Monthly State Let Construction Report For Brownwood District As Of Aug 16, 2016 Page 1 Of 2

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEASTLAND
Highway IH 20
From AT IH 20
To .
CSJ 0007-04-113
Proj ID CC 7-4-113
Work Type CRASH WALLS
 
0.100 278879.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-04-113
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163239
Totals 278879.60 0.00 0.00 0.0

CountyEASTLAND
Highway IH 20
From AT 0.5 MI. W OF FM 571 AND ALSO AT
To 2.5 MI. W OF SH 16
CSJ 0007-06-070
Proj ID STP 2005(276)TEG
Work Type CONSTRUCT TWO SAFETY REST AREAS
 
3.119 16358386.58 0.00 16466163.62 99.9
Work Order 01-04-13
Work Began 02-01-13
Work Completed  
Time Computed 01-20-13
Contract Working Days 415
Addl Days Granted 180
Working Days Charged 628
Percent Time Used 105
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070
EROSION CONTROL MANAGEMENT SERVICES(0.83%)
ABILENE SHEET METAL(1.43%)
CURTIS MECHANICAL CONTRACTORS, INC.(2.10%)
GRIZZLY GLASS & MIRROR, INC. (1.01%)
LONE OAK LANDSCAPE LLC (0.38%)
LONE STAR BARRIER SERVICES, LLC(0.66%)
PEACHTREE CONSTRUCTION, LTD. (4.79%)
SCR CONSTRUCTION CO., INC. (0.18%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42%)
TIPPENN FABRICATION & ERECTION (5.06%)
ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57%)
BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53%)
CORPUS CHRISTI STAMP WORKS, INC. (0.05%)
FINLEY TERMITE AND PEST CONTROL, INC.(0.01%)
SOLID ROCK LAWN & LANDSCAPE(0.21%)
TEX OP CONSTRUCTION, LP(0.20%)
GOMEZ FLOOR COVERING, INC. (1.55%)
ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07%)
B.A.D.J., INC. DBA THE TOPSPOT (0.21%)
WILKS MASONRY CORPORATION(4.34%)
LIBERTY PAINTING & DRYWALL (0.65%)
HUNTER KNEPSHIELD COMPANY(0.73%)
CLLA GROUP, LLC(1.46%)
AMERITEX FLAG & FLAGPOLE, LLC(0.03%)
A & A CONSTRUCTION (0.26%)
LIBERTY PAINTING & DRYWALL (0.65%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.11%)
CONROE WOOD PRODUCTS INC.(0.00%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
SAR TRANSPORTATION, LLC(0.00%)
CHAMPION FUEL SOLUTIONS(0.00%)
Contract # 10123203
Totals 16358386.58 0.00 16466163.62 99.9

CountySTEPHENS
Highway US 180
From 0.47 MI. E OF SHACKELFORD C/L
To 0.77 MI. E OF FM 3201
CSJ 0011-07-047
Proj ID STP 1302(081)
Work Type BASE OVERLAY, 2CST, ADD PASSING LANES
 
4.452 4046707.37 0.00 1152078.74 28.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-03-16
Work Began 04-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 34
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-047
CONTRACTORS SERVICE COMPANY(0.45%)
MARCOM"S MOWING SERVICE, LLC (1.03%)
STRIPING TECHNOLOGY, L.P.(2.46%)
W.S. CONSTRUCTION COMPANY(5.18%)
STRIPING SYSTEMS, INC. (0.03%)
Contract # 11153222
Totals 4046707.37 0.00 1152078.74 28.4

CountySTEPHENS
Highway US 180 ETC
From 0.5 MI. W OF FM 2231
To FM 3099
CSJ 0011-07-049
Proj ID STP 2016(307)
Work Type SEAL COAT
 
201.520 5258018.35 0.00 3827907.09 72.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 31
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-049
D.I.J. CONSTRUCTION, INC (6.29%)
BARRICADES PLUS, LLC (0.56%)
BRYDL CONTRACTING, INC.(0.01%)
Contract # 10153028
Totals 5258018.35 0.00 3827907.09 72.8

CountySTEPHENS
Highway US 180
From GONZALES CREEK
To FM 287
CSJ 0011-08-026
Proj ID STP 1602(051)
Work Type RECONSTRUCT URBAN ROADWAY
 
5.129 13412991.58 0.00 87321.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 459
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-08-026
CHEROKEE SERVICES(0.17%)
D. I. J. CONSTRUCTION, INC.(1.17%)
GIBSON & ASSOCIATES, INC.(0.66%)
HJC FARMS, INC.(0.63%)
J&M CONTRACTING COMPANY( 14.52%)
PENHALL COMPANY(0.08%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.49%)
WILLIS ELECTRIC CO., LP(2.37%)
FAMBRO CONSTRUCTION, INC.( 12.03%)
Contract # 05163002
Totals 13412991.58 0.00 87321.00 0.6

CountyCOLEMAN
Highway US 84 ETC
From TAYLOR C/L
To FM 702
CSJ 0054-02-032
Proj ID STP 2016(918)HES
Work Type TEXTURIZE SHOULDERS AND CENTERLINE
 
61.043 399367.10 0.00 421383.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 37
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-02-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163233
Totals 399367.10 0.00 421383.00 99.9

CountyBROWN
Highway US 84
From AT FT. WORTH & WESTERN RAILROAD
To .
CSJ 0054-07-069
Proj ID STP 1302(079)RGS
Work Type RAILROAD BRIDGE REPLACEMENT
 
0.520 8488149.70 0.00 84881.50 1.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-10-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163207
Totals 8488149.70 0.00 84881.50 1.0

CountyBROWN
Highway US 67 ETC
From NEAR US 377
To NEAR US 84
CSJ 0054-07-082
Proj ID NH 1602(035)
Work Type SEAL COAT
 
8.295 1070153.48 0.00 641876.24 59.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 23
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-082
FLASHER EQUIPMENT COMPANY(1.25%)
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. ( 54.08%)
PAVEMENT MARKINGS INC. ( 10.76%)
Contract # 03163232
Totals 1070153.48 0.00 641876.24 59.9

CountyEASTLAND
Highway US 183
From 0.599 MI. N
To BROWN C/L
CSJ 0127-02-140
Proj ID STP 2015(785)
Work Type ADD PASSING LANES
 
0.246 113364.13 0.00 20000.00 17.6
CountyBROWN
Highway US 183
From EASTLAND C/L
To FM 1467
CSJ 0127-03-031
Proj ID STP 2015(785)
Work Type ADD PASSING LANES
 
7.886 2377048.46 0.00 708095.75 29.7
CountyBROWN
Highway US 183
From FM 1467
To 3.6 MI N OF US 67(NEAR BWD AIRPORT)
CSJ 0127-04-032
Proj ID STP 1502(143)HES
Work Type ADD PASSING LANES
 
2.985 1788921.69 0.00 854464.75 47.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-11-15
Work Began 12-15-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 139
Percent Time Used 82
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0127-03-031
D. I. J. CONSTRUCTION, INC.(3.35%)
TEXAS ALTERNATIVE GRASSER, INC.(0.29%)
HJC FARMS, INC.(1.37%)
NORTH EASTERN PAVERS ( 23.51%)
RAMBO CONTRACTING, INC.(3.20%)
Contract # 04153259
Totals 4279334.28 0.00 1582560.50 36.9

CountySAN SABA
Highway FM 580
From US 190
To LAMPASAS C/L
CSJ 0231-14-017
Proj ID STP 2015(389)HES
Work Type ADD'L PAVED SURF WIDTH, WDN STRS
 
14.144 5387952.96 424110.09 3365270.39 62.4
Work Order 03-13-15
Work Began 06-23-15
Work Completed  
Time Computed 06-11-15
Contract Working Days 474
Addl Days Granted 0
Working Days Charged 234
Percent Time Used 49
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0231-14-017
D. I. J. CONSTRUCTION, INC.(2.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.37%)
PRIMATE CONSTRUCTION, INC. (0.14%)
ROADWAY SPECIALTIES, INC.(4.88%)
SAN-ANN-CO., INC.(0.99%)
TEXAS ALTERNATIVE GRASSER, INC.(0.47%)
BROCK CONSTRUCTION, LLC(0.30%)
Contract # 01153225
Totals 5387952.96 424110.09 3365270.39 62.4

CountyEASTLAND
Highway SH 6
From 4.4 MI. E OF CARBON
To COMANCHE C/L
CSJ 0257-04-025
Proj ID STP 2014(867)
Work Type BASE OVERLAY AND 2 COURSE SURF TRT
 
5.099 3574742.00 0.00 2720890.23 76.1
CountyCOMANCHE
Highway SH 6
From EASTLAND C/L
To 3.22 MI. E
CSJ 0257-05-044
Proj ID STP 2014(867)
Work Type RECONSTRUCT ROADWAY
 
3.219 1920300.43 0.00 7433.80 0.3
Work Order 02-05-15
Work Began 03-16-15
Work Completed  
Time Computed 04-06-15
Contract Working Days 203
Addl Days Granted 42
Working Days Charged 208
Percent Time Used 84
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0257-04-025
NORTHEASTERN PAVERS, INC.( 23.73%)
TEXAS ALTERNATIVE GRASSER, INC.(0.26%)
HJC FARMS, INC.(0.67%)
STRIPING TECHNOLOGY, L.P.(2.67%)
Contract # 07143216
Totals 5495042.43 0.00 2728324.03 49.6

CountyCOMANCHE
Highway SH 6
From 3.22 MI. E OF EASTLAND C/L
To NEAR SH 16
CSJ 0257-05-042
Proj ID STP 2015(058)
Work Type RECONSTRUCT ROADWAY
 
5.822 3990282.05 277811.05 3763769.42 94.8
Work Order 02-05-15
Work Began 03-16-15
Work Completed  
Time Computed 04-06-15
Contract Working Days 165
Addl Days Granted 32
Working Days Charged 219
Percent Time Used 111
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0257-05-042
D. I. J. CONSTRUCTION, INC.(2.16%)
HJC FARMS, INC.(0.45%)
TEXAS ALTERNATIVE GRASSER, INC.(0.36%)
NORTH EASTERN PAVERS ( 17.67%)
Contract # 09143214
Totals 3990282.05 277811.05 3763769.42 94.8

CountyMCCULLOCH
Highway US 190
From US 377
To SAN SABA C/L
CSJ 0272-01-031
Proj ID STP 2016(924)HES
Work Type UPGRADE GUARDRAIL & SFTY TREAT STRS
 
17.174 1084525.50 0.00 0.00 0.0
CountySAN SABA
Highway FM 45
From MILLS C/L
To RICHLAND SPRINGS NORTH CITY LIMIT
CSJ 0480-08-023
Proj ID STP 2016(925)HRR
Work Type UPGRADE GUARDRAIL & SFTY TREAT STRS
 
12.071 714070.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-03-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0272-01-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163025
Totals 1798595.50 0.00 0.00 0.0

CountyBROWN
Highway SH 279 ETC
From FM 1849
To NEAR BROWNWOOD NORTH CITY LIMIT
CSJ 0480-01-032
Proj ID STP 2015(829)HES
Work Type UPGRADE GUARDRAIL & SFTY TRT STRS
 
48.004 1716374.55 179399.66 1519902.05 88.5
Work Order 06-11-15
Work Began 09-10-15
Work Completed  
Time Computed 09-10-15
Contract Working Days 344
Addl Days Granted 4
Working Days Charged 199
Percent Time Used 57
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0480-01-032
WOLFE CONSTRUCTION GROUP, INC. (3.10%)
Contract # 04153009
Totals 1716374.55 179399.66 1519902.05 88.5

CountyMILLS
Highway FM 45
From BROWN C/L
To SAN SABA C/L
CSJ 0480-07-009
Proj ID STP 1602(052)
Work Type GRADING, STRUCTURES, BASE, AND SURF
 
4.362 4563803.88 0.00 31680.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-20-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0480-07-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163004
Totals 4563803.88 0.00 31680.00 0.6

CountyEASTLAND
Highway FM 8
From 0.273 MI. E OF FM 2214
To 0.06 MI. W OF HOG CREEK
CSJ 0550-01-023
Proj ID STP 2014(544)
Work Type GRADING, STRS, FLEX BASE, AND SURF
 
0.322 458987.68 59841.00 88059.40 19.1
CountyEASTLAND
Highway FM 2214
From 0.5 MI E OF FM 571
To FM 8
CSJ 1697-02-019
Proj ID STP 2014(544)
Work Type GRADING, STRS, FLEX BASE AND SURFAC
 
4.701 4840589.80 156656.95 3488139.87 72.0
Work Order 08-07-14
Work Began 01-06-15
Work Completed  
Time Computed 12-10-14
Contract Working Days 272
Addl Days Granted 31
Working Days Charged 302
Percent Time Used 99
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1697-02-019
MARCOM"S MOWING SERVICE, LLC (0.49%)
NORTH EASTERN PAVERS ( 11.45%)
S & S BRIDGE PAINTING, INC.(0.55%)
TEXAS ALTERNATIVE GRASSER, INC.(0.62%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.37%)
WILLIS ELECTRIC CO., LP(2.05%)
SHINN & GREGORY, INC.(0.48%)
EROSION CONTROL MANAGEMENT SERVICES(0.61%)
ELLIS-MCGINNIS CONSTRUCTION CO.(3.96%)
Contract # 05143002
Totals 5299577.48 216497.95 3576199.27 67.4

CountyEASTLAND
Highway FM 8
From AT HOG CREEK
To .
CSJ 0550-01-026
Proj ID BR 1502(309)
Work Type WIDEN BRIDGE, REHAB DECK & APPRS
 
0.156 1189721.30 0.00 819586.50 68.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-24-15
Work Began 03-21-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 96
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 0550-01-026
HJC FARMS, INC.(2.46%)
PEACHTREE CONSTRUCTION, LTD. (5.77%)
S&S BRIDGE PAINTING(4.91%)
SHINN & GREGORY, INC.(2.30%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.66%)
TEXOP CONSTRUCTION (0.46%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
STRIPING TECHNOLOGY, L.P.(2.36%)
DFW SERVICES, LLC(0.97%)
PENHALL COMPANY(0.45%)
GRANBURY EXCAVATING, INC.( 14.37%)
Contract # 06153019
Totals 1189721.30 0.00 819586.50 68.8

CountyEASTLAND
Highway FM 571
From AT LEON RIVER
To .
CSJ 0570-01-019
Proj ID BR 2015(462)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.133 821742.40 19636.00 816183.28 99.3
CountyCOMANCHE
Highway CR
From ON CR 435 AT SABANA RIVER
To .
CSJ 0923-17-063
Proj ID BR 2012(743)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.070 379885.40 0.00 376106.25 99.0
CountyCOMANCHE
Highway CR
From ON CR 178 AT SABANA RIVER DRAW
To .
CSJ 0923-17-070
Proj ID BR 2014(382)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 134401.00 80.00 138681.00 99.9
Work Order 02-05-15
Work Began 05-05-15
Work Completed  
Time Computed 05-06-15
Contract Working Days 160
Addl Days Granted 22
Working Days Charged 181
Percent Time Used 99
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0570-01-019
CONTRACTORS SERVICE COMPANY(0.93%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.99%)
ODUM SERVICES, L.P.(3.50%)
PRATER EQUIPMENT CO., INC. (2.67%)
MESA ROD BUSTERS, INC. (0.16%)
JB FARM & RANCH( 18.42%)
GJ SEEDING, LLC(1.07%)
STRIPING TECHNOLOGY, L.P.(0.63%)
SHINN & GREGORY, INC.(6.56%)
Contract # 12143211
Totals 1336028.80 19716.00 1330970.53 99.6

CountyEASTLAND
Highway FM 2461
From IH 20
To FM 2214
CSJ 0714-05-018
Proj ID STP 2015(836)HES
Work Type UPGRADE GUARDRAIL & SFTY TREAT STRS
 
8.435 444021.50 0.00 412189.75 92.8
CountyEASTLAND
Highway FM 2461
From IH 20
To FM 2214
CSJ 0714-05-020
Proj ID STP 2015(835)
Work Type REHABILITATION OF EXISTING ROADWAY
 
8.435 1998843.11 189774.34 941996.40 47.1
Work Order 05-21-15
Work Began 06-30-15
Work Completed  
Time Computed 06-21-15
Contract Working Days 238
Addl Days Granted 5
Working Days Charged 228
Percent Time Used 93
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0714-05-020
D.I.J. CONSTRUCTION, INC (3.58%)
MARCOM"S MOWING SERVICE, LLC (3.62%)
NORTHEASTERN PAVERS, INC.( 20.91%)
TEXAS ALTERNATIVE GRASSER, INC.(0.26%)
LUZ LERMA CONSTRUCTION, INC. (5.28%)
Contract # 04153011
Totals 2442864.61 189774.34 1354186.15 55.4

CountyBROWN
Highway CR
From ON CR 225 AT CLEAR CREEK
To .
CSJ 0923-06-056
Proj ID BR 2015(387)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 603204.63 0.00 0.00 0.0
CountyBROWN
Highway CR
From ON CR 258 AT DOUDLE CREEK
To .
CSJ 0923-06-070
Proj ID BR 2015(388)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 416710.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 143
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163217
Totals 1019914.95 0.00 0.00 0.0

page 1 | page 2