Monthly State Let Construction Report For Childress District As Of Apr 11, 2016 Page 1 Of 2

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWHEELER
Highway US 83
From 250 FT. NORTH OF WHEELER NCL, NORTH
To HEMPHILL COUNTY LINE
CSJ 0030-08-035
Proj ID STP 1502(376)
Work Type WIDENING OF A NON - FREEWAY FACILITY
 
12.458 9811524.17 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-08-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153031
Totals 9811524.17 0.00 0.00 0.0

CountyWHEELER
Highway US 83
From 0.500 MI N OF SHAMROCK NCL, NORTH
To WHEELER SCL
CSJ 0030-09-047
Proj ID STP 1502(377)
Work Type WIDENING OF A NON FREEWAY FACILITY
 
14.092 9018908.40 0.00 1578105.83 17.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-15
Work Began 01-15-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 30
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-09-047
DALE BROWN, INC. (3.50%)
BARRICADES UNLIMITED (1.24%)
DUSTROL, INC.(0.25%)
HJC FARMS, INC.(1.97%)
Contract # 07153259
Totals 9018908.40 0.00 1578105.83 17.4

CountyCHILDRESS
Highway US 62
From PRAIRIE DOG TOWN FORK OF RR, NORTH
To US 62/83 SPLIT
CSJ 0031-05-042
Proj ID NH 2016(613)
Work Type REHABILITATION OF EXISTING ROADWAY
 
6.557 4890499.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0031-05-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153041
Totals 4890499.30 0.00 0.00 0.0

CountyDONLEY
Highway US 287
From HEDLEY SCL, SE
To HALL C/L_(SBL)
CSJ 0042-08-056
Proj ID NH 2016(308)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
9.813 2680662.61 0.00 32000.00 1.1
CountyHALL
Highway US 287
From MEMPHIS SCL, SE
To RED RIVER BRIDGE (NBL)
CSJ 0042-09-122
Proj ID NH 2016(308)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
11.956 3169557.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-08-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153015
Totals 5850220.34 0.00 32000.00 0.5

CountyCHILDRESS
Highway US 287
From 17TH STREET, EAST
To 340 FT. EAST OF FM 2530
CSJ 0043-01-078
Proj ID NH 1502(313)
Work Type REHABILITATION OF EXISTING ROAD
 
2.007 2560131.56 839946.95 1644652.10 64.2
CountyHARDEMAN
Highway US 287
From 55 FT WEST OF FM 2568, EAST
To SH 6
CSJ 0043-02-072
Proj ID NH 1502(313)
Work Type REHABILITATION OF EXISTING ROAD
 
0.840 442291.10 89590.70 95485.10 21.5
CountyHARDEMAN
Highway US 287
From SH 6, EAST
To 65 FT. WEST OF FM 2568
CSJ 0043-04-077
Proj ID NH 1502(313)
Work Type REHABILITATION OF EXISTING ROAD
 
1.226 6912523.04 986281.41 1085627.51 15.7
Work Order 08-26-15
Work Began 01-14-16
Work Completed  
Time Computed 01-14-16
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 22
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-01-078
DUSTROL, INC.(0.07%)
LINDAMOOD DEMOLITION, INC. (5.22%)
LUZ LERMA CONSTRUCTION, INC. (4.67%)
MCL CONTRACTING, LLC (1.45%)
PRIMATE CONSTRUCTION, INC. (1.81%)
TEXAS PANHANDLE CONSTRUCTION, INC. (0.72%)
BARRICADES UNLIMITED (0.59%)
Contract # 06153213
Totals 9914945.70 1915819.06 2825764.71 28.5

CountyCHILDRESS
Highway US 287
From DISTRICT WIDE
To .
CSJ 0043-01-079
Proj ID NH 2016(310)
Work Type INSTALL DMS & UPGRADE TRAFFIC SIGNA
 
0.009 1893993.41 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-01-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153208
Totals 1893993.41 0.00 0.00 0.0

CountyHARDEMAN
Highway US 287 ETC
From FM 2568, SOUTH
To WANDERER'S CREEK (SBL)
CSJ 0043-04-078
Proj ID NH 2016(014)
Work Type SEALCOAT
 
122.883 3997851.76 0.00 850523.03 21.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-04-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153205
Totals 3997851.76 0.00 850523.03 21.2

CountyKING
Highway US 82
From 1.210 MILES EAST OF US 83, EAST
To 0.599 MILES WEST OF SH 222
CSJ 0133-01-048
Proj ID NH 2016(614)
Work Type REHABILITATION OF EXISTING ROADWAY
 
12.052 5930781.41 0.00 305179.54 5.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 03-23-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 5
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-01-048
BARRICADES UNLIMITED (0.53%)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC( 14.41%)
TEXOP CONSTRUCTION (1.13%)
TRP CONSTRUCTION GROUP, LLC(2.93%)
Contract # 12153042
Totals 5930781.41 0.00 305179.54 5.1

CountyMOTLEY
Highway US 62 ETC
From FM 1380, E
To COTTLE C/L
CSJ 0146-01-048
Proj ID STP 2016(199)HES
Work Type CENTERLINE TEXTURING
 
104.334 699984.33 0.00 395982.68 56.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 03-07-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 55
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0146-01-048
RED 16 CONSTRUCTION(4.50%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC ( 10.41%)
Contract # 10153021
Totals 699984.33 0.00 395982.68 56.5

CountyHALL
Highway SH 86
From 118 FT E OF CR 3
To SH 70
CSJ 0303-05-018
Proj ID STP 2014(473)
Work Type REHABILITATION OF EXISTING ROADWAY
 
0.616 2600383.20 0.00 2879602.79 99.9
CountyHALL
Highway SH 86
From 118 FT E OF CR 3
To SH 70
CSJ 0303-05-019
Proj ID STP 1302(074)
Work Type ROW UTL. ADJ.
 
0.616 408330.05 0.00 409233.82 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-01-14
Work Began 06-02-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 212
Addl Days Granted 8
Working Days Charged 172
Percent Time Used 78
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0303-05-018
ALAMO BROTHERS CONCRETE, INC.( 20.20%)
BARRICADES UNLIMITED (1.08%)
WEST TEXAS UTILITY CONTRACTORS, INC. ( 12.33%)
Contract # 03143216
Totals 3008713.25 0.00 3288836.61 99.9

CountyBRISCOE
Highway SH 207
From 4538 FT NORTH OF FM146
To 1435 FT NORTH OF FM146
CSJ 0357-06-020
Proj ID STP 2014(868)HES
Work Type REALIGN INTERSECTIONS
 
1.293 1025196.80 0.00 1061560.50 99.9
CountyBRISCOE
Highway SH 207
From 1435 FT NORTH OF FM146
To 1222 FT SOUTH OF FM146
CSJ 0970-03-021
Proj ID STP 2014(869)HES
Work Type REALIGN INTERSECTIONS
 
0.503 169641.70 0.00 151851.34 89.5
Work Order 09-30-14
Work Began 07-06-15
Work Completed  
Time Computed 10-16-14
Contract Working Days 102
Addl Days Granted 10
Working Days Charged 113
Percent Time Used 100
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0357-06-020
BARRICADES UNLIMITED (0.99%)
E. DIAZ TRUCKING (2.02%)
HJC FARMS, INC.(1.35%)
TEXAS ALTERNATIVE GRASSER, INC.(2.02%)
WILLIS ELECTRIC CO., LP(3.25%)
Contract # 07143232
Totals 1194838.50 0.00 1213411.84 99.9

CountyWHEELER
Highway FM 48
From HEMPHILL C/L, S
To 0.312 MI S OF SH 152
CSJ 0489-01-020
Proj ID STP 1502(378)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
7.701 5491233.54 0.00 35625.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0489-01-020
BARRICADES UNLIMITED (1.18%)
Contract # 07153237
Totals 5491233.54 0.00 35625.00 0.6

CountyHALL
Highway FM 94
From COTTLE C/L, N
To 1.793 MILES
CSJ 0704-03-014
Proj ID STP 2013(579)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
1.793 3941795.70 0.00 1660598.64 42.1
CountyCOTTLE
Highway FM 94
From MOTLEY C/L, NE
To HALL C/L
CSJ 0704-04-015
Proj ID STP 2013(580)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
2.152 2522188.80 0.00 698540.00 27.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-15
Work Began 09-14-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 240
Addl Days Granted 10
Working Days Charged 107
Percent Time Used 42
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0704-03-014
BARRICADES UNLIMITED (0.44%)
CONTRACTORS SERVICE COMPANY(0.25%)
LANCO TURF & SEEDING, INC. (0.74%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.69%)
MARCOM"S MOWING SERVICE, LLC (0.78%)
MCL CONTRACTING, LLC (0.36%)
PENHALL COMPANY(0.10%)
ROSS GRAHAM(0.77%)
DALE BROWN, INC. (1.58%)
Contract # 01153221
Totals 6463984.50 0.00 2359138.64 36.4

CountyCOTTLE
Highway FM 1038
From @ SALT CREEK
To .
CSJ 0760-01-024
Proj ID BR 2016(311)
Work Type REPLACEMENT OF AN EXISTING BRIDGE
 
0.142 863088.65 0.00 5570.88 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0760-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153014
Totals 863088.65 0.00 5570.88 0.6

CountyWHEELER
Highway FM 592
From FM 1906, NORTH
To SH 152
CSJ 0761-01-019
Proj ID STP 2015(634)
Work Type WIDENING OF A NON FREEWAY FACILITY
 
4.012 3738577.49 776941.15 2037084.50 54.4
CountyWHEELER
Highway FM 1906
From US 83, E
To FM 592
CSJ 2147-01-009
Proj ID STP 2015(634)
Work Type WIDENING OF A NON FREEWAY FACILITY
 
7.864 5365641.48 1637626.71 2410923.21 44.9
Work Order 03-11-15
Work Began 07-20-15
Work Completed  
Time Computed 07-20-15
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 72
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0761-01-019
BARRICADES UNLIMITED (1.61%)
WILLIS ELECTRIC CO., LP(1.02%)
Contract # 01153030
Totals 9104218.97 2414567.86 4448007.71 48.8

CountyWHEELER
Highway FM 592
From @ SWEETWATER CREEK
To .
CSJ 0761-05-013
Proj ID BR 2016(155)
Work Type REPLACEMENT OF EXISTING BRIDGE
 
0.099 2138189.00 0.00 320168.11 14.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-15
Work Began 03-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 7
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0761-05-013
PENHALL COMPANY (AUSTIN) (0.23%)
LANCO TURF & SEEDING, INC. (0.58%)
BARRICADES UNLIMITED (1.37%)
Contract # 10153003
Totals 2138189.00 0.00 320168.11 14.9

CountyCOLLINGSWORTH
Highway FM 1547
From @ BIG SANDY CREEK
To .
CSJ 0797-07-030
Proj ID BR 2016(687)
Work Type BRIDGE REPLACEMENT
 
0.080 884874.00 0.00 0.00 0.0
CountyCOLLINGSWORTH
Highway CR
From @ ELM CREEK
To .
CSJ 0925-13-017
Proj ID BR 2016(688)
Work Type BRIDGE REPLACEMENT
 
0.100 299810.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0797-07-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163025
Totals 1184684.00 0.00 0.00 0.0

CountyCOLLINGSWORTH
Highway FM 1547
From 3.72 MILES N OF HALL C/L, N
To 1.5 MILES S OF FM 1056
CSJ 0844-04-009
Proj ID STP 1502(379)HES
Work Type WIDENING OF A NON - FREEWAY FACILITY
 
7.970 6114806.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-31-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 179
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0844-04-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153234
Totals 6114806.40 0.00 0.00 0.0

CountyHALL
Highway FM 1547
From US 287
To 0.23 MILES EAST OF US 287
CSJ 0844-05-008
Proj ID STP 1402(008)RGS
Work Type CONSTRUCT RR GRADE SEPARATION STR
 
0.438 5436253.20 178647.37 5030841.98 92.5
Work Order 09-15-14
Work Began 01-05-15
Work Completed  
Time Computed 01-05-15
Contract Working Days 247
Addl Days Granted 5
Working Days Charged 239
Percent Time Used 94
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0844-05-008
ACU CONSTRUCTION LLC (0.30%)
BARRICADES UNLIMITED (0.84%)
LANCO TURF & SEEDING, INC. (0.13%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.77%)
MCL CONTRACTING, LLC (1.49%)
PENHALL COMPANY(0.10%)
WILLIS ELECTRIC CO., LP(1.56%)
MCL CONTRACTING, LLC (0.29%)
Contract # 07143048
Totals 5436253.20 178647.37 5030841.98 92.5

CountyCHILDRESS
Highway VA
From DISTRICT WIDE
To .
CSJ 0925-00-062
Proj ID STP 2015(324)
Work Type DISTRICT WIDE CRACK SEAL
 
564.270 766449.54 0.00 118151.46 15.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-10-14
Work Began 03-23-15
Work Completed  
Time Computed 11-26-14
Contract Working Days 46
Addl Days Granted 6
Working Days Charged 52
Percent Time Used 100
Contractor(s)
TEXAS ROAD MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-062
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143224
Totals 766449.54 0.00 118151.46 15.4

page 1 | page 2