Proj ID STP 2013(843)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.010 3821270.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-30-15
Work Began 00-00-00
Work Completed  
Time Computed 08-30-15
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0610-07-098
MORRIS COUNTY CONTRACTORS, L.L.C.(5.81%)
TEXOP CONSTRUCTION (0.74%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.15%)
PENHALL COMPANY(0.19%)
RK HALL, LLC ( 14.06%)
PANOLA SIGN & BARRICADE, INC.(0.83%)
STRIPING TECHNOLOGY, L.P.(0.14%)
Contract # 05153012
Totals 3821270.50 0.00 0.00 0.0

CountyHARRISON
Highway FM 31
From 1.3 MI N OF PANOLA C/L
To PANOLA C/L
CSJ 0640-01-044
Proj ID STP 1502(054)
Work Type CEMENT TRT, FL BS, SURF & PAV MARKS
 
1.261 837048.73 343846.27 343846.27 41.0
Work Order 05-15-15
Work Began 06-03-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 11
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0640-01-044
SOUTHWEST ENVIRONMENT SERVICES LLC (0.17%)
PANOLA SIGN & BARRICADE, INC.(0.55%)
STRIPE-A-ZONE, INC.(1.99%)
Contract # 04153252
Totals 837048.73 343846.27 343846.27 41.0

CountyHARRISON
Highway FM 31
From INDIAN SPRINGS ROAD
To PANOLA C/L
CSJ 0640-01-047
Proj ID STP 2015(249)HESG
Work Type FLASH CHEV, TEXT SHLDR & CL TEXTURE
 
24.186 1234567.06 2990.50 1112823.81 90.1
Work Order 11-14-14
Work Began 01-26-15
Work Completed  
Time Computed 01-16-15
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 60
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0640-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143209
Totals 1234567.06 2990.50 1112823.81 90.1

page 1 | page 2 | page 3