Monthly State Let Construction Report For Atlanta District As Of Sep 15, 2016 Page 2 Of 2

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCASS
Highway FM 1399
From FM 250
To SH 8
CSJ 0546-08-011
Proj ID STP 2016(338)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
15.694 1162910.40 65150.34 650743.49 55.9
Work Order 12-21-15
Work Began 01-20-16
Work Completed  
Time Computed 01-20-16
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 68
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0546-08-011
N-LINE TRAFFIC MAINTENANCE, L.P. (1.16%)
SOUTHWEST ENVIRONMENT SERVICES LLC (4.54%)
DUSTIN ALLEN, INC. (4.76%)
Contract # 11153013
Totals 1162910.40 65150.34 650743.49 55.9

CountyCASS
Highway FM 125
From SH 43
To LOUISIANA STATE LINE
CSJ 0546-09-039
Proj ID STP 1502(226)HES
Work Type GR, STR, BS, SURF, HFST & PAV MRKS
 
37.671 3490097.96 1500.00 1136125.20 32.5
Work Order 08-13-15
Work Began 05-25-16
Work Completed  
Time Computed 09-12-15
Contract Working Days 260
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 15
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-09-039
POLY-CARB, INC.(3.69%)
PANOLA SIGN & BARRICADE, INC.(0.89%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.98%)
STRIPE-A-ZONE, INC.( 13.72%)
TX TINMAN ENTERPRISES, LLC.(5.00%)
Contract # 06153214
Totals 3490097.96 1500.00 1136125.20 32.5

CountyMARION
Highway SH 43
From AT BIG CYPRESS CREEK
To .
CSJ 0569-03-021
Proj ID STP 1602(314)
Work Type REHABILITATION OF EXISTING BRIDGE
 
0.339 1204182.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0569-03-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163037
Totals 1204182.24 0.00 0.00 0.0

CountyTITUS
Highway IH 30
From FRANKLIN COUNTY LINE
To MORRIS COUNTY LINE
CSJ 0610-03-079
Proj ID NH 2015(407)
Work Type PAV REP, ACP SURFACING AND PAV MARK
 
97.964 33725327.54 205695.00 27358611.21 81.1
Work Order 02-10-15
Work Began 04-15-15
Work Completed  
Time Computed 04-11-15
Contract Working Days 595
Addl Days Granted 0
Working Days Charged 286
Percent Time Used 48
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-03-079
DUSTROL, INC.(3.91%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.33%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.32%)
DUSTIN ALLEN, INC. (3.58%)
STRIPE-A-ZONE, INC.(7.29%)
JM YANEZ CONSTRUCTION(1.60%)
SCR CONSTRUCTION CO., INC. (1.48%)
EAST TEXAS BRIDGE, INC.(9.22%)
STRAIGHT LINE SAWING & SEALING (0.36%)
SAMMY GIST ENTERPRISES, INC. (0.20%)
BRYDL CONTRACTING, INC.(0.03%)
Contract # 12143202
Totals 33725327.54 205695.00 27358611.21 81.1

CountyBOWIE
Highway IH 30
From SH 98
To SP 86
CSJ 0610-06-078
Proj ID IM 0303(126)
Work Type PAV REP, PLANING, ACP & PAV MRKS
 
17.707 8894155.74 66742.41 8748099.39 98.8
Work Order 05-06-14
Work Began 07-08-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 113
Addl Days Granted 3
Working Days Charged 152
Percent Time Used 131
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-06-078
SOUTHWEST ENVIRONMENT SERVICES LLC (0.02%)
COWBELL TRAFFIC SERVICES, INC. (0.13%)
DUSTROL, INC.(8.10%)
SCR CONSTRUCTION CO., INC. (8.95%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23%)
DUSTIN ALLEN, INC. (2.50%)
STRIPING TECHNOLOGY, L.P.(1.27%)
STRAIGHT LINE SAWING & SEALING (0.36%)
Contract # 04143025
Totals 8894155.74 66742.41 8748099.39 98.8

CountyBOWIE
Highway IH 30
From AT FM 2253 UNDERPASS
To .
CSJ 0610-07-098
Proj ID STP 2013(843)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.010 3821270.50 132992.10 3350044.61 87.6
Work Order 06-30-15
Work Began 08-18-15
Work Completed  
Time Computed 08-18-15
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 206
Percent Time Used 71
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0610-07-098
MORRIS COUNTY CONTRACTORS, L.L.C.(5.81%)
TEXOP CONSTRUCTION (0.74%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.47%)
PENHALL COMPANY(0.19%)
RK HALL, LLC ( 14.06%)
PANOLA SIGN & BARRICADE, INC.(0.83%)
STRIPING TECHNOLOGY, L.P.(1.63%)
WRIGHT BROTHERS EXCAVATING CO. (1.28%)
CHEROKEE SERVICES(0.41%)
DIRECTIONAL DRILLING (0.01%)
Contract # 05153012
Totals 3821270.50 132992.10 3350044.61 87.6

CountyCAMP
Highway FM 1519
From CR 3109
To FM 556
CSJ 0633-05-018
Proj ID STP 2016(286)HES
Work Type FLASH CHEV, TEXT SHLDR & CL TEXTURE
 
28.805 1439952.07 0.00 1416759.52 98.3
Work Order 12-10-15
Work Began 04-01-16
Work Completed  
Time Computed 01-11-16
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 65
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0633-05-018
BRYDL CONTRACTING, INC.(0.69%)
Contract # 11153207
Totals 1439952.07 0.00 1416759.52 98.3

CountyPANOLA
Highway FM 31
From US 79
To FM 123
CSJ 0640-02-029
Proj ID STP 2016(737)
Work Type CMT TRT EXIST MTL, OCST, ACP, & PM
 
4.848 3629436.31 3999.99 1275306.61 35.1
Work Order 03-15-16
Work Began 05-03-16
Work Completed  
Time Computed 05-02-16
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 35
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0640-02-029
PANOLA SIGN & BARRICADE, INC.(0.62%)
STRIPE-A-ZONE, INC.(3.30%)
DREWERY & WHEATON, LLC (1.92%)
TEXOP CONSTRUCTION (0.77%)
FREDONIA CONSTRUCTION SERVICES (0.27%)
DREWERY BROS TREE SERVICE, INC.(2.16%)
Contract # 02163028
Totals 3629436.31 3999.99 1275306.61 35.1

CountyPANOLA
Highway FM 123
From US 79
To FM 31
CSJ 0731-01-051
Proj ID STP 2016(738)
Work Type CMT TRT BASE, ACP & PVMT MARKINGS
 
21.422 3958704.28 45639.23 547908.01 13.8
Work Order 03-29-16
Work Began 05-31-16
Work Completed  
Time Computed 04-28-16
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 46
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0731-01-051
PANOLA SIGN & BARRICADE, INC.(0.47%)
EAST TEXAS BRIDGE, INC.( 10.92%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.15%)
B & E CONSTRUCTION INC.( 12.21%)
DUSTIN ALLEN, INC. (4.78%)
STRIPE-A-ZONE, INC.(9.16%)
Contract # 02163231
Totals 3958704.28 45639.23 547908.01 13.8

CountyHARRISON
Highway FM 450
From AT LITTLE CYPRESS CREEK
To .
CSJ 0843-02-012
Proj ID BR 2013(659)
Work Type REPLACE BRIDGE & APPRS
 
2.006 7845576.22 95216.48 7904203.28 99.9
Work Order 08-08-13
Work Began 08-15-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 440
Addl Days Granted 0
Working Days Charged 403
Percent Time Used 91
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0843-02-012
PANOLA SIGN & BARRICADE, INC.(0.18%)
STRIPING TECHNOLOGY, L.P.(0.92%)
MAC TRANSPORTATION, LTD, L.L.P.(4.24%)
AMERICAN REMEDIATION OPTIONS, INC. (2.46%)
DENMAN DRILLING CO., INC.(0.33%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.25%)
Contract # 05133220
Totals 7845576.22 95216.48 7904203.28 99.9

CountyCASS
Highway VA
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 0919-00-073
Proj ID STP 1602(315)
Work Type PAVEMENT MARKINGS
 
95.991 680959.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-18-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0919-00-073
STRIPING SYSTEMS, INC. (0.70%)
Contract # 07163216
Totals 680959.20 0.00 0.00 0.0

CountyUPSHUR
Highway FM 555
From SH 155
To SH 154
CSJ 1018-02-017
Proj ID STP 1502(227)HES
Work Type GR, BS, SURF, HFST & PAV MRKS
 
10.673 1904823.20 263655.70 1348760.75 70.8
Work Order 08-26-15
Work Began 05-09-16
Work Completed  
Time Computed 09-25-15
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 80
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1018-02-017
PANOLA SIGN & BARRICADE, INC.(0.76%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.55%)
TOTAL HIGHWAY MAINTENANCE, LLC ( 14.37%)
MURRAY CONSTRUCTION(1.56%)
HARRIS TRUCKING SERVICES (2.70%)
Contract # 06153224
Totals 1904823.20 263655.70 1348760.75 70.8

CountyHARRISON
Highway FM 2625
From FM 31
To FM 9
CSJ 3283-01-014
Proj ID STP 1502(055)
Work Type CEMENT TRT, FL BS, SURF & PAV MARKS
 
8.690 4532166.52 206275.52 3010597.35 66.4
Work Order 05-15-15
Work Began 06-15-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 44
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3283-01-014
PANOLA SIGN & BARRICADE, INC.(0.45%)
STRIPING TECHNOLOGY, L.P.(2.27%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.67%)
JOHNSON CONSTRUCTION SERVICES, LLC.(0.45%)
ISAACS CONSTRUCTION SERVICES, LLC. (0.47%)
Contract # 04153253
Totals 4532166.52 206275.52 3010597.35 66.4

page 1 | page 2