Monthly State Let Construction Report For Atlanta District As Of Apr 11, 2016 Page 2 Of 2

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCASS
Highway FM 1399
From FM 250
To SH 8
CSJ 0546-08-011
Proj ID STP 2016(338)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
15.694 1162910.40 18911.00 337710.50 29.0
Work Order 12-21-15
Work Began 01-20-16
Work Completed  
Time Computed 01-20-16
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 20
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0546-08-011
N-LINE TRAFFIC MAINTENANCE, L.P. (1.16%)
SOUTHWEST ENVIRONMENT SERVICES LLC (4.54%)
DUSTIN ALLEN, INC. (4.76%)
Contract # 11153013
Totals 1162910.40 18911.00 337710.50 29.0

CountyCASS
Highway FM 1399
From FM 250
To SH 8
CSJ 0546-08-012
Proj ID STP 2016(138)HESG
Work Type FLASH CHEV, TEXT SHLDR & CL TEXTURE
 
24.202 896724.18 0.00 235769.51 26.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-24-15
Work Began 03-07-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 21
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-08-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153007
Totals 896724.18 0.00 235769.51 26.2

CountyCASS
Highway FM 125
From SH 43
To LOUISIANA STATE LINE
CSJ 0546-09-039
Proj ID STP 1502(226)HES
Work Type GR, STR, BS, SURF, HFST & PAV MRKS
 
37.671 3490097.96 0.00 107480.00 3.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 260
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0546-09-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153214
Totals 3490097.96 0.00 107480.00 3.0

CountyTITUS
Highway IH 30
From FRANKLIN COUNTY LINE
To MORRIS COUNTY LINE
CSJ 0610-03-079
Proj ID NH 2015(407)
Work Type PAV REP, ACP SURFACING AND PAV MARK
 
97.964 33725327.54 1755068.26 18957290.72 56.2
Work Order 02-10-15
Work Began 04-15-15
Work Completed  
Time Computed 04-11-15
Contract Working Days 595
Addl Days Granted 0
Working Days Charged 191
Percent Time Used 32
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-03-079
DUSTROL, INC.(3.91%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.33%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.32%)
DUSTIN ALLEN, INC. (3.58%)
STRIPE-A-ZONE, INC.(7.29%)
JM YANEZ CONSTRUCTION(1.60%)
SCR CONSTRUCTION CO., INC. (1.48%)
EAST TEXAS BRIDGE, INC.(9.22%)
STRAIGHT LINE SAWING & SEALING (0.36%)
SAMMY GIST ENTERPRISES, INC. (0.20%)
BRYDL CONTRACTING, INC.(0.03%)
Contract # 12143202
Totals 33725327.54 1755068.26 18957290.72 56.2

CountyBOWIE
Highway IH 30
From SH 98
To SP 86
CSJ 0610-06-078
Proj ID IM 0303(126)
Work Type PAV REP, PLANING, ACP & PAV MRKS
 
17.707 8894155.74 0.00 8440701.24 95.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-06-14
Work Began 07-08-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 113
Addl Days Granted 3
Working Days Charged 152
Percent Time Used 131
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-06-078
SOUTHWEST ENVIRONMENT SERVICES LLC (0.02%)
COWBELL TRAFFIC SERVICES, INC. (0.13%)
DUSTROL, INC.(8.10%)
SCR CONSTRUCTION CO., INC. (8.95%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23%)
DUSTIN ALLEN, INC. (2.50%)
STRIPING TECHNOLOGY, L.P.(1.27%)
Contract # 04143025
Totals 8894155.74 0.00 8440701.24 95.3

CountyBOWIE
Highway IH 30
From AT SH 98 (EB) UNDERPASS
To .
CSJ 0610-06-087
Proj ID BR 2016(573)
Work Type BRIDGE REPAIR
 
0.043 88000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-06-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163011
Totals 88000.00 0.00 0.00 0.0

CountyBOWIE
Highway IH 30
From AT FM 2253 UNDERPASS
To .
CSJ 0610-07-098
Proj ID STP 2013(843)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.010 3821270.50 226654.78 2266830.83 59.3
Work Order 06-30-15
Work Began 08-18-15
Work Completed  
Time Computed 08-18-15
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 126
Percent Time Used 43
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0610-07-098
MORRIS COUNTY CONTRACTORS, L.L.C.(5.81%)
TEXOP CONSTRUCTION (0.74%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.47%)
PENHALL COMPANY(0.19%)
RK HALL, LLC ( 14.06%)
PANOLA SIGN & BARRICADE, INC.(0.83%)
STRIPING TECHNOLOGY, L.P.(1.63%)
WRIGHT BROTHERS EXCAVATING CO. (1.28%)
Contract # 05153012
Totals 3821270.50 226654.78 2266830.83 59.3

CountyCAMP
Highway FM 1519
From CR 3109
To FM 556
CSJ 0633-05-018
Proj ID STP 2016(286)HES
Work Type FLASH CHEV, TEXT SHLDR & CL TEXTURE
 
28.805 1439952.07 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-15
Work Began 04-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 21
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0633-05-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153207
Totals 1439952.07 0.00 0.00 0.0

CountyPANOLA
Highway FM 31
From US 79
To FM 123
CSJ 0640-02-029
Proj ID STP 2016(737)
Work Type CMT TRT EXIST MTL, OCST, ACP, & PM
 
4.848 3629436.31 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0640-02-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163028
Totals 3629436.31 0.00 0.00 0.0

CountyPANOLA
Highway FM 123
From US 79
To FM 31
CSJ 0731-01-051
Proj ID STP 2016(738)
Work Type CMT TRT BASE, ACP & PVMT MARKINGS
 
21.422 3958704.28 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0731-01-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163231
Totals 3958704.28 0.00 0.00 0.0

CountyHARRISON
Highway FM 450
From AT LITTLE CYPRESS CREEK
To .
CSJ 0843-02-012
Proj ID BR 2013(659)
Work Type REPLACE BRIDGE & APPRS
 
2.006 7845576.22 65034.05 7498569.34 95.5
Work Order 08-08-13
Work Began 08-15-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 440
Addl Days Granted 0
Working Days Charged 327
Percent Time Used 74
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0843-02-012
PANOLA SIGN & BARRICADE, INC.(0.18%)
STRIPING TECHNOLOGY, L.P.(0.92%)
MAC TRANSPORTATION, LTD, L.L.P.(4.24%)
AMERICAN REMEDIATION OPTIONS, INC. (2.46%)
DENMAN DRILLING CO., INC.(0.33%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.25%)
Contract # 05133220
Totals 7845576.22 65034.05 7498569.34 95.5

CountyUPSHUR
Highway FM 555
From SH 155
To SH 154
CSJ 1018-02-017
Proj ID STP 1502(227)HES
Work Type GR, BS, SURF, HFST & PAV MRKS
 
10.673 1904823.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-26-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1018-02-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153224
Totals 1904823.20 0.00 0.00 0.0

CountyMARION
Highway FM 805
From CR 3410
To 1.3 MI. E. OF SH 43
CSJ 1101-01-013
Proj ID STP 1502(014)HES
Work Type SAFE TREAT FIXED OBJECTS & WIDEN LN
 
7.199 1172292.91 0.00 662101.21 56.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-01-15
Work Began 07-06-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 63
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1101-01-013
PANOLA SIGN & BARRICADE, INC.(0.76%)
SOUTHWEST ENVIRONMENT SERVICES LLC (4.55%)
JM YANEZ CONSTRUCTION(7.74%)
STRIPING TECHNOLOGY, L.P.(2.51%)
Contract # 04153228
Totals 1172292.91 0.00 662101.21 56.4

CountyTITUS
Highway FM 1402
From 1.2 MI N OF IH 30
To 1.8 MI N OF IH 30
CSJ 1384-01-021
Proj ID C 1384-1-21
Work Type GR, BASE, SURF & PM
 
0.622 1351578.66 112.50 1404900.23 99.9
Work Order 01-17-14
Work Began 02-24-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 66
Contractor(s)
TEXANA LAND & ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1384-01-021
BAHENA CONSTRUCTION CO.,INC. (9.74%)
GIST ENTERPRISES, INC. (1.45%)
LYON BARRICADE AND CONSTRUCTION CO.(0.76%)
SAMMY G. SMALLWOOD (0.50%)
STRIPING TECHNOLOGY, L.P.(4.23%)
TURF WORKZ (2.28%)
MOORE CONSTRUCTION, INC. (3.27%)
Contract # 10133211
Totals 1351578.66 112.50 1404900.23 99.9

CountyBOWIE
Highway FM 2253
From IH 30
To US 82
CSJ 2048-01-014
Proj ID STP 2014(596)
Work Type GRADING, BASE, SURFACING & PAV MARKS
 
0.383 2250079.40 50454.30 2240429.63 99.9
Work Order 06-18-14
Work Began 08-18-14
Work Completed  
Time Computed 08-18-14
Contract Working Days 100
Addl Days Granted 67
Working Days Charged 190
Percent Time Used 113
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2048-01-014
MAC TRANSPORTATION, LTD, L.L.P.(1.98%)
STRIPING TECHNOLOGY, L.P.(1.08%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.98%)
ODUM SERVICES, L.P.(1.02%)
PANOLA SIGN & BARRICADE, INC.(0.23%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.12%)
RICK HARGROVE TRUCKING (1.98%)
TEXOP CONSTRUCTION (1.14%)
RK HALL, LLC ( 12.79%)
SOUTHEAST GRINDING & GROOVING, LLC (0.06%)
Contract # 04143206
Totals 2250079.40 50454.30 2240429.63 99.9

CountyHARRISON
Highway FM 2625
From FM 31
To FM 9
CSJ 3283-01-014
Proj ID STP 1502(055)
Work Type CEMENT TRT, FL BS, SURF & PAV MARKS
 
8.690 4532166.52 1200.00 1808689.76 39.9
Work Order 05-15-15
Work Began 06-15-15
Work Completed  
Time Computed 01-30-16
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 23
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3283-01-014
PANOLA SIGN & BARRICADE, INC.(0.45%)
STRIPING TECHNOLOGY, L.P.(2.27%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.14%)
JOHNSON CONSTRUCTION SERVICES, LLC.(0.45%)
Contract # 04153253
Totals 4532166.52 1200.00 1808689.76 39.9