Monthly State Let Construction Report For Childress District As Of Jul 13, 2015 Page 1 Of 2

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWHEELER
Highway US 83
From 0.500 MI N OF SHAMROCK NCL, NORTH
To WHEELER SCL
CSJ 0030-09-047
Proj ID STP 1502(377)
Work Type WIDENING OF A NON FREEWAY FACILITY
 
14.092 9018908.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-09-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153259
Totals 9018908.40 0.00 0.00 0.0

CountyKING
Highway US 83
From COTTLE C/L, S
To GUTHRIE
CSJ 0032-05-038
Proj ID C 32-5-38
Work Type MISCELLANEOUS WORK
 
15.270 77364.00 0.00 0.00 100.0
CountyKING
Highway US 83
From US 82, S
To STONEWALL C/L
CSJ 0032-06-036
Proj ID C 32-6-36
Work Type MISCELLANEOUS WORK
 
14.440 8596.00 0.00 0.00 100.0
CountyHALL
Highway SH 256
From 0.3 MILES E OF SH 70, E
To FM 2361
CSJ 0541-02-030
Proj ID C 541-2-30
Work Type REPLACE BRIDGERAIL
 
30.323 581853.35 0.00 119526.24 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-12
Work Began 00-00-00
Work Completed 06-23-14
Time Computed 09-05-12
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0541-02-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06123013
Totals 667813.35 0.00 119526.24 100.0

CountyDONLEY
Highway US 287
From ARMSTRONG C/L
To CLARENDON WCL (SBL)
CSJ 0042-06-067
Proj ID NH 2014(061)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
11.635 2248102.73 0.00 2331175.41 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 09-25-14
Work Completed 02-10-15
Time Computed 02-02-14
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 85
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-06-067
FLAT LINE, INC.(1.29%)
HJC FARMS, INC.(5.20%)
BARRICADES UNLIMITED (0.66%)
WEST TEXAS RUMBLE STRIP(0.36%)
E. DIAZ TRUCKING (3.00%)
Contract # 10133207
Totals 2248102.73 0.00 2331175.41 100.0

CountyHALL
Highway US 287
From RED RIVER BRIDGE, SE
To CHILDRESS C/L (NBL)
CSJ 0042-09-120
Proj ID NH 2014(752)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
3.350 1106400.71 0.00 1197485.85 100.0
CountyCHILDRESS
Highway US 287
From HALL C/L, SE
To 0.36 MILES WEST OF FM 164(NBL)
CSJ 0042-12-063
Proj ID NH 2014(752)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
9.172 3136409.13 0.00 3581850.34 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-09-14
Work Began 10-07-14
Work Completed 06-08-15
Time Computed 05-25-14
Contract Working Days 73
Addl Days Granted 11
Working Days Charged 69
Percent Time Used 82
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-12-063
ALTUS TRAFFIC MANAGEMENT LLC (0.23%)
DUSTROL, INC.(2.33%)
PENHALL COMPANY(0.21%)
SCR CONSTRUCTION CO., INC. (0.67%)
TEXAS ALTERNATIVE GRASSER, INC.(0.23%)
BARRICADES UNLIMITED (1.17%)
Contract # 04143032
Totals 4242809.84 0.00 4779336.19 100.0

CountyCHILDRESS
Highway US 287
From 17TH STREET, EAST
To 340 FT. EAST OF FM 2530
CSJ 0043-01-078
Proj ID NH 1502(313)
Work Type REHABILITATION OF EXISTING ROAD
 
2.007 2560131.56 0.00 0.00 0.0
CountyHARDEMAN
Highway US 287
From 55 FT WEST OF FM 2568, EAST
To SH 6
CSJ 0043-02-072
Proj ID NH 1502(313)
Work Type REHABILITATION OF EXISTING ROAD
 
0.840 442291.10 0.00 0.00 0.0
CountyHARDEMAN
Highway US 287
From SH 6, EAST
To 65 FT. WEST OF FM 2568
CSJ 0043-04-077
Proj ID NH 1502(313)
Work Type REHABILITATION OF EXISTING ROAD
 
1.226 6912523.04 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-01-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153213
Totals 9914945.70 0.00 0.00 0.0

CountyHARDEMAN
Highway SH 6
From @ BNSF RR OVERPASS
To .
CSJ 0097-02-037
Proj ID BR 2014(756)
Work Type MISCELLANEOUS WORK
 
0.453 2936931.42 122659.50 1524777.85 51.9
Work Order 08-29-14
Work Began 12-08-14
Work Completed  
Time Computed 09-14-14
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 53
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0097-02-037
GARY A. CRAIN, INC.(0.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 10.72%)
CONTRACTORS SERVICE COMPANY(0.31%)
BARRICADES UNLIMITED (0.33%)
DUSTROL, INC.(1.85%)
GIBSON & ASSOCIATES, INC.(2.46%)
LANCO TURF & SEEDING, INC. (1.42%)
DUSTY ALLEN, INC.(2.65%)
MCL CONTRACTING, LLC (0.40%)
Contract # 06143217
Totals 2936931.42 122659.50 1524777.85 51.9

CountyHARDEMAN
Highway SH 6
From US 287, S
To 6 MILES
CSJ 0098-01-036
Proj ID STP 2014(757)
Work Type REHABILITATION OF EXISTING ROADWAY
 
6.000 4804257.07 1518915.69 3785148.33 78.7
Work Order 09-09-14
Work Began 04-15-15
Work Completed  
Time Computed 09-25-14
Contract Working Days 103
Addl Days Granted 10
Working Days Charged 43
Percent Time Used 38
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0098-01-036
DUSTROL, INC.(0.40%)
BARRICADES UNLIMITED (2.26%)
E. DIAZ TRUCKING (5.00%)
Contract # 06143019
Totals 4804257.07 1518915.69 3785148.33 78.7

CountyFOARD
Highway SH 6
From @ RAGGEDY CREEK
To .
CSJ 0098-02-025
Proj ID BR 1102(556)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.094 1135621.40 0.00 1112683.30 97.9
CountyFOARD
Highway FM 267
From @ BEAVER CREEK
To .
CSJ 2164-02-017
Proj ID BR 1102(557)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.114 644822.40 0.00 145328.86 22.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-14
Work Began 10-20-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 148
Percent Time Used 84
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0098-02-025
PENHALL COMPANY (AUSTIN) (0.17%)
DUSTIN ALLEN, INC. (2.87%)
TEXAS ALTERNATIVE GRASSER, INC.(0.87%)
CONTRACTORS SERVICE COMPANY(0.75%)
BARRICADES UNLIMITED (0.88%)
J. LEE MILLIGAN, INC.( 11.83%)
Contract # 06143215
Totals 1780443.80 0.00 1258012.16 70.6

CountyKNOX
Highway SH 6
From HASKELL C/L, N
To 2ND STREET
CSJ 0098-05-033
Proj ID STP 2015(838)
Work Type REHABILITATION OF EXISTING ROAD
 
1.587 1413454.41 0.00 0.00 0.0
CountyKNOX
Highway US 277
From HASKELL C/L, N
To FM 267
CSJ 0157-02-045
Proj ID NH 2015(837)
Work Type REHABILITATION OF EXISTING ROAD
 
2.603 1495602.83 0.00 0.00 0.0
Work Order 05-14-15
Work Began 00-00-00
Work Completed  
Time Computed 06-14-15
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 4
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0157-02-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153025
Totals 2909057.24 0.00 0.00 0.0

CountyMOTLEY
Highway SH 70
From NORTH PEASE RIVER
To .
CSJ 0105-04-042
Proj ID BR 2013(663)
Work Type REPLACEMENT OF EXISTING BRIDGE
 
0.240 2085247.00 12000.00 2152204.82 100.0
CountyMOTLEY
Highway SH 70
From @ MIDDLE PEASE RIVER
To .
CSJ 0105-04-043
Proj ID BR 2013(663)
Work Type REPLACEMENT OF EXISTING BRIDGE
 
0.315 2182953.50 0.00 2203372.31 100.0
Work Order 07-31-13
Work Began 09-03-13
Work Completed 05-19-15
Time Computed 08-16-13
Contract Working Days 275
Addl Days Granted 12
Working Days Charged 285
Percent Time Used 99
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0105-04-042
BARRICADES UNLIMITED (0.82%)
DUSTROL, INC.(0.19%)
LANCO TURF & SEEDING, INC. (0.47%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.58%)
MASTERPIECE GRINDING & GROOVING, LLC (0.13%)
ROSS GRAHAM(0.40%)
G & L REBAR(0.49%)
MCL CONTRACTING, LLC (0.71%)
HOLMES CONSTRUCTION CO., L.P.(1.22%)
PENHALL COMPANY (AUSTIN) (0.19%)
DUININCK, INC. (3.25%)
Contract # 05133233
Totals 4268200.50 12000.00 4355577.13 100.0

CountyFOARD
Highway US 70
From 4.361 MI WEST OF CROWELL WCL, E
To CROWELL WCL
CSJ 0146-05-033
Proj ID STP 2015(059)
Work Type REHABILITATION OF EXISTING ROAD
 
4.361 4032532.41 0.00 0.00 0.0
Work Order 10-09-14
Work Began 00-00-00
Work Completed  
Time Computed 10-25-14
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 26
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0146-05-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143229
Totals 4032532.41 0.00 0.00 0.0

CountyHALL
Highway SH 86
From 118 FT E OF CR 3
To SH 70
CSJ 0303-05-018
Proj ID STP 2014(473)
Work Type REHABILITATION OF EXISTING ROADWAY
 
0.616 2600383.20 0.00 2791141.81 99.9
CountyHALL
Highway SH 86
From 118 FT E OF CR 3
To SH 70
CSJ 0303-05-019
Proj ID STP 1302(074)
Work Type ROW UTL. ADJ.
 
0.616 408330.05 0.00 401767.90 98.3
Work Order 05-01-14
Work Began 06-02-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 212
Addl Days Granted 8
Working Days Charged 166
Percent Time Used 75
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0303-05-018
ALAMO BROTHERS CONCRETE, INC.( 20.20%)
BARRICADES UNLIMITED (1.08%)
WEST TEXAS UTILITY CONTRACTORS, INC. ( 12.33%)
Contract # 03143216
Totals 3008713.25 0.00 3192909.71 99.9

CountyBRISCOE
Highway SH 207
From 4538 FT NORTH OF FM146
To 1435 FT NORTH OF FM146
CSJ 0357-06-020
Proj ID STP 2014(868)HES
Work Type REALIGN INTERSECTIONS
 
1.293 1025196.80 0.00 15514.64 1.5
CountyBRISCOE
Highway SH 207
From 1435 FT NORTH OF FM146
To 1222 FT SOUTH OF FM146
CSJ 0970-03-021
Proj ID STP 2014(869)HES
Work Type REALIGN INTERSECTIONS
 
0.503 169641.70 0.00 0.00 0.0
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 10-16-14
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0357-06-020
BARRICADES UNLIMITED (0.99%)
E. DIAZ TRUCKING (2.02%)
HJC FARMS, INC.(1.35%)
TEXAS ALTERNATIVE GRASSER, INC.(2.02%)
WILLIS ELECTRIC CO., LP(3.25%)
Contract # 07143232
Totals 1194838.50 0.00 15514.64 1.2

CountyHALL
Highway SH 256 ETC
From US 287, E
To CHILDRESS C/L
CSJ 0381-02-020
Proj ID STP 2015(060)
Work Type SEAL COAT
 
124.042 5030824.43 86262.82 1260548.66 25.0
Work Order 10-10-14
Work Began 00-00-00
Work Completed  
Time Computed 10-26-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 12
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0381-02-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143024
Totals 5030824.43 86262.82 1260548.66 25.0

CountyBRISCOE
Highway SH 207
From FLOYD C/L NORTH
To SH 86
CSJ 0453-06-011
Proj ID STP 2014(229)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
11.022 4243800.64 0.00 2050507.00 48.3
Work Order 01-06-14
Work Began 05-12-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 81
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0453-06-011
ALTUS TRAFFIC MANAGEMENT LLC (0.32%)
FLAT LINE, INC.(0.73%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.17%)
TEXAS ALTERNATIVE GRASSER, INC.(0.59%)
HJC FARMS, INC.(0.69%)
TEX OP CONSTRUCTION, LP(0.16%)
WILLIS ELECTRIC CO., LP(0.92%)
Contract # 11133023
Totals 4243800.64 0.00 2050507.00 48.3

CountyWHEELER
Highway FM 48
From HEMPHILL C/L, S
To 0.312 MI S OF SH 152
CSJ 0489-01-020
Proj ID STP 1502(378)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
7.701 5491233.54 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0489-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153237
Totals 5491233.54 0.00 0.00 0.0

CountyKING
Highway SH 222
From US 82, SE
To KNOX C/L
CSJ 0496-03-010
Proj ID STP 2013(813)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
6.983 2445663.33 25872.76 2227682.19 100.0
CountyKNOX
Highway SH 222
From KING C/L, SE
To 4.015 MILES
CSJ 0496-04-031
Proj ID STP 2013(813)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
4.015 1217352.66 0.00 1162174.02 100.0
Work Order 08-19-13
Work Began 09-23-13
Work Completed 02-12-15
Time Computed 09-04-13
Contract Working Days 203
Addl Days Granted 4
Working Days Charged 252
Percent Time Used 121
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0496-03-010
W.S. CONSTRUCTION COMPANY(6.00%)
CONTRACTORS SERVICE COMPANY(0.51%)
HJC FARMS, INC.(2.35%)
TEXAS ALTERNATIVE GRASSER, INC.(0.42%)
WEST TEXAS RUMBLE STRIP(0.15%)
ZACK BURKETT CO. ( 42.81%)
BARRICADES UNLIMITED (1.67%)
Contract # 06133026
Totals 3663015.99 25872.76 3389856.21 100.0

CountyHALL
Highway FM 94
From COTTLE C/L, N
To 1.793 MILES
CSJ 0704-03-014
Proj ID STP 2013(579)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
1.793 3941795.70 0.00 32392.12 0.8
CountyCOTTLE
Highway FM 94
From MOTLEY C/L, NE
To HALL C/L
CSJ 0704-04-015
Proj ID STP 2013(580)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
2.152 2522188.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0704-03-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153221
Totals 6463984.50 0.00 32392.12 0.5

CountyWHEELER
Highway FM 592
From FM 1906, NORTH
To SH 152
CSJ 0761-01-019
Proj ID STP 2015(634)
Work Type WIDENING OF A NON FREEWAY FACILITY
 
4.012 3738577.49 0.00 52780.00 1.4
CountyWHEELER
Highway FM 1906
From US 83, E
To FM 592
CSJ 2147-01-009
Proj ID STP 2015(634)
Work Type WIDENING OF A NON FREEWAY FACILITY
 
7.864 5365641.48 0.00 0.00 0.0
Work Order 03-11-15
Work Began 00-00-00
Work Completed  
Time Computed 03-27-15
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0761-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153030
Totals 9104218.97 0.00 52780.00 0.5

CountyHALL
Highway FM 1547
From US 287
To 0.23 MILES EAST OF US 287
CSJ 0844-05-008
Proj ID STP 1402(008)RGS
Work Type CONSTRUCT RR GRADE SEPARATION STR
 
0.438 5436253.20 268122.33 2897267.63 53.2
Work Order 09-15-14
Work Began 01-05-15
Work Completed  
Time Computed 01-05-15
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 34
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0844-05-008
ACU CONSTRUCTION LLC (0.30%)
BARRICADES UNLIMITED (0.84%)
LANCO TURF & SEEDING, INC. (0.13%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.77%)
MCL CONTRACTING, LLC (1.49%)
PENHALL COMPANY(0.10%)
WILLIS ELECTRIC CO., LP(1.56%)
MCL CONTRACTING, LLC (0.29%)
Contract # 07143048
Totals 5436253.20 268122.33 2897267.63 53.2

page 1 | page 2